VIA MAIL: heather@epdsolutions.com
March 15, 2024
Riverside Legacy IV Nichols Road, LLC
Attn: Heath Rushing
5550 Newbury Street, Suite B
Baltimore, MD 21209
RE: Planning Application No. 2020-103, Baker Street Industrial
Dear Heath Rushing;
We have completed a second review of the above-mentioned application you submitted requesting the
following entitlements: Zone Change (ZC-2023-04) to change a portion of the project site currently
Limited Manufacturing (M-1) to General Manufacturing (M -2); a Tentative Parcel Map (TPM 38812) to
subdivide the approximately 65.81-acre site into three (3) parcels ranging in size from 10.41 acres to
43.73 acres and two (2) lettered lots for right -of-way purposes; Industrial Design Review (IDR-2023-03)
to construct two (2) warehouse/logistics buildings totaling 1,000,451 sq. ft.; and a Conditional Use Permit
(CUP-2023-10) to establish warehouse/logistics. The project site is located at the southeast corner of
Pierce Street and Baker Street. (APNs: 378-020-014, 015, 016, 028, 029, 030, 031, 036, 037, and 048).
This letter is our determination that your application referenced above is INCOMPLETE in accordance
with Government Code Section 65920 (Permit Streamlining Act). Furthermore, this letter specifies the
incomplete parts of your application and provides you with the requirements to complete your application.
You must address all items included in the attachment(s) for our division to continue processing the
application and to begin environmental evaluation of the proposed project pursuant to the California
Environmental Quality Act (CEQA).
In response to this letter, please resubmit all application materials, including all required fees, plans, and
supporting exhibits. For further instructions, forms, and information, visit www.lake-elsinore.org.
If you have questions about this letter, please contact me at (951) 674-3124 ext. 273 or jmendoza@lake-
elsinore.org.
Joey Mendoza
Associate Planner, City of Lake Elsinore
CC: EPD Solutions
Attn: Heather Roberts
3333 Michelson Drive, Suite 500
Irvine, CA 92612
PA-2023-103 (Baker St. Industrial) DRC #2 LOI
03/15/2024
Page 2 of 4
PLANNING DIVISION COMMENTS
1. The current General Plan Land Use Designation for the project site is Limited Industrial (LI). The LI
designation provides for industrial parks, warehouses, manufacturing, research and development,
public and quasi-public uses, and similar and compatible uses. The Floor Area Ratio (FAR) shall not
exceed 0.45.
2. The proposed project shall comply with the following development standards as outlined in the M-2
zone:
Development Standard Required
Minimum net lot area One (1) acre net
Street frontage width 100 ft.
Front Setback Min. 15 ft. Average 20 ft.
Side Yard (ROW) Min. 15 ft. Average 20 ft.
Building Height 45 ft.
Landscape improvement
Adjacent to Street Min. 15 ft. Average 20 ft.
Landscape Coverage 12%
3. The project is located within a Western Riverside Multiple Species Habitat Conservation Plan
(MSHCP) Criteria Cell # 4166. A completed and approved Lake Elsinore Acquisition Program (LEAP)
application and map must be provided prior to entitlement approval.
4. Site Plan
▪ The revised submittal shall include a fully dimensioned site plan drawn to a legible scale showing
the number and dimensions for all parking stalls, drive aisles, and all structures, including walls.
▪ The 45’ (approx.) wall along the rear property line for both buildings is reflected on the grading
plan but not clearly shown on the site plan. A fully dimensioned wall detail is required .
▪ The utility poles must be undergrounded for new development, per LEMC 16.64 -
Improvements. Revise the site plan to show the poles and note that they will be placed
underground prior to occupancy.
▪ A site plan approved by SCE is required showing that the parking, landscaping , and drive aisles
under the easement are allowed in the configuration and location shown.
▪ The proximity between the two drive approaches on Baker Street for Buildings 1 and 2 will cause
safety, circulation, and stacking issues. Revise the site plan to show one shared drive approach
for Buildings 1 and 2.
▪ Building 2 orientation should be modified to “hide” the trailer parking and dock doors behind the
building facing the south property line.
▪ The plans show five gated truck ingress/egress areas, stacking, and parking. Provide a detail
drawn to a scale of 1:50 or another legible scale for these areas to show the guard shack, the
gate mechanism, stacking, and turn movements with a truck turning template.
▪ The site plan shows a third building in the project data sheet , presumably to be constructed on
Parcel 3 at a later date. If a third building is planned, the full development must be considered in
the CEQA EIR analysis to avoid “piecemealing.”
PA-2023-103 (Baker St. Industrial) DRC #2 LOI
03/15/2024
Page 3 of 4
▪ Parcel 3 must meet the minimum street frontage width requirement of 100 feet for any new lot
created in the M-2 district, per LEMC 17.140.060. The Site plan must demonstrate how this
requirement will be met.
▪ A tenant must be identified prior to the issuance of a certificate of occupancy for Buildings 1 and
2 to ensure that the type of tenant and their operations do not modify the air, traffic, GHG, and
noise impacts.
5. Cross Sections
▪ The height of the parapet on the cross sections must be fully dimensioned to show that all roof top
equipment will be fully screened from the public right of way.
▪ A reciprocal ingress and egress and parking agreement shall be prepared and recorded to allow
access between parcels.
▪ The height of the walls must be fully dimensioned.
▪ Cross sections must be fully dimensioned and include human scale and from the public right of
way to the rear property line.
6. Floor Plan
▪ The dimensions and location of the mezzanine and office space must be shown on the floor
plans. If the buildings are speculative, the floor plan must show the location of the mezzanine
and office space with a maximum “not to exceed” square footage so that the parking can be
calculated.
7. Application Information
▪ The technical studies and the EIR document are required. Please ensure that the technical
studies are based on the site plan that incorporates the comments provided.
▪ A narrative to justify the height increase must be submitted showing that the required finding for
a CUP can be made in a positive manner.
▪ The parking study is required to justify the reduced number of spaces shown the plan and a copy
must be submitted to the planning Division as well as the Engineering Division for review. Please
note that, preparation and submittal of a parking study does not guarantee a reduction in the
required spaces.
8. Elevations
▪ Show the location of the lighting of the building
▪ Show the dimensions for the variance in height along the roof line and a wall cross -section with
the dimensions of the pop-out's depth.
▪ The parapet shall have a definitive cap as opposed to a metal flashing.
▪ Add glazing or other architectural detail to the west elevation to enhance the building corner visible
from Nichols and Baker.
▪ The screen wall and equipment line of sight shall be drawn at a scale of 1:50 and fully
dimensioned.
▪ Building 2 dock doors are on the north/northeast elevation as oppose d to the east. The elevations
should be revised to clarify the orientation.
PA-2023-103 (Baker St. Industrial) DRC #2 LOI
03/15/2024
Page 4 of 4
9. The photo simulations should be revised to include location and street name identification and to
clearly show the project in relation to the surrounding neighborhood. The preliminary grading plan
shows that there will be significant grade difference between the project site and the adjacent
properties. As previously requested, t he light of sight/view simulation should also include views for
areas impacted by the grading.
10. A fiscal impact analysis should be prepared for City review.
11. Public outreach is strongly encouraged. A public outreach plan should be submitted for department
review.
12. The project must conclude required Assembly Bill No. 52 (SB52) Tribal Consultations .
13. Pending Comments
a. Comments from the following City Departments regarding this project are attached to this
letter:
i. Engineering Department
ii. Fire Prevention