CONDITIONS OF APPROVAL
PROJECT: PA 2020-85/RDR 2020-01
PROJECT NAME: Iris at Summerly
PROJECT LOCATION: APN: 371-040-016 (TR 31920-22)
APPROVAL DATE:
EFFECTIVE DATE:
EXPIRATION DATE:
GENERAL
1. Planning Application No. 2020-85 (Residential Design Review No. 2020-01) for the design
and construction of 58 single-family residential units, preliminary plotting, conceptual wall
and fence plan, and related improvements (Project). The Project is located in Tract Map
No. 31920-22 (APN: 371-040-016) of the Summerly Development of the East Lake
Specific Plan (ELSP).
2. The applicant shall defend (with counsel acceptable to the City), indemnify, and hold
harmless the City, its Officials, Officers, Employees, Agents, and its Consultants
(Indemnitees) from any claim, action, or proceeding against the Indemnitees to attack, set
aside, void, or annul an approval of the City, its advisory agencies, appeal boards, or
legislative body concerning approval, implementation and construction of the Planning
Application No. 2020-85 (Residential Design Review No. 2020-01), which action is bought
within the time period provided for in California Government Code Sections 65009 and/or
66499.37, and Public Resources Code Section 21167, including the approval, extension
or modification Planning Application No. 2020-85 (Residential Design Review No. 2020-
01) or any of the proceedings, acts or determinations taken, done, or made prior to the
decision, or to determine the reasonableness, legality or validity of any condition attached
thereto. The Applicant's indemnification is intended to include, but not be limited to,
damages, fees and/or costs awarded against or incurred by Indemnitees and costs of suit,
claim or litigation, including without limitation attorneys' fees, penalties and other costs,
liabilities and expenses incurred by Indemnitees in connection with such proceeding. The
City will promptly notify the applicant of any such claim, action, or proceeding against the
City. If the project is challenged in court, the City and the applicant shall enter into formal
defense and indemnity agreement, consistent with this condition.
3. Within 30 days of project approval, the applicant shall sign and complete an
"Acknowledgment of Conditions" and shall return the executed original to the Community
Development Department for inclusion in the case records.
PLANNING DIVISION
4. Residential Design Review No. 2020-01, shall lapse and become void two (2) years
following the date on which the design review became effective, unless one of the
following: (1) prior to the expiration of two years, a building permit related to the design
review is issued and construction commenced and diligently pursued toward completion;
or (2) prior to the expiration of two years, the applicant has applied for and has been
granted an extension of the design review approval pursuant to subsections (B) and (C)
of Lake Elsinore Municipal Code (LEMC) Section 17.184.120. Notwithstanding conditions
to the contrary, a design review granted pursuant to LEMC Chapter 17.184 shall run with
the land for this two-year period, subject to any approved extensions, and shall continue
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 2 of 15
to be valid upon a change of ownership of the site, which was the subject of the design
review application.
5. All construction shall comply with these Conditions of Approval and those provisions and
requirements contained in the Amendment No. 11 of the ELSP and LEMC, prior to
issuance of certificate of occupancy and release of utilities.
6. All site improvements shall be constructed as indicated on the approved building
elevations and site plans for the Residential Design Review.
7. Future site plotting and construction shall be consistent with these Conditions of Approval,
those conditions approved with Tentative Tract Map No. 31920, and those provisions and
requirements contained in the Amendment No. 11 of the ELSP, and the LEMC, subject to
approval by the Community Development Director or designee.
8. The following architectural details shall be provided:
All front fence returns shall be decorative masonry walls. Wood fences will not be
allowed along the front elevation. Wood, vinyl or steel (wrought iron or aluminum)
gates are allowed in order to allow access to rear yards.
The applicant shall provide four-sided articulation. Architectural enhancements and
treatments shall be provided on all residential elevations (front, rear and side) visible
from streets and other public views.
All fireplaces shall be natural gas fireplaces only. No wood burning fireplaces shall
be allowed.
9. All weep screeds shall be a maximum three (3) inches above any hard surface and four
inches above any earth surface.
10. Any revisions to approved site plans or building elevations shall be reviewed and approved
by the Community Development Director or designee. Materials and colors as depicted in
the approved Design Review Package shall be used unless minor modifications are
approved by the Community Development Director or designee or major modifications are
approved by the Planning Commission.
11. The applicant shall provide a flat concrete pad or area a minimum of 3'- 0" by 7'- 0"
adjacent to the dwelling for the storage of the City trash barrels. The storage pad or area
shall conceal the trash barrels from public view, subject to the approval of the Community
Development Director or designee. Precise grading plans shall identify the location of the
aforementioned flat concrete pad and air conditioning units.
12. The building addresses (in numerals at least four inches high) shall be displayed near the
entrance and easily visible from the front of the unit and public right-of-way. The applicant
shall obtain street addresses for all production lots prior to issuance of building permit.
13. The applicant shall comply with all requirements of the City's Grading Ordinance.
Construction generated dust and erosion shall be mitigated in accordance with the
provisions of Municipal Code, Chapter 15.72 and using accepted techniques. Interim
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 3 of 15
erosion control measures shall be provided 30 days after the site's rough grading, as
approved by the City Engineer.
14. Prior to the issuance of a building permit, the Applicant shall submit a product placement
plan depicting the plan and design for each lot to be approved by the Community
Development Director or designee. Care is to be taken to ensure that adjacent units are
not of the same plan and design and there is adequate variation.
15. The applicant shall comply with all applicable City Codes and Ordinances.
16. Prior to issuance of building permit, building plans for the model home complex shall
comply with all American Disabilities Act (ADA) requirements, including provision of an
accessible bathroom.
17. A cash bond in the amount of $1,000 shall be required for the model home complex. This
bond is to guarantee removal of the temporary fencing material, parking lot, etc. that have
been placed onsite for the model home complex. The bond will be released after removal
of the materials and the site is adequately restored, subject to the approval of the
Community Development Director or designee.
18. A cash bond in the amount of $1,000 of shall be required for any garage conversion of the
model(s). Bonds will be released after removal of all temporary materials and the site is
adequately restored, subject to the approval of the Community Development Director or
designee.
19. A cash bond in the amount of $1,000 of shall be required for any construction trailers used
during construction. Bonds will be released after removal of trailers, subject to the approval
of the Community Development Director or designee.
20. The project shall connect to sewer and meet all requirements of the Elsinore Valley
Municipal Water District (EVMWD). The applicant shall submit water and sewer plans to
the EVMWD and shall incorporate all district conditions and standards.
21. All mechanical and electrical equipment associated with the residences shall be ground
mounted. All outdoor ground or wall mounted utility equipment shall be consolidated in a
central location and architecturally screened, subject to the approval of the Community
Development Director or designee, prior to issuance of building permit.
22. All front yards and side yards on corner lots shall be properly landscaped with automatic
(manual or electric) irrigation system to provide 100 percent landscape coverage using a
combination of drip and conventional irrigation methods. One (1) set of the Final
Landscaping/Irrigation Detail Plan along with a digital copy (i.e. PDF copy) with
appropriate fees shall be submitted for review and approval by the Community
Development Director or designee, prior to issuance of a building permit
Perimeter walls shall be protected by shrubs and other plantings that discourage
graffiti.
The applicant shall ensure a clear line of sight at ingress/egress points by providing
plantings within 15 feet of ingress/egress points whose height does not exceed three
feet and whose canopy does not fall below six feet.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 4 of 15
The landscape plan shall provide for California native drought-tolerant ground cover,
shrubs, and trees. Special attention to the use of Xeriscape or drought resistant
plantings with combination drip irrigation system to be used to prevent excessive
watering.
No front-yard grass turf landscaping shall be installed.
All landscape improvements shall be bonded with a 100 percent Faithful Performance
Bond for materials and labor for two years or Certificate of Occupancy.
All landscaping and irrigation shall be installed within an affected portion of any phase
at the time a certificate of occupancy is requested for any building.
All new Model Homes shall be Xeriscaped and signage provided identifying Xeriscape
landscaping. Xeriscape is a method of landscape design that minimizes water use by:
1) Implementing hydrozones;
2) Minimizes high water-use plant material as identified by Water Use
Classifications of Landscape Species (WUCOLS) (such as turf) and incorporates
water-efficient (“drought-tolerant” / climate-appropriate) plants;
3) Requires an efficient irrigation system that includes:
a. ET-Based (“Smart irrigation”) controller(s) with weather-sensing, automatic
shut-off and seasonal adjustment capabilities;
b. Efficient irrigation water application through use of:
i. Low-volume point-source irrigation (such as drip irrigation and bubblers)
for all shrub planter areas (maximum of 3:1 slope) with a minimum
irrigation efficiency of 0.90 ; and/or
ii. Spray or rotor-type nozzles for areas a minimum of eight (8) feet wide,
for slopes 3:1 and greater, AND with a minimum irrigation efficiency of
0.71.
4) Improvement of soil structure for better water retention; and
5) Application of mulch to hinder evaporation.
The Final landscape plan shall be consistent with any approved site and/or plot plan.
The Final landscape plan shall include planting and irrigation details.
All exposed slopes in excess of three feet in height within the subject tract and within
private lots shall have a permanent irrigation system and erosion control vegetation
installed, as approved by the Planning Division, prior to issuance of certificate of
occupancy.
All landscaping and irrigation shall comply with the water-efficient landscaping
requirements set forth in LEMC Chapter 19.08 (Water Efficient Landscape
Requirements), as adopted and any amendments thereto.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 5 of 15
Applicant shall provide a landscaping installation plan prior to the issuance of building
permits to be approved by the Community Development Director or their designee.
The Final landscape plan submitted shall have 50% of the total landscape area as
ground cover.
23. Fences located in any front yard shall not exceed three feet in height with the exception
that wrought-iron fences may be five feet in height. Chain link fences shall be prohibited.
24. Garages shall be constructed to provide a minimum of twenty feet by twenty feet (20’ x
20’) of interior clear space to accommodate two vehicles.
25. These Conditions of Approval and those conditions approved with Tentative Tract Map
No. 31920 shall be reproduced on subsequent building plans prior to issuance of building
permit.
26. Provisions of the City's Noise Ordinance shall be satisfied during all site preparation and
construction activity. Site preparation activity and construction shall not commence before
7:00 AM and shall cease no later than 5:00 PM, Monday through Friday. Only finish work
and similar interior construction may be conducted on Saturdays and may commence no
earlier than 8:00 am and shall cease no later than 4:00 p.m. Construction activity shall
not take place Sunday or any Legal Holidays.
27. The applicant shall place a weatherproof 3’ x 3’ sign at the entrance to the project site
identifying the approved days and hours of construction activity and a statement that
complaints regarding the operation can be lodged with the City of Lake Elsinore Code
Enforcement Division (951) 674-3124.
28. The Homeowner’s Association shall maintain all project improvements and facilities,
including the landscaping, perimeter walls, park facilities, and drainage improvements.
29. The developer shall comply with all of the terms and conditions of that certain First
Amended and Restated Development Agreement Between the City of Lake Elsinore and
Laing-CP Lake Elsinore LLC” which recorded on December 17, 2004 in the Official
Records of Riverside County, California as Instrument No. 1001282 and the First
Operating Memorandum of Understanding dated November 23, 2010 and the Second
Operating Memorandum of Understanding dated June 4, 2018 by and between the City
and McMillin Summerly, LLC, the successor in interest to Laing, including without limitation
the payment of the Summerly Traffic Infrastructure Fee in the amount of One Dollar and
Thirty Cents ($1.30) per square foot of assessable space.
30. The applicant shall provide all prospective homebuyers and homeowners a written
disclosure statement identifying that the project is located within an active recreation area.
Such activities will include, but are not limited to sporting activities, water sport and
recreation activities, off road racing, sky diving, hang gliding, etc. Said written disclosure
statements shall indicate that such recreation activities will include, but are not limited to
noise impacts, excessive lighting and dust.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 6 of 15
BUILDING DIVISION
General Conditions
31. Final Building and Safety Conditions. Final Building and Safety Conditions will be
addressed when building construction plans are submitted to Building and Safety for
review. These conditions will be based on occupancy, use, the California Building Code
(CBC), and related codes which are enforced at the time of building plan submittal.
32. Compliance with Code. All design components shall comply with applicable provisions of
the 2019 edition of the California Building, Plumbing and Mechanical Codes: 2019
California Electrical Code; California Administrative Code, 2019 California Energy Codes,
2019 California Green Building Standards, California Title 24 Disabled Access
Regulations, and Lake Elsinore Municipal Code.
33. Street Addressing. Applicant must obtain street addressing for all proposed buildings by
requesting street addressing and submitting a site plan for commercial or multi-family
residential projects or a recorded final map for single- family residential projects.
34. Clearance from LEUSD. A receipt or clearance letter from the Lake Elsinore School
District shall be submitted to the Building and Safety Department to ensure the payment
or exemption from School Mitigation Fees.
35. Obtain Approvals Prior to Construction. Applicant must obtain all building plans and permit
approvals prior to commencement of any construction work.
36. Obtaining Separate Approvals and Permits. Trash enclosures, patio covers, light
standards, and any block walls will require separate approvals and permits.
37. Sewer and Water Plan Approvals. On-site sewer and water plans will require separate
approvals and permits.
At Plan Review Submittal
38. Submitting Plans and Calculations. Applicant must submit to Building and Safety four (4)
complete sets of plans and two (2) sets of supporting calculations for review and approval
including:
a. An electrical plan including load calculations and panel schedule, plumbing
schematic, and mechanical plan applicable to scope of work.
b. A Sound Transmission Control Study in accordance with the provisions of the
Section 1207, of the 2019 edition of the California Building Code.
c. A precise grading plan to verify accessibility for the persons with disabilities.
d. Truss calculations that have been stamped by the engineer of record of the building
and the truss manufacturer engineer.
Prior to Issuance of Grading Permit(s)
39. Onsite Water and Sewer Plans. Onsite water and sewer plans, submitted separately from
the building plans, shall be submitted to Building and Safety for review and approval.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 7 of 15
40. Demolition Permits. A demolition permit shall be obtained if there is an existing structure
to be removed as part of the project.
Prior to Issuance of Building Permit(s)
41. Plans Require Stamp of Registered Professional. Applicant shall provide appropriate
stamp of a registered professional with original signature on the plans.
Prior to Beginning of Construction
42. Pre-Construction Meeting. A pre-construction meeting is required with the building
inspector prior to the start of the building construction.
ENGINEERING DIVISION
General Requirements
43. This project shall comply with the applicable Conditions of Approval of Tentative Tract
31920 as approved by City Council on July 27, 2004.
44. All arrangements for relocation of utility company facilities (power poles, vaults, etc.) out
of the roadway shall be the responsibility of the property owner or his agent. All overhead
utilities shall be undergrounded.
45. All slopes, open space, community walls and landscaping except for public parks, school
property and flood control district facilities shall be maintained by the property owner or
property owner’s association or another maintenance entity approved by the City Council.
46. Community walls will be located on Homeowner’s Association lots.
47. In accordance with the City’s Franchise Agreement for waste disposal & recycling, the
developer shall be required to contract with CR&R Inc. for removal and disposal of all
waste material, debris, vegetation and other rubbish generated during cleaning,
demolition, clear and grubbing or all other phases of construction.
48. Developer shall mitigate to prevent any flooding and/or erosion downstream caused by
development of the site and or diversion of drainage.
49. In the absence of grass, front yard drainage shall include mitigation measures to address
erosion.
50. No building will be allowed in drainage easements. Drainage easements will be kept free
and clear.
51. Any grading that affects “waters of the United States”, wetlands or jurisdictional
streambeds, shall require approval and necessary permits from respective Federal and/or
State agencies.
