HomeMy WebLinkAboutItem No. 16 SB-1Downtown Pavement Resurfacing ProjectCity Council Agenda Report City of Lake Elsinore 130 South Main Street Lake Elsinore, CA 92530 www.lake-elsinore.org File Number: TMP 21-242 Agenda Date: 6/22/2021 Status: PassedVersion: 1 File Type: Council Consent Calendar In Control: City Council / Successor Agency Agenda Number: 16) SB-1 Downtown Pavement Resurfacing Project Fiscal Year 2021-22 Adopt A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LAKE ELSINORE, CALIFORNIA, ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2021-22 FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017. Page 1 City of Lake Elsinore Printed on 12/29/2023 REPORT TO CITY COUNCIL To: Honorable Mayor and Members of the City Council From: Jason Simpson, City Manager Prepared By: Remon Habib, City Engineer Date: June 22, 2021 Subject: SB-1 Downtown Pavement Resurfacing Project Fiscal Year 2021-22 Recommendation Adopt A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LAKE ELSINORE, CALIFORNIA, ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2021-22 FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017. Background The new resolution will be uploaded to the “CALSMART” web tool to obtain project approval for SB1 funding for Fiscal Year 2021/2022. Bucknam Infrastructure Group performed a Pavement Assessment in 2017, based on their pavement condition survey (9/8/2017), the downtown pavement condition indexes were rated on a scale from 0 to 100 depicting the condition of the existing pavement. Resurfacing recommendations are divided into the following categories based on the pavement condition:  2” Grind and Overlay  4” Grind and Overlay  Slurry Seal Discussion The downtown pavement resurfacing project will include sections at a 2” grind and overlay, AC reconstruction, PCC reconstruction, and a small portion of the area being scheduled for a slurry seal. The estimated cost for the downtown resurfacing is $1,964,900. Once SB-1 funding is secured, projects from the list above will be advertised for bid. The City of Lake Elsinore’s projected SB1 allocation for FY21-22 is $1,218,951. The following areas for the project are as follows: SB-1 Downtown Pavement Resurfacing Project FY 21/22 June 22, 2021 Page 2 Street Name From To Treatment 1 Ellis St. Pottery St. Flint St. 2" AC Overlay 2 Ellis St. Heald Ave Franklin St. AC Reconstruction 3 Ellis St. Franklin St. Pottery St. PCC Recon. 4 Lookout St. Pottery St. Flint St. 2" AC Overlay 5 Lookout St. Flint St. End Slurry Seal II 6 Granite St. Flint St. End Slurry Seal II 7 Granite St. Pottery St. Flint 2" AC Overlay 8 E. Hill St. Franklin St. Pottery St. 2" AC Overlay 9 E. Hill St. Pottery St. Flint St. AC Reconstruction 10 Adobe St. Pottery St. Flint St. AC Reconstruction 11 Adobe St. S. End Pottery St. AC Reconstruction 12 Adobe St. Flint St. N. End 2” AC Overlay 13 Franklin St. Main St. Conklin Ave Slurry Seal II 14 Pottery St. Main St. E. Hill St. Slurry Seal II 15 Pottery St. E. Hill St. Adobe St. 2” AC Overlay 16 Pottery St. Adobe St. Rancho St. AC Reconstruction 17 Sumner Ave Main St. Ellis St. PCC Recon. 18 Flint St. Main St. Rupard St. 2" AC Overlay 19 Prospect St. Main St. Chestnut St. Slurry Seal II 20 Heald Ave Main St. Maroni Ave 2” AC Overlay 21 Chestnut St. Prospect St. Graham Ave Slurry Seal II Fiscal Impact The funding allocation for the Fiscal Year 2021-2022 Downtown Pavement Resurfacing Project will be from the allocated SB-1 funds available with the remainder being funded from Measure A funds. Exhibits A - Resolution B - Project Map RESOLUTION NO 2021- A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LAKE ELSINORE, CALIFORNIA, ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2021- 22 FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017 WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 in order to address the significant multi-modal transportation funding shortfalls statewide; and WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of our City of Lake Elsinore are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and WHEREAS, the City of Lake Elsinore must adopt a list of all projects proposed to receive funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1 by resolution, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and WHEREAS, the City of Lake Elsinore, will receive and estimated $1,218,951 in RMRA funding in Fiscal Year 2021-2022 from SB 1; and WHEREAS, this is the fifth year in which the City of Lake Elsinore is receiving SB 1 funding and will enable the City of Lake Elsinore to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and WHEREAS, the City of Lake Elsinore has undergone a robust public process to ensure public input into our community’s transportation priorities/the project list; and WHEREAS, the City of Lake Elsinore used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the community’s priorities for transportation investment; and WHEREAS, the funding from SB 1 will help the City of Lake Elsinore maintain and rehabilitate 11 streets/roads, and add active transportation infrastructure throughout the City of Lake Elsinore this year and hundreds of similar projects into the future; and WHEREAS, the 2018 California Statewide Local Streets and Roads Needs Assessment found that the City’s streets and roads are in “at-risk” condition and this revenue will help us increase the overall quality of our road system and over the next decade will bring our streets and roads into a “good” condition; and WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-edge technology, materials and practices, will have significant positive co-benefits statewide. NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the City Council of the City of Lake Elsinore, State of California, as follows: Section 1. The foregoing recitals are true and correct. Section 2. The fiscal year 2021-22 list of projects planned to be funded with Road Maintenance and Rehabilitation Account revenues include: The Downtown Pavement Rehabilitation Phase III Project will consist of 2 to 4 inches of grind and overlay of Asphalt pavement or slurry seal type II, depending on the existing condition of pavement. The project is located in the downtown area of the City of Lake Elsinore, in Riverside County, California. The useful life of the project is expected to be around 10 to 12 years with design to be completed in December 2021 and construction to be completed in June 2022. Street Name From To Treatment 1 Ellis St Pottery St Flint St 2" AC Overlay 2 Ellis St Heald Ave Franklin St AC Reconstruction 3 Ellis St Franklin St Pottery St PCC Recon. 4 Lookout St Pottery St Flint St 2" AC Overlay 5 Lookout St Flint St End Slurry Seal II 6 Granite St Flint St End Slurry Seal II 7 Granite St Pottery St Flint St 2" AC Overlay 8 E. Hill St Franklin St Pottery St 2" AC Overlay 9 E. Hill St Pottery St Flint St AC Reconstruction 10 Adobe St Pottery St Flint St AC Reconstruction 11 Adobe St S. End Pottery St AC Reconstruction 12 Adobe St Flint St N. End 2” AC Overlay 13 Franklin St Main St Conklin Ave Slurry Seal II 14 Pottery St Main St E. Hill St Slurry Seal II 15 Pottery St E. Hill St Adobe St 2” AC Overlay 16 Pottery St Adobe St Rancho St AC Reconstruction 17 Sumner Ave Main St Ellis St PCC Recon. 18 Flint St Main St Rupard St 2" AC Overlay 19 Prospect St Main St Chestnut St Slurry Seal II 20 Heald Ave Main St Maroni Ave 2” AC Overlay 21 Chestnut St Prospect St Graham Ave Slurry Seal II PASSED AND ADOPTED at a regular meeting of the City Council of the City of Lake Elsinore, California this _______ day of _______, 2021: Robert E. Magee Mayor Attest: Candice Alvarez, MMC City Clerk STATE OF CALIFORNIA ) COUNTY OF RIVERSIDE ) ss. CITY OF LAKE ELSINORE ) I, Candice Alvarez, MMC City Clerk of the City of Lake Elsinore, California, do hereby certify that Resolution No. ______ was adopted by the City Council of the City of Lake Elsinore, California, at the Regular meeting of _________, and that the same was adopted by the following vote: AYES: NOES: ABSENT: ABSTAIN: _____________________________ Candice Alvarez, MMC City Clerk SLURRY SEAL TYPE II2" GRIND AND OVERLAYAC RECONSTRUCTIONPCI: 43 TO 60PCI: 6 0 PCI: 9 0 PCI: 6 8 PCI: 2 8 PCI: 1 0 PCI: 2 8PCI: 70PCI: 45 TO 30PCI: 76*PROPOSED AC BERMSPROPOSED CROSS GUTTER***********DOWNTOWN STREETRESURFACING PROJECTSB-1 - FY 21-22PCC RECONSTRUCTION