HomeMy WebLinkAboutItem No. 15 - SB 1 Broadway Street Tract Pavement Resurfacing Project FY 242515)SB 1 Broadway Street Tract Pavement Resurfacing Project FY 24/25
Adopt A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LAKE ELSINORE,
CALIFORNIA, ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2024-2025
FUNDED BY SB: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017.
Page 1 of 3
REPORT TO CITY COUNCIL
To:Honorable Mayor and Members of the City Council
From:Jason Simpson, City Manager
Prepared by:Remon Habib, City Engineer
Date:May 14, 2024
Subject:SB 1 Broadway Street Tract Pavement Resurfacing Project FY 24/25
Recommendation
Adopt A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LAKE ELSINORE,
CALIFORNIA, ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2024-2025 FUNDED BY
SB: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017.
Background
The new resolution will be uploaded to “CALSMART” web tool in order to obtain project approval
for SB 1 funding for Fiscal Year 2024/2025.
Bucknam Infrastructure Group performed a Pavement Assessment in 2022. Based on their
pavement condition survey (02/2022), the Broadway Street Tract pavement condition indexes
were rated on a scale from 0 to 100 depicting condition of existing pavement. Resurfacing
recommendations are divided into the following categories based on the pavement condition.
•Slurry Seal
•2” Grind and Overlay
•4” Asphalt Reconstruction
Discussion
The Broadway Street Tract Pavement Resurfacing Project will include Type II Slurry Seal, 2” grind
and overlay, and 4” asphalt reconstruction. The following areas for the project are as follows:
Street Name From To Treatment
1 Broadway St.Lake St.Laurelwood Ln.4" AC Recon
Broadway Street Tract Resurfacing
Page 2 of 3
2 California St.St. Clair St.CDS 2" AC Overlay
3 Nebraska St.St. Clair St.CDS 2" AC Overlay
4 Massachusetts St.St. Clair St.Belmont Ave.2" AC Overlay
5 Ralph Rd.St. Clair St.CDS 2" AC Overlay
6 Torn Ranch Rd.St. Clair St.Broadway St.2" AC Overlay
7
Belmont Ave.California St.
Massachusetts
St.2" AC Overlay
8 Napa St.California St.CDS Slurry Seal
9 Alameda Ct.California St. CDS Slurry Seal
10 Tehama Ct.California St.CDS Slurry Seal
11 Alpine Ct.California St.CDS Slurry Seal
12 St. Clair St.California St.Torn Ranch Rd.2” AC Overlay
13 Laurelwood Ln.Laurelwood Ct.White Oak Rd. 4" AC Recon
14 Laurelwood Ct.Laurelwood Ln.CDS 4" AC Recon
15 Woodcrest Dr.Machado St.Parkview Dr. 2” AC Overlay
16 Monterey St.Machado St.Ponderosa St.4" AC Recon
17 Bristlecone St.Torrey St.Ponderosa St.4" AC Recon
17 Pinyon St.Torrey St.Ponderosa St.4" AC Recon
18 Torrey St.Pinyon St.Bristlecone St.4" AC Recon
19 Ponderosa St.Pinyon St.Bristlecone St.4" AC Recon
20 Crestview Dr.Machado St.CDS 4" AC Recon
The estimated cost for the Broadway Street Tract Pavement Resurfacing Project is $2,001,210.
Once SB 1 funding is secured, areas from the list above will be advertised for bid. The City of
Lake Elsinore’s projected SB 1 allocation for FY 2024-2025 is $1,841,959.
Broadway Street Tract Resurfacing
Page 3 of 3
Fiscal Impact
The funding allocation for the Broadway Street Tract Pavement Resurfacing Project will be from
the allocated SB 1 funds with the remainder being funded from Measure A.
Attachments
Attachment 1 - Resolution
Attachment 2 - Project Map
3
7
3
0
2
RESOLUTION NO 2024-
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LAKE ELSINORE,
CALIFORNIA ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2024-
2025 FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF
2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter
5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April
2017 in order to address the significant multi-modal transportation funding shortfalls statewide;
and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the
residents of our City of Lake Elsinore are aware of the projects proposed for funding in our
community and which projects have been completed each fiscal year; and
WHEREAS, the City of Lake Elsinore must adopt a list of all projects proposed to receive
funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1 by
resolution, which must include a description and the location of each proposed project, a proposed
schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City of Lake Elsinore, will receive an estimated $1,841,959 in RMRA
funding in Fiscal Year 2024-2025 from SB 1; and
WHEREAS, this is the eighth year in which the City of Lake Elsinore is receiving SB 1
funding and will enable the City of Lake Elsinore to continue essential road maintenance and
rehabilitation projects, safety improvements, repairing and replacing aging bridges, and
increasing access and mobility options for the traveling public that would not have otherwise been
possible without SB 1; and
WHEREAS, the City of Lake Elsinore has undergone a robust public process to ensure
public input into our community’s transportation priorities/the project list; and
WHEREAS, the City of Lake Elsinore used a Pavement Management System to develop
the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective
projects that also meet the communities priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City of Lake Elsinore maintain and
rehabilitate 20 streets/roads, and add active transportation infrastructure throughout the City of
Lake Elsinore this year and hundreds of similar projects into the future; and
WHEREAS, the 2021 California Statewide Local Streets and Roads Needs Assessment
found that the City’s streets and roads are in “at-risk” condition and this revenue will help us
3
7
3
0
2
increase the overall quality of our road system and over the next decade will bring our streets and
roads into a “good” condition; and
WHEREAS, the SB 1 project list and overall investment in our local streets and roads
infrastructure with a focus on basic maintenance and safety, investing in complete streets
infrastructure, and using cutting-edge technology, materials and practices, will have significant
positive co-benefits statewide.
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the City
Council of the City of Lake Elsinore, State of California, as follows:
Section 1: The foregoing recitals are true and correct.
Section 2: The Fiscal Year 2024-25 list of projects planned to be funded with Road
Maintenance and Rehabilitation Account revenues include:
The Broadway Street Tracts Pavement Rehabilitation Project will consist of Slurry Seal, 2 inch of
grind and overlay and 4” reconstruction of Asphalt pavement, depending on the existing condition
of pavement. The project is located in the north-west area of the City of Lake Elsinore, in Riverside
County, California. The useful life of the project is expected to be around 10 to 12 years with
design to start in May 2024 and be completed in July 2024 and construction to start in September
2024 and be completed in November 2024.
Street Name From To Treatment
1 Broadway St.Lake St.Laurelwood Ln.4" AC Recon
2 California St.St. Clair St.CDS 2" AC Overlay
3 Nebraska St.St. Clair St.CDS 2" AC Overlay
4 Massachusetts St.St. Clair St.Belmont Ave.2" AC Overlay
5 Ralph Rd.St. Clair St.CDS 2" AC Overlay
6 Torn Ranch Rd.St. Clair St.Broadway St.2" AC Overlay
7 Belmont Ave.California St.Massachusetts St..2" AC Overlay
8 Napa St.California St.CDS Slurry Seal
9 Alameda Ct.California St. CDS Slurry Seal
10 Tehama Ct.California St.CDS Slurry Seal
11 Alpine Ct.California St.CDS Slurry Seal
3
7
3
0
2
12 St. Clair St.California St.Torn Ranch Rd.2” AC Overlay
13 Laurelwood Ln.Laurelwood Ct.White Oak Rd. 4" AC Recon
14 Laurelwood Ct.Laurelwood Ln.CDS 4" AC Recon
15 Woodcrest Dr.Machado St.Parkview Dr. 2” AC Overlay
16 Monterey St.Machado St.Ponderosa St.4" AC Recon
17 Bristlecone St.Torrey St.Ponderosa St.4" AC Recon
17 Pinyon St.Torrey St.Ponderosa St.4" AC Recon
18 Torrey St.Pinyon St.Bristlecone St.4" AC Recon
19 Ponderosa St.Pinyon St.Bristlecone St.4" AC Recon
20 Crestview Dr.Machado St.CDS 4" AC Recon
Passed and Adopted at a regular meeting of the City Council of the City of Lake Elsinore,
California, this 14th day of May 2024.
Steve Manos
Mayor
Attest:
Candice Alvarez, MMC
City Clerk
STATE OF CALIFORNIA )
COUNTY OF RIVERSIDE ) ss.
CITY OF LAKE ELSINORE )
I, Candice Alvarez, MMC City Clerk of the City of Lake Elsinore, California, do hereby certify that
Resolution No. ______ was adopted by the City Council of the City of Lake Elsinore, California,
at the Regular meeting of _________, and that the same was adopted by the following vote:
AYES:
NOES:
ABSENT:
ABSTAIN:
_____________________________
Candice Alvarez, MMC
City Clerk
BROADWAY TRACT RESURFACING
PROJECT-SB-1
FY 24-25
SLURRY SEAL TYPE II
2" GRIND AND OVERLAY
3" GRIND AND OVERLAY