52. All required grading and improvement plans, soils, geology, hydrology and hydraulic, and
seismic reports shall be prepared by a Registered Civil Engineer.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 8 of 15
53. Prior to City Council approval of the final Tract Map the developer shall, in accordance
with Government Code, have constructed all improvements or have improvement plans
submitted and approved, agreements executed and securities posted.
54. AutoCad Guidelines:
a. The City’s title block shall be used and is available at www.lake-elsinore.org.
b. Don’t use spaces in the filenames of the CAD data.
c. Whatever coordinate system is used, it should be in feet.
d. CAD data shall use California State Plane, Zone 6 coordinates.
e. The CAD file must not have references to other CAD files.
f. CAD data shall include attributes required for GIS purposes.
Fees
55. The developer shall pay all Engineering Division assessed Development Impact, Plan
Check and Permit fees (LEMC 16.34). Applicable Development Impact Fees include:
Traffic Infrastructure Fee (TIF) – due at building permit, and Transportation Uniform
Mitigation Fee (TUMF) – due prior to occupancy. Fee rate will be assessed in accordance
with the First Amended and Restated Development Agreement Between the City of Lake
Elsinore and Laing-CP Lake Elsinore LLC” which recorded on December 17, 2004 in the
Official Records of Riverside County, California as Instrument No. 1001282 and the First
Operating Memorandum of Understanding dated November 23, 2010 and the Second
Operating Memorandum of Understanding dated June 4, 2018 by and between the City
and McMillin Summerly, LLC, the successor in interest to Laing.
Flood Plain
56. Meet all requirements of LEMC 15.68 and 15.64 regarding floodplain management and
flood hazard regulations. Finish floor elevation of all buildings shall be a minimum of 1267
ft., and at or above the approved LOMR-F elevation.
57. At the direction of the City Engineer, the developer shall process a lot specific LOMR-F or
prepare Elevation Certificates for each lot to the insurance standard.
58. The lowest floor of each structure shall, at a minimum, be 1267.2 feet msl NAVD 88.
59. The current LOMR-F information shall be shown on the grading plans.
60. A copy of the approved LOMR-F or Elevation Certificate shall be provided to each buyer.
61. Projects in the back basin shall comply with the special conditions to Permit No. 88-00215-
00-RRS (Lake Elsinore Management Project)
Storm Water Management / Pollutant Prevention
62. The developer shall obtain and maintain coverage under the General Permit –
Construction. A copy of the Change of Information (COI) and/or NOI shall be submitted
to the Engineering Division prior to permit issuance. A SWPPP shall be prepared,
implemented and maintained onsite to provide erosion control measures and best
management practices (BMP’s) throughout all phases of construction.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 9 of 15
63. All storm drain inlet facilities shall be appropriately marked “Only Rain in the Storm Drain”
using the City authorized marker to prevent illegal dumping in the storm drain system.
64. The developer shall submit an amendment to the Master Water Quality Management Plan
(WQMP). The requirements of the WQMP Amendment may affect the overall layout of the
project. Therefore, WQMP submittal should be during the initial process of the project.
The final WQMP Amendment must be approved prior to grading permit issuance.
65. DURING CONSTRUCTION, NPDES education guidelines and Best Management
Practices (BMPs) shall be posted to inform users of this development of environmental
awareness and good housekeeping practices that contribute to protection of storm water
quality and meet the goals of the BMPs of the Riverside County NPDES Drainage Area
Management Plan.
Improvements
66. An Encroachment Permit shall be obtained prior to any work on City and/or State right-of-
way. The developer shall submit the permit application, required fees and documents
prior to issuance.
67. Revisions to the previously approved street improvement plans, to accommodate
driveway locations, will be required. No utility laterals can be located within any portion of
the driveway approach.
68. Sight distance into and out of the project location shall comply with CALTRANS Standards.
69. All landscaping and fencing at intersections shall meet City Sight Distance Standards.
70. Roof drains shall drain to a landscaped area.
71. No service laterals shall be located underneath driveway approaches or aprons.
72. If existing improvements are to be modified, the existing improvement plans on file shall
be modified accordingly and approved by the City Engineer prior to issuance of building
permit.
73. 10-year storm runoff shall be contained within the curb and the 100-year storm runoff shall
be contained within the street right-of-way. When either of these criteria is exceeded,
drainage facilities shall be provided.
74. All drainage facilities in this project shall be constructed to Riverside County Flood Control
District Standards.
75. All compaction reports, grade certifications, monument certifications (with tie notes
delineated on 8 ½" x 11" Mylar) shall be submitted to the Engineering Division before final
inspection of public works improvements will be scheduled and approved.
76. All natural drainage traversing the site shall be conveyed through the site, or shall be
collected and conveyed by a method approved by the City Engineer. All off-site drainage,
if different from historic flow, shall be conveyed to a public facility, accepted by adjacent
property owners by a letter of drainage acceptance, or conveyed to a drainage easement.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 10 of 15
77. All Public Works requirements shall be constructed and complied with as a condition of
development as specified in the Lake Elsinore Municipal Code (LEMC) and Lake Elsinore
Public Works Standard Plans.
78. The developer shall install blue dot markers in the roadway at a right angle to Fire Hydrant
locations per Lake Elsinore Standards.
79. The street light system shall be designed by SCE as a LS2, City owned system. The City
approved LED light standard hall be used.
80. Street Light Plans shall be submitted for plan check with the appropriate application and
plan check fee.
81. The developer shall provide signing and striping plans for the required improvements of
this project.
82. Erosivity of drainage directed across the front yard shall be mitigated; mitigation measures
may include use of three (3) to four (4) inch rock to form a dry river bed.
Grading
83. Grading plans shall reference NAVD 88 datum and elevations. The current LOMR
information shall be placed on the plans for easy reference.
84. Prior to commencement of grading operations, developer is to provide to the City with a
map of all proposed haul routes to be used for movement of export material. All such
routes shall be subject to the review and approval of the City Engineer. Haul route shall
be submitted prior to issuance of a grading permit. Export sites located within the Lake
Elsinore City limits must have an active grading permit. Hauling of over 5,000 cy subject
to City Council approval (LEMC 15.72.065). Costs incurred by City in conjunction with
approval of the haul route shall be paid by the applicant.
85. The project shall comply with CBC 1804.3 site grading requirements.
86. Applicant to provide to the City a video record of the condition of all proposed public City
haul roads. In the event of damage to such roads, applicant shall pay full cost of restoring
public roads to the baseline condition. A bond may be required to ensure payment of
damages to the public right-of-way, subject to the approval of the City Engineer.
87. A grading plan signed and stamped by a California Registered Civil Engineer shall be
submitted for City review and approval for all addition and/or movement of soil (grading)
on the site. The plan shall include separate sheets for erosion control, haul route and
traffic control. The grading submittal shall include all supporting documentation and be
prepared using City standard title block, standard drawings and design manual (available
at www.lake-elsinore.org).
88. All grading plan contours shall extend to minimum of 50 feet beyond property lines to
indicate existing drainage pattern.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 11 of 15
89. If the grading plan identifies alterations in the existing drainage patterns as they exit the
site, a Hydrology and Hydraulic Report for review and approval by City Engineer shall be
required prior to issuance of grading permits. All grading that modifies the existing flow
patterns and/or topography shall be approved by the City Engineer.
90. The developer shall apply for, obtain and submit to the City Engineering Division a letter
from Southern California Edison (SCE) indicating that the construction activity will not
interfere with existing SCE facilities (aka SCE NIL).
91. All grading shall be done under the supervision of a geotechnical engineer. Slopes
steeper than 2 to 1 shall be evaluated for stability and proper erosion control and approved
by the City.
92. Developer shall execute and submit grading and erosion control agreement, post grading
security and pay permit fees as a condition of grading permit issuance.
93. Developer shall pay all grading permit applicable processing, permit, security and
development fees including those fees identified in an applicable development agreement.
Prior to Issuance of Building Permit
94. The final map shall be approved and recorded prior to building permit issuance.
95. Provide final soils, geology and seismic report, including recommendations for parameters
for seismic design of buildings, and walls prior to building permit.
96. All required public right-of-way dedications and easements shall be prepared by the
developer or his agent and shall be submitted to the Engineering Department for review
and approval prior to issuance of building permit.
97. All internal street improvement and signing and striping plans shall be completed and
approved by the City Engineer.
98. All revised street improvement plans will be submitted for plan check and approved by the
City Engineer.
Prior to Occupancy
99. All signing and striping and traffic control devices for the required improvements internal
to TR 31920-22 shall be installed.
100. All public improvements internal to TR 31920-22 shall be completed in accordance with
the approved plans or as condition of this development to the satisfaction of the City
Engineer. Acceptance of public improvements can be requested once all construction of
homes has ended and a final slurry has been applied.
101. Any damage to existing landscape easement areas due to project construction shall be
repaired or replaced at no cost to the City.
102. Any damage to existing asphalt streets, concrete sidewalks, curbs, gutters and driveways
will be repaired to the satisfaction of the City Engineer prior to tract final.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 12 of 15
103. Final soil report showing compliance with recommendations, compaction reports, grade
certifications, monument certifications (with tie notes delineated on 8 ½ x 11” mylar) shall
be submitted in .tif format on CD to the Engineering Division before final inspection will be
scheduled.
104. In the event of damage to City roads from hauling or other construction related activity,
applicant shall pay full cost of restoring public roads to the baseline condition.
105. Prior to grading or building permit close-out and/or the issuance of a certificate of use or
a certificate of occupancy, developer shall:
Demonstrate that all structural BMPs required for TR 31920-22 have been
constructed, installed and are functioning in conformance with approved plans and
specifications and the WQMP. Certification by a registered civil engineer using the
City’s form shall be provided
Demonstrate that they are prepared to implement all non-structural BMPs required
for TR 31920-22 included in the conditions of approval or building/grading permit
conditions;
Demonstrate that an adequate number of copies of the approved project specific TR
31920-22 Amendment to the WQMP are available for the future owners/occupants;
and
The developer shall provide all education guidelines for Water Quality Management
Practices to the separate owners of the development, regarding the environmental
awareness on good housekeeping practices that contribute to protection of storm
water quality and meet the goals of the approved WQMP in the Riverside County
NPDES Drainage Area Management Plan. Contact the City NPDES Coordinator for
handout/guideline information.
106. As-built plans for all approved plan sets shall be submitted for review and approval by the
City. The developer/developer/owner is responsible for revising the original mylar plans.
107. The approved, revised plans and Final recorded map(s) shall be provided to the City on a
CD/DVD in .tif format and as GIS Shape files of all final maps and street and storm drain
plans. *ALL DATA MUST BE IN projected Coordinate System: NAD 83 State Plane
California Zone VI U.S. Fleet.
108. All final studies and reports shall be submitted in .tif format on a CD/DVD. Studies and
reports include, Soils, Seismic, Hydrology, Hydraulics, Grading, WQMP, etc.
CITY OF LAKE ELSINORE FIRE MARSHAL
General Conditions
109. Lake Elsinore Fire Protection Planning Office Responsibility - It is the responsibility
of the recipient of Fire Department conditions to forward them to all interested parties. The
permit number is required on all correspondence. Questions should be directed to the
Riverside County Fire Department, Lake Elsinore Fire Protection Planning Division at 130
S. Main St., Lake Elsinore, CA 92530. Phone: (951) 671-3124 Ext. 225. The following fire
department conditions shall be implemented in accordance with the Lake Elsinore
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 13 of 15
Municipal Code and the adopted codes at the time of project building plan submittal, these
conditions are in addition to the adopted code requirements.
110. Blue Dot Reflectors - Blue retro-reflective pavement markers shall be mounted on private
streets, public streets and driveways to indicate location of fire hydrants. Prior to
installation, placement of markers must be approved by the Riverside County Fire Dept.
111. Minimum Hydrant Fire Flow - Minimum required fire flow shall be 1,500 GPM for 2 hours
duration at 20 PSI residual operating pressure, which must be available before any
combustible material is placed on the job site. Average spacing between hydrants 500’
and 250’ maximum distance from any point on the street or road frontage to hydrant.
