HomeMy WebLinkAboutItem No. 19 - Energy Efficiency-light Emitting Diode (LED) Fixture Replacement Agreement with19)Energy Efficiency-light Emitting Diode (LED) Fixture Replacement Agreement with
Southern California Edison (SCE)
Approve and authorize the City Manager to execute an Agreement with SCE to convert
SCE owned fixtures in the City of Lake Elsinore to LED fixtures in such final form as
approved by the City Attorney.
Page 1 of 2
REPORT TO CITY COUNCIL
To:Honorable Mayor and Members of the City Council
From:Jason Simpson, City Manager
Prepared by:Remon Habib, City Engineer
Date:May 27, 2025
Subject:Energy Efficiency-light Emitting Diode (LED) Fixture Replacement
Agreement with Southern California Edison (SCE)
Recommendation
Approve and authorize the City Manager to execute an Agreement with SCE to convert SCE
owned fixtures in the City of Lake Elsinore to LED fixtures in such final form as approved by the
City Attorney.
Background
SCE approached the City regarding the conversion of SCE owned fixtures throughout the City to
high efficiency LED fixtures. SCE will manage the project, provide the LED fixtures at no cost to
the City.
Discussion
SCE estimates about 742 street light fixtures throughout the City that are still owned by Southern
California Edison. SCE proposes to change the aging low efficiency fixtures with LED
replacement. The new fixtures are reliable, dark sky compliant, and are robust in all weather
conditions. Life expectancy of the new fixtures is anticipated to be 12 to 20 years. Installation is
anticipated to begin within seven months of executing the agreement. The 20 year savings outlook
is estimated to be $41,240 yearly per SCE’s estimate.
Fiscal Impact
According to SCE’s estimates, the fiscal impact on the City is an annual savings of $41,240 over
a 20-year period.
LED Fixture Replacement Agreement
Page 2 of 2
Attachments
Attachment 1- LED Fixture Replacement Agreement
Engineering
Southern California Edison Original Cal. PUC Sheet No. 57074-E
Rosemead, California (U 338-E) Cancelling Cal. PUC Sheet No.
Sheet 1
SCHEDULE LS-1 OPTION E,
ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED) FIXTURE REPLACEMENT
RATE AGREEMENT
Form 14-965
(To be inserted by utility) Issued by (To be inserted by Cal. PUC)
Advice 3241-E R.O. Nichols Date Filed Jun 30, 2015
Decision 14-10-046 Senior Vice President Effective Jun 1, 2016
1P8 Resolution
SOUTHERN CALIFORNIA EDISON COMPANY
SCHEDULE LS-1 OPTION E, ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED)
FIXTURE REPLACEMENT RATE AGREEMENT
Form 14-965
06/2016
1
This Schedule LS-1 Option E, Energy Efficiency-Light Emitting Diode (LED) Fixture Replacement Rate
Agreement (Agreement), effective this day of _,
_(Effective Date), is entered into between Southern California Edison Company (SCE)
and ________, an SCE customer taking service on Schedule LS-1 (Applicant), referred to
collectively as "Parties," and individually as "Party." This Agreement provides for SCE, at Applicant’s
request, to replace the existing street lighting fixtures serving Applicant’s premises with Light Emitting
Diode (LED) street lighting fixtures to achieve energy efficiency benefits for Applicant, as set forth in
Special Condition 14, Option E, Energy Efficiency-Light Emitting Diode (LED) Fixture Replacement, of
Schedule LS-1.
The Parties agree as follows:
1. LED FIXTURES
SCE shall install, own, operate, and maintain LED Fixtures for Applicant as set forth in Exhibit "A"
attached hereto and incorporated herein by this reference. The LED Fixtures provided hereunder
shall at all times remain the property of SCE.
2. LED FIXTURE REPLACEMENT COSTS
2.1 The replacement costs of the LED Fixtures provided hereunder shall be borne by
Applicant.
2.2 Applicant shall pay the charge for the LED Fixtures Replacement rate, which includes an
Energy Efficiency Premium Charge (EEPC) and a Base LED Charge, under Option E of
Schedule LS-1. Applicant elects Option E in lieu of an upfront, one-time payment of the
replacement costs.
2.3 SCE does not guarantee that any energy or bill savings will accrue to Applicant as a result
of the LED Fixture replacements.
3. COMMENCEMENT OF SERVICE
The Parties agree that SCE has the right to charge Applicant, and Applicant has an obligation to
pay SCE, for the charges set forth in Schedule LS-1, Option E, commencing on the date SCE
begins serving the LED Fixtures installed pursuant to this Agreement.
4. TERM AND TERMINATION
4.1 This Agreement shall be effective as of the Effective Date and shall continue for a term of
twenty (20) years from the commencement of service as specified in Section 3 above
(Term).
4.2 Applicant may terminate this Agreement at any time during the Term upon a thirty (30) -
day advance written notice, provided that Applicant, prior to or within the 30-day advance
notice period, assigns the Agreement to any New Party In (NPI) that owns, rents or
leases the premises served by the street lighting fixtures replaced under this Agreement
and will take service under Option E of Schedule LS-1 effective as of the date of termination;
otherwise, Applicant shall pay a one-time termination charge equal to the present value of
the balance of the EEPC of Option E over the remaining Term. The present value is
determined based on SCE’s authorized rate of return on rate base, or discounted rate of
7.90%.
SOUTHERN CALIFORNIA EDISON COMPANY
SCHEDULE LS-1 OPTION E, ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED)
FIXTURE REPLACEMENT RATE AGREEMENT
Form 14-965
06/2016
2
5. AMENDMENTS; ASSIGNMENTS
5.1 Any changes or amendments to this Agreement must be in writing and must be executed
by the Applicant and SCE and, if required, be approved by the California Public Utilities
Commission (Commission).
5.2 Applicant shall not assign this Agreement without the prior written consent of SCE;
provided, however, that Applicant may assign the Agreement pursuant to the terms and
conditions of Section 4.2 above, and the NPI must assume all rights and obligations
under this Agreement for the remaining Term. Any assignment and assumption shall be in
a form acceptable to SCE.
6. NOTICE
Any notice either Applicant or SCE may wish to provide the other regarding this Agreement must
be in writing. Such notice must be either hand-delivered or sent by U.S. certified or registered
mail, postage prepaid, to the person designated to receive notice for the other Party below, or to
such other address as either may designate by written notice. Notices delivered by hand shall be
deemed effective when delivered. Notices delivered by mail shall be deemed effective when
received, as acknowledged by the receipt of the certified or registered mailing.
Applicant: SCE:
(Name)
Business Customer Division
(Title) Southern California Edison Company
2244 Walnut Grove Avenue
(Address) Rosemead, CA 91770
(City, State, Zip)
7. NONWAIVER
The failure of either Party to enforce any of the terms and conditions or to exercise any right or
privilege in this Agreement shall not be construed as a waiver of any such term and conditions or
rights or privileges, and the same shall continue and remain enforce and effect as if no such
failure to enforce or exercise had occurred.
8. SEVERABILITY
In the event that any of the provisions, or portions thereof, of this Agreement are held to be
unenforceable or invalid by the Commission, or any court of competent jurisdiction, the validity
and enforceability of the remaining provisions or any portion thereof shall not be affected.
9. APPLICABLE LAWS, RULES, AND REGULATIONS
This Agreement shall be subject to, and interpreted under the laws, rules, decisions and regulations
of the State of California, without regard to its conflict of laws principles, the Commission, and SCE's
Commission-approved tariffs.
SOUTHERN CALIFORNIA EDISON COMPANY
SCHEDULE LS-1 OPTION E, ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED)
FIXTURE REPLACEMENT RATE AGREEMENT
Form 14-965
06/2016
3
10. CALIFORNIA PUBLIC UTILITIES COMMISSION JURISDICTION
10.1 This is a filed form tariff agreement authorized by the Commission for use by SCE. No
officer, inspector, solicitor, agent or employee of SCE has any authority to waive, alter, or
amend any part of this Agreement except as provided herein or authorized by the
Commission. This Agreement is to be used in conjunction with Schedule LS-1 and
supplements the terms and conditions of the Applicant's electric service under Schedule
LS-1.
10.2 This Agreement shall at all times be subject to such changes or modifications by the
Commission as said Commission may, from time to time, direct in the exercise of its
jurisdiction.
10.3 Notwithstanding any other provisions of this Agreement, SCE has the right to unilaterally
file with the Commission, pursuant to the Commission's rules and regulations, an
application for change in rates, charges, classification, service, or rule or any agreement
relating thereto.
11. ENTIRE AGREEMENT
This Agreement, including SCE’s Commission-approved tariffs, constitutes the complete agreement
and understanding between the Applicant and SCE regarding the LED Fixtures replacement costs.
Prior agreements, representations, understandings, whether expressed or implied, and
communications, oral or written, between the Applicant and SCE shall not be construed to be a part
of this Agreement.
12. AUTHORIZATION SIGNATURE
In witness whereof, the Parties hereto have caused this Agreement to be signed by their duly
authorized representatives.
APPLICANT
BY:
NAME:
TITLE:
DATE SIGNED:
SOUTHERN CALIFORNIA EDISON COMPANY
BY:
NAME:
TITLE:
DATE SIGNED:
Form 14-965
06/2016
4
SOUTHERN CALIFORNIA EDISON COMPANY
EXHIBIT “A”
SCHEDULE LS-1 OPTION E,
ENERGY EFFICIENCY-LIGHT EMITTING DIODE (LED) FIXTURE REPLACEMENT
APPLICANT
CUSTOMER ACCOUNT NO.
SERVICE ACCOUNT NO.
(Additional account numbers/addresses may be attached hereto.)
SERVICE ADDRESS
APPLICANT REQUESTED READY TO SERVE DATE
ASAP
SCE READY TO SERVE DATE
DESCRIPTION OF LED FIXTURES/SCOPE OF WORK: SPECIFY HOW MANY STREET LIGHTING
FIXTURE REPLACEMENTS ARE BEING REQUESTED AND AGREED TO UNDER THIS
AGREEMENT AND OTHER RELEVANT DETAILS.
W.O. No(s):