HomeMy WebLinkAboutItem No. 13 - Change Order No. 1 - Regan Paving Page 1 of 2 REPORT TO CITY COUNCIL To:Honorable Mayor and Members of the City Council From:Jason Simpson, City Manager Prepared by:Shannon Buckley, Assistant City Manager Date:February 14, 2023 Subject:Change Order No. 1 to Public Works Construction Agreement with Regan Paving for the Asphalt Paving of Library Street Parking Lot Recommendation Approve and authorize the City Manager to execute Change Order No. 1 not exceeding $21,091.00 with Regan Paving for the asphalt paving of Library Street Parking Lot, Project No. Z10071, in final form, as approved by the City Attorney. Background This project aims to construct additional parking close to Main Street with easy access to City Hall and Main Street. The City retained a Civil Engineer to design the Library Street Parking Lot with lighting, landscaping, and irrigation amenities and nearly 100 full-size car parking spaces. In addition, a bio-retention facility has been designed and constructed to remove contaminants and sedimentation from stormwater runoff. On September 27, 2022, a public works construction contract was awarded to Regan Paving for the project's complete Paving, signage, and striping portion. Discussion During the construction process of this project, it was determined additional work was needed to deliver ADA accessibility from the handicapped parking spaces into City Park. This additional scope of work was completed in conjunction with the resurfacing of Library Street. With the ADA accessibility across Library Street and into City Park, future ADA thoroughfare at City Park is considerably more passable. Fiscal Impact Funding is available in the Fiscal Year 2022/2023 annual operating budget. Regal Paving Change Order No. 1 Page 2 of 2 Attachments Attachment 1 - Change Order No. 1 date January 24, 2023 CITY OF LAKE ELSINORE 130 S. MAIN STREET LAKE ELSINORE, CA 92530 (951) 674-3124 PROJECT CHANGE ORDER CHANGE ORDER #1 DATE:January 24, 2023 THIS CHANGE ORDER IS APPLICABLE TO: CITY PROJECT ##Z10071 CONTRACT AWARDED TO: PROJECT TITLE:Library Street Parking Lot Regan Paving DATE AWARDED:September 27, 2022 Authorized by:Jason Simpson TOTAL AMOUNT OF CONTRACT City Manager PRIOR TO THIS CHANGE ORDER $255,993.00 (inclusive of contingency) CONTRACTOR IS AUTHORIZED TO MAKE THE FOLLOWING CHANGES: QUANTITIES INCREASED ITEM QUANTITY UNIT UNIT PRICE EXTENSION ADA Accessibility to City Park From Library Lump Sum 1.00 $21,091.00 $21,091.00 Street Parking Lot QUANTITIES DECREASED ITEM QUANTITY UNIT PRICE EXTENSION None TOTAL $21,091.00 THE AMOUNT OF THE CONTRACT WILL BE (INCREASED) BY THE SUM OF $21,091.00 Change Order No.1 Review by:Initials Date Approved by:Date Assistant City Manager Contractor City Manager: