HomeMy WebLinkAboutIntersection at Nichols and Alberhill Ranch rd 2 From: Matthew Reed
To: Rennai Patterson
Subject: Intersection at Nichols and Alberhill Ranch rd
Date: Tuesday,March 25,2025 10:20:07 AM
The week of July 29th, 2024 Nichols rd was paved. They waited for asphalt cure time and had
started striping on August 6th, 2024. They striped Lake st and Nichols the same week and I do
not have exact dates of when they completed each street. Between January 8th and January
15th, the traffic lights at the intersection of Nichols and Alberhill Ranch rd were placed on
flashing red. On February 3rd, the cameras were adjusted. By February 5th, the traffic light
was in normal operation mode.
Matt Reed
Inspector
Engineering Department
City of Lake Elsinore
951-674-3124 ext. 296