Planning Case Comments
DATE: 9/30/2022
CASE: PA 2021-19
Rome Hill Commercial
2nd Review
APN 371-150-001, -002
PLANNER: Mathew Evans, Principal Planner
REVIEWED BY: Steve Payne, Assistant Fire Marshal
The Fire Department has reviewed this submittal and provides the following comments.
The applicant or developer shall provide fire hydrants in accordance with the following:
Prior to placing any combustibles on site, provide an approved water source for firefighting purposes.
Prior to building permit issuance, submit plans to the water district for a water system capable of delivering fire flow as required by the California Fire Code and Fire Department standards.
Fire hydrants shall be spaced in accordance with the California Fire Code. Hydrants must produce the required fire flow per the California Fire Code.
Required fire flow is estimated to be 2,125 GPM at 20 PSI for a 2-hour duration based on 2019 California Fire Code and 41,296 square foot building area with Type II-B construction.
Prior to building permit issuance, install the approved water system, approved access roads, and contact the Fire Department for a verification inspection.
Gates must meet Fire Department standards at the time of building permit application. Current standards require that gates have a Knox rapid entry system, an infrared gate opener, and
be set back up to 35 feet allow emergency vehicles to safely stop away from traffic flow.
If the project is to be developed in phases, each phase of development must meet applicable standards prior to occupancy.
These comments are preliminary; further review will occur upon receiving building plans. Additional conditions may be necessary at that time.
Please feel free to contact me with any questions.