Standard Fire hydrants shall be installed (6”x4”x2-1/2”).
112. Standard Fire Hydrants- Super fire hydrants (6” x 4” x 2-2 1/2”), shall be located not less
than 25 feet or more than 250 feet from any portion of the building as measures along
approved vehicular travel ways. The required fire flow shall be available from any adjacent
hydrant(s) in the system.
113. Minimum Access Standards - The following access requirements are required to be
implemented to ensure fire department and emergency vehicular access. All roadways
shall conform to the City of Lake Elsinore approved roadway standards but in no case
shall the minimum fire department vehicular access be less the following provisions:
A. Twenty-four feet (24’) clear width. Where parking is to be provided, each parking
side shall be provided with eight (8’) additional feet on each side of the fire
department access.
B. Median openings or crossovers between opposing lanes of a divided highway or
street shall be located only at approved intersections at intervals of not less than
500 feet. [Ord. 529 § 3.2(F), 1973].
C. The required all weather vehicular access shall be able to support no less than
70,000 lbs. over 2 axles.
D. Roadway gradient shall not exceed 15% on any access road, driveways, and
perimeter roads.
E. Turning Radius shall be 26’ inside and 38’ outside for all access roads.
114. Secondary Access - In the interest of Public Safety, this project shall provide an Alternate
or Secondary Access. Said access shall be constructed in accordance to the City of Lake
Elsinore Engineering Department standards to accommodate full fire response and
community evacuation.
115. Separation of Occupancy- A fire barrier wall for the separation of occupancies is required
per the California Building Code. Fire walls, fire barriers, fire partitions, smoke barriers,
and smoke partitions or any other wall required to have protected openings or penetrations
shall be effectively and permanently identified with signs or stenciling. Such identification
shall be located in accessible concealed floor, floor ceiling or attic spaces repeated at
intervals not exceeding 30 feet along the wall, and include lettering not less than 0.5 inch
in height, incorporating the suggested wording “FIRE AND/OR SMOKE BARRIER-
PROTECT ALL OPENINGS,” or other wording.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 14 of 15
Prior to Building Permit Issuance
116. Plan Check Fee- Building plan check fees shall be made payable to the “City of Lake
Elsinore”, and shall be submitted to the Fire Department at the time of plan submittal.
117. Water System Plans - Applicant and/or developer shall separately submit 2 sets of water
system plans to the Fire Department for review. Plans must be signed by a registered Civil
Engineer and/or water purveyor prior to Fire Department review and approval. Mylars will
be signed by the Fire Department after review and approval. Two (2) copies of the signed
and approved water plans shall be returned to the Fire Department before release of a
building permit.
118. Prior to Building Construction Verification - This project shall be inspected and
approved by the Fire Marshal or designee prior to bringing combustible materials on site.
During such inspection all permanent road signs shall be in place, all hydrants shall on
operating and approved for use by the water purveyor, and all permanent road surfaces
shall be completed including primary and secondary access circulation.
Prior to Building Final Inspection
119. Residential Fire Sprinkler Systems for Single family and two-family 13D - Install a
complete fire sprinkler system designed in accordance with California Residential Code,
California Fire Code and adopted standards. A C-16 licensed contractor must submit
plans, along with the current fee, to the Fire Department for review and approval prior to
installation.
MITIGATION MONITORING AND REPORTING PROGRAM
120. The Mitigation Monitoring & Reporting Program (MMRP), which was adopted for Tentative
Tract Map No. 31920.
Conditions of Approval PC: April 21, 2020
PA 2020-85/RDR 2020-01 CC: TBD
Applicant’s Initials: _____ Page 15 of 15
I hereby state that I acknowledge receipt of the approved Conditions of Approval for the above
named project and do hereby agree to accept and abide by all Conditions of Approval as approved
by the City Council of the City of Lake Elsinore on _________. I also acknowledge that all
Conditions shall be met as indicated.
Date:
Applicant’s Signature:
Print Name:
Address:
Phone Number: