HomeMy WebLinkAboutPA 2023-103 LOI #2 (Amended)
VIA MAIL: heather@epdsolutions.com
April 15, 2024
Riverside Legacy IV Nichols Road, LLC
Attn: Heath Rushing
5550 Newbury Street, Suite B
Baltimore, MD 21209
RE: Planning Application No. 2020-103, Baker Street Industrial
Dear Heath Rushing;
We have completed an initial review of the above-mentioned application you submitted requesting the
following entitlements: Zone Change (ZC-2023-04) to change a portion of the project site currently
Limited Manufacturing (M-1) to General Manufacturing (M-2); a Tentative Parcel Map (TPM 38812) to
subdivide the approximately 65.81-acre site into three (3) parcels ranging in size from 10.41 acres to
43.73 acres and two (2) lettered lots for right-of-way purposes; Industrial Design Review (IDR-2023-03)
to construct two (2) warehouse/logistics buildings totaling 1,000,451 sq. ft.; and a Conditional Use Permit
(CUP-2023-10) to establish warehouse/logistics. The project site is located at the southeast corner of
Pierce Street and Baker Street. (APNs: 378-020-014, 015, 016, 028, 029, 030, 031, 036, 037, and 048).
This letter is our determination that your application referenced above is INCOMPLETE in accordance
with Government Code Section 65920 (Permit Streamlining Act). Furthermore, this letter specifies the
incomplete parts of your application and provides you with the requirements to complete your application.
You must address all items included in the attachment(s) for our division to continue processing the
application and to begin environmental evaluation of the proposed project pursuant to the California
Environmental Quality Act (CEQA).
In response to this letter, please resubmit all application materials, including all required fees, plans, and
supporting exhibits. For further instructions, forms, and information, visit www.lake-elsinore.org.
If you have questions about this letter, please contact me at (951) 674-3124 ext. 273 or jmendoza@lake-
elsinore.org.
Joey Mendoza
Associate Planner, City of Lake Elsinore
CC: EPD Solutions
Attn: Heather Roberts
3333 Michelson Drive, Suite 500
Irvine, CA 92612
PA 2023-103 (Baker St. Industrial) DRC #2 LOI
04/15/2024
Page 2 of 5
GENERAL PLAN AND ZONING CLASSIFICATION DEVELOPMENT STANDARDS
1. The current General Plan Land Use Designation for the project site is Limited Industrial (LI). The LI
designation provides for industrial parks, warehouses, manufacturing, research and development,
public and quasi-public uses, and similar and compatible uses. The Floor Area Ratio (FAR) shall not
exceed 0.45.
2. The proposed project shall comply with the following development standards as outlined in the M-2
zone:
Development Standard Required
Minimum net lot area One (1) acre net
Street frontage width 100 �.
Front Setback Min. 15 �. Average 20 �.
Side Yard (ROW) Min. 15 �. Average 20 �.
Building Height 45 �.
Landscape improvement
Adjacent to Street Min. 15 �. Average 20 �.
Landscape Coverage 12%
3. Public outreach is strongly encouraged.
a. The applicant has submitted a Public Outreach Plan for Planning records. Outreach will increase
once a final design is agreed upon.
PLANNING DIVISION COMMENTS
4. Good Neighbor Policy Site and Design Compliance
The project includes a warehouse exceeding 250,000 sq. ft. in size. It is, therefore, subject to
Council Policy No. 400-16, “Good Neighbor Policy” for Warehousing, Logistics, and Distribution
Uses (GNP), adopted by the City Council on April 25, 2023. Review of the latest proposed Site
Plan shows tentative compliance with the GNP. Final GNP compliance will be determined upon
final and deemed complete application.
Siting and Design:
o 1. Sensitive Receptor Setback Requirement
The GNP-eligible building’s (Building 2) setback is over 475’-0” from the closest
parcel line of the nearest sensitive receptor.
At the time of this letter’s creation, the subject sensitive receptor is non-
conforming for its zoning classification, and as such, is being sold as a
manufacturing site.
If the property is purchased for its nonconforming use as a residence, the
applicant has provided dense landscape screening between Building 1 and the
subject sensitive receptor.
The applicant completed the required PAR requirement for the project prior to
formally applying for an entitlement.
o 2. Parking and Queueing Requirement
A stu dy was prepared, as required by LEMC Ch. 14.148.030.D and the
applicant is currently working with the City to finalize a parking requirement.
The applicant has implemented the queueing requirement by designing the site
to facilitate multiple on-site queues and paths of travel for trucks to access
PA 2023-103 (Baker St. Industrial) DRC #2 LOI
04/15/2024
Page 3 of 5
alternative access routes around the site to prevent stacking or queueing off-
site into the public right-of-way.
o 3. Entry Gates Setback and On-site Queueing Requirement
The applicant has proposed a site design with entry gates setback further than
the 140’ required by the GNP.
The applicant has included double truck stacking lanes for the GNP eligible
building.
o 4. Landscaping, Screening, and Fuel Plan
Though the applicant has submitted preliminary landscaping plans which
satisfy the 15’ requirement and tree size requirement, the Fuel Plan and Fire
Mitigation Plan are pending Fire Marshal approval.
To be updated upon subsequent submittal.
o 5. Building Planes Visible from Public View
The applicant has worked with the Planning Division to enhance the aesthetics
of the building elevations.
The applicant will meet with the Planning Division to enhance the appearance
of the screening wall along Baker on a future date.
The applicant will provide line of sight cross-sections for review.
o Items 6 through 13 of the GNP are not subject to review at this stage and may be
included in the Conditions of Approval for the project prior to Public Hearings.
5. MSHCP/LEAP Compliance
The project is located within Western Riverside Multiple Species Habitat Conservation Plan
(MSHCP) Criteria Cell # 4166. Prior to entitlement approval, a completed and approved LEAP
application and map must be provided.
An application for MSHCP Consistency Determination (LEAP) and the required fee is currently
under review.
6. Site Plan
A fully dimensioned site plan drawn to a legible scale showing the number and dimensions for all
parking stalls, drive aisles, and all structures, including walls, shall be included with the revised
submittal.
The 45’ (approx.) wall along the rear property line for both buildings is reflected on the grading
plan but not clearly shown on the site plan. A fully dimensioned wall detail is required.
A determination regarding the undergrounding or relocation of existing power poles must be
reached with Engineering and SCE prior to entitlement approval.
A site plan approved by SCE is required showing that the parking, landscaping, and drive aisles
under the easement are allowed in the configuration and location shown.
The plans show five gated truck ingress/egress areas, stacking, and parking. Provide a detail
drawn to a scale of 1:50 or another legible scale for these areas to show the guard shack, the
gate mechanism, stacking, and turn movements with a truck turning template.
The site plan shows a third building, “Building 3,” in the Project Data sheet, though no third building
is proposed in the project description or on the plans. Please amend the Project Data sheet to
reflect the correct project scope.
PA 2023-103 (Baker St. Industrial) DRC #2 LOI
04/15/2024
Page 4 of 5
Parcel 3 proposes a stand-alone parking lot for trailers. LEMC §17.140.020 and §17.136020 do
not list stand-alone parking lots as allowable uses within the M-1 and M-2 zones. The parcel must
either be merged into Parcel 2, or a new permitted use must be proposed within the parcel.
o If a permitted use is found and Parcel 3 is to remain intact, it must meet the minimum street
frontage width requirement of 100 ft. for any new lot created in the M-2 district, per LEMC
§17.140.060. The Site Plan must also be modified to reflect how this will be achieved.
A tenant must be identified prior to the issuance of a certificate of occupancy for Buildings 1 and
2 to ensure that the type of tenant and their operations do not modify the air, traffic, GHG, and
noise impacts.
7. Cross Sections
The height of the parapet on the cross sections must be fully dimensioned to show that all rooftop
equipment will be fully screened from the public right of way.
Areciprocal ingress and egress and parking agreements shall be prepared and recorded to allow
access between parcels.
The applicant shall meet with the Planning Division to review and finalize a design for the
screening walls to ensure greater general aesthetic value.
o The applicant shall update the Project Description to include the screening wall height as
part of the approval request.
Cross sections must be fully dimensioned and include human scale from the public right of way
to the rear property line.
8. Floor Plan
If the proposed buildings are speculative, the floor plan must show the location of the mezzanine
and office space with a maximum “not to exceed” square footage so that parking can be correctly
calculated.
9. Application Information
Technical studies and the EIR document are required. Ensure the technical studies are based on
the site plan and incorporate the comments provided.
A narrative justifying the height increases for the buildings and screening walls must be submitted,
showing that the required finding for a CUP can be made positively.
The parking study is required to justify the reduced number of spaces shown on the plan. Please
note that preparing and submitting a parking study does not guarantee a reduction in the required
spaces.
o The applicant has submitted a parking study, and comments are forthcoming.
10. Elevations
Show the location of the lighting of the building.
Show the dimensions for the variance in height along the roof line and a wall cross-section with
the depth dimensions of the pop-outs.
The parapet shall have a definitive cap as opposed to metal flashing.
PA 2023-103 (Baker St. Industrial) DRC #2 LOI
04/15/2024
Page 5 of 5
Add architectural detail to the west elevation to enhance the building corner visible from Nichols
and Baker.
The screen wall and equipment line of sight shall be drawn at a scale of 1:50 and fully
dimensioned.
For preciseness, elevation labels shall be revised to demonstrate correct cardinal orientation.
Photo simulations should be revised to include location and street name identification and to
clearly show the project's relation to the surrounding neighborhood. The preliminary grading plan
shows that there will be a significant grade difference between the project site and the adjacent
properties. As previously requested, the line of sight/view simulation should also include views for
areas impacted by site grading.
A fiscal impact analysis should be prepared for City review.
o The applicant has submitted a fiscal impact analysis. This comment will be removed when
an analysis is approved.
The project must conclude the required Assembly Bill No. 52 (AB 52) Tribal Consultations.
o The Planning Division is currently undertaking the consultation process. This comment will
be removed when all consultations are concluded.
11. Interagency Comments
a. Comments from the following City Departments regarding this project are attached to this
letter:
i. Engineering Department
ii. Fire Prevention Department
b. Please direct specific questions to the following DRC members as applicable:
i. Fire: Traci Williams, Ext. 228 or twilliams@lake-elsinore.org
ii. Building & Safety: Bill Belvin, Ext. 286 or bbelvin@lake-elsinore.org
iii. Engineering: Paul Fizer, Ext. 804 or pfizer@lake-elsinore.org
ENGINEERING DEPARTMENT
PA 2021-35
(PAR 2021-05)
Baker Industrial APN 378-020-014, -015, -016, -028, -029, -030, -031, -036, -037, -
048
DRC Date: April 4, 2024
COMMENTS #2:
1. Project is required to submit a revised WQMP in the next DRC submittal as it was not included in
the current DRC package. Revisions to the WQMP were requested in the last engineering comment
set.
2. Parcel 1 is required to give access to Parcel 2 and 3 for ingress/egress for emergency purposes.
Will this be included on the proposed TPM or per separate instrument?
3. Project is required to provide an NIL from Southern California Edison to the City of Lake Elsinore
for the large easement that is crossing the property as well as the smaller easements of 10’
(temporary) and 20’ along the frontage.
a. It is recommended that this process is started as early as possible.
4. On Sheet 2 of 6 of the conceptual grading plan include the dedication notes for the typical note
cross sections (I.e. Baker Street, Pierce Street, Section G-G).
5. Has the Riverside County Flood Control been approached to maintain the stormwater pipes over
36” in diameter? It is not typical for the City to maintain drainage pipes over the size of 36” as it is
depicted in the Maintenance Plan.
6. Storm drain easements were not noted on the tentative map. Are storm drain easements to be
provided per a separate instrument?
7. Project is required to construct ultimate roadway improvements for Pierce Street connecting up to
the existing portion of Hoff Avenue for secondary access.
8. How will the roadway along Pierce Street be treated/considered in the WQMP? Based on the
grading plans, there is no proposed treatment.
9. There are minor comments provided for the Hydraulic Analysis section of the Hydrology Report,
which be found be here: PA-2020-103 (SUB #2) - HYDRO_ ENG REDLINES.pdf
10. Preliminary hydraulic analysis for the desilting basin should be included as a part of this report as
it will ultimately affect the site plan.
11. Traffic scoping and parking analysis comments will be provided at a later time.
12. There are minor revisions required for the Tentative Parcel Map which can be located here: PA-
2020-103 (SUB #2) - TPM_ ENG REDLINES.pdf
13. Additional comments will follow upon further information provided.
Planning Case Comments
April 8, 2024
CASE: PA 2020-103
TPM 2023-04 and CUP 2023-10
Baker Street Industrial
PLANNER: Joey Mendoza, Associate Planner
REVIEWED BY: Traci Williams, Fire Marshal
The Fire Department has reviewed this submittal and provides the
following comments for the applicant’s consideration.
1. This project is in a Very High Fire Hazard Severity Zone of
Riverside County as shown on a map on file with the Clerk of the
Board of Supervisors. Any building constructed within this project
shall comply with special construction provisions contained in the
California Building Code and the California Fire Code.
2. Unless otherwise approved by the Lake Elsinore OFM, dead end
fire apparatus access roads shall not exceed:
• For Very High Fire Hazard Severity Zone and High Fire
Hazard Severity Zone areas – 660 feet
• For Moderate Fire Hazard Severity Zone areas – 800 feet
• For all other areas – 1320 feet
Secondary egress/access fire apparatus access roads shall
provide independent egress/access from/to the area or as
otherwise approved by the OFM. Secondary egress/access fire
apparatus access roads shall be as remote as practical from the
primary fire apparatus access road to reduce the possibility that
both routes will be obstructed by a single emergency.
In Cooperation With
The California Department of Forestry and Fire Protection
130 South Main Street, Lake Elsinore, CA 92530 • Phone (951) 674-3124
www.rvcfire.org
Proudly serving the
unincorporated areas
of riverside county
and the cities of:
Banning
Beaumont
Coachella
Desert Hot Springs
Eastvale
Indian Wells
Indio
Jurupa Valley
Lake Elsinore
La Quinta
Menifee
Moreno Valley
Norco
Palm Desert
Perris
Rancho Mirage
Rubidoux CSD
San Jacinto
Temecula
Wildomar
BOARD OF
SUPERVISORS:
Kevin Jeffries
District 1
Karen Spiegel
District 2
CHARLES WASHINGTON
District 3
V. Manual Perez
District 4
Dr. Yxstian Gutierrez
District 5
Additional fire apparatus access roads based on the potential for
impairment by vehicle congestion, condition of terrain, climatic
conditions, anticipated magnitude of a potential incident, or other
factors that could limit access may be required by the Fire
Marshal. (CFC 503.1.2)
3. The applicant or developer must submit a high fire mitigation plan
and report to the Fire Department, prior to map approval.
(*Provided with 3/2024 submittal)
4. The applicant or developer shall provide fire hydrants in
accordance with the following:
a. Prior to placing any combustibles on site, provide an
approved water source for firefighting purposes.
b. Prior to building permit issuance, submit plans to the water
district for a water system capable of delivering fire flow as
required by the California Fire Code and Fire Department
standards. Fire hydrants shall be spaced in accordance
with the California Fire Code. Hydrants must produce the
required fire flow per the California Fire Code.
c. Fire flow shall be determined by the building of the single
largest square footage. The required fire flow is estimated to
be 4,000 GPM at 20 PSI for a 4-hour duration, per the 2022
California Fire Code and 778,423 square foot building area
with Type III-B construction.
5. In all new buildings and structures which are 5,000 square feet or
greater, an approved automatic sprinkler system shall be provided
regardless of occupancy classification. Where Sections 903.2.1 –
903.2.21 of the California Fire Code have more restrictive
requirements than those listed below, the more restrictive
requirement shall take precedence.
6. Prior to building permit issuance, install the approved water system
and contact the Fire Department for a verification inspection.
7. The applicant must provide a fire command center for buildings
larger than 300,000 square feet in area in accordance with
California Fire Code 508, Lake Elsinore Municipal Code Section
15.56 and fire department standards.
8. The applicant will need to evaluate the need for emergency
responder radio coverage inside the building in accordance with
California Fire Code Section 510. Prior to building plan review, the
applicant is encouraged to contact the Riverside County Fire
Department for radio requirements.
9. Roads and gates must meet Engineering Department and Fire
Department standards at the time of building permit application.
Current standards require that dead-end roads do not exceed 600
feet in length. Electric gates must have a Knox rapid entry system
and an infrared opening device. Gates must be set back up to 35
feet allow emergency vehicles to safely stop away from traffic flow.
10. Prior to issuance of Building Permits, the applicant/developer shall
provide the Office of the Fire Marshal with an approved site plan for
Fire Lanes and signage. (CFC 501.3)
11. If the project is to be completed in phases, a formal phasing map or
phasing plan shall be submitted. Primary access and secondary
access (where necessary) for each parcel shall be provided at each
phase.
12. Fire apparatus access roads shall have an unobstructed width of
not less than twenty–four (24) feet as approved by the Office of the
Fire Marshal. The outside turning radius shall be a minimum of 38’,
excluding parking. If street parking is to be proposed, the
additional width shall be coordinated with the Engineering
department to accommodate the necessary added street width.
13. The Fire Apparatus Access Road shall be of all-weather surface and
capable of sustaining an imposed load of 85,000 lbs. GVW. The fire
apparatus access road or temporary access road shall be reviewed
and approved by the Office of the Fire Marshal and in place during
the time of construction. (CFC 501.4)
14. Roads and gates must meet Engineering Department and Fire
Department standards at the time of building permit application.
Current standards require that dead-end roads do not exceed
1320 feet in length. Electric gates must have a Knox rapid entry
system and an infrared opening device. Gates must be set back
up to 35 feet to allow emergency vehicles to safely stop away from
traffic flow.
15. The proposed project is expected to have a cumulative adverse
impact on the fire department’s ability to provide an acceptable level
of service. These impacts include an increased number of
emergency and public service calls due to the increased presence
of structures, traffic, and population.
These comments are preliminary; further review will occur upon
receiving additional plans. Additional requirements may be necessary
at that time. Please feel free to contact me with any questions.