HomeMy WebLinkAboutItem No. 33 - Supplemental Document ROPS 23-24 draftRecognized Obligation Payment Schedule (ROPS 23-24) - Summary
Filed for the July 1, 2023 through June 30, 2024 Period
Successor Agency: Lake Elsinore
County: Riverside
Current Period Requested Funding for Enforceable
Obligations (ROPS Detail)
23-24A Total
(July -
December)
23-24B Total
(January -
June)
ROPS 23-24
Total
A Enforceable Obligations Funded as Follows (B+C+D) $ 552,033 $ 4,169,386 $ 4,721,419
B Bond Proceeds - - -
C Reserve Balance 262,500 3,874,176 4,136,676
D Other Funds 289,533 295,210 584,743
E Redevelopment Property Tax Trust Fund (RPTTF) (F+G) $ 8,436,907 $ 9,042,138 $ 17,479,045
F RPTTF 8,229,749 8,834,981 17,064,730
G Administrative RPTTF 207,158 207,157 414,315
H Current Period Enforceable Obligations (A+E) $ 8,988,940 $ 13,211,524 $ 22,200,464
Certification of Oversight Board Chairman:
Name Title
Pursuant to Section 34177 (o) of the Health and Safety
code, I hereby certify that the above is a true and
accurate Recognized Obligation Payment Schedule for
the above named successor agency. /s/
Signature Date
Lake Elsinore
Recognized Obligation Payment Schedule (ROPS 23-24) - ROPS Detail
July 1, 2023 through June 30, 2024
A B C D E F G H I J K L M N O P Q R S T U V W
Item
# Project Name Obligation
Type
Agreement
Execution
Date
Agreement
Termination
Date
Payee Description Project
Area
Total
Outstanding
Obligation
Retired ROPS
23-24 Total
ROPS 23-24A (Jul - Dec)
23-24A
Total
ROPS 23-24B (Jan - Jun)
23-24B
Total
Fund Sources Fund Sources
Bond
Proceeds
Reserve
Balance
Other
Funds RPTTF Admin
RPTTF
Bond
Proceeds
Reserve
Balance
Other
Funds RPTTF Admin
RPTTF
$194,514,239 $22,200,464 $- $262,500 $289,533 $8,229,749 $207,158 $8,988,940 $- $3,874,176 $295,210 $8,834,981 $207,157 $13,211,524
12 Summerly DDA OPA/DDA/
Construction
03/11/2011 09/08/2038 McMillin
Summerly
LLC and
Civic
Partners-
Elsinore LLC
DDA pledges a
portion of
property tax
revenues
through 2038.
Total
outstanding
debt or
obligation is
estimated
based on
projections of
tax revenue
growth at 2%
per annum. If
property values
and
corresponding
revenues grow
at a higher or
lower rate than
2% per annum,
the total
obligation will
similarly
increase or
decreased.
DDA pledges a
portion of tax
increment for
so long as the
Agency
receives tax
increment
Project
II and
III
56,374,979 N $6,080,557 - - - 1,277,013 - $1,277,013 - 3,281,134 - 1,522,410 - $4,803,544
13 Summerly DDA
Extraordinary
Infrastructure
Fund
OPA/DDA/
Construction
03/11/2011 09/08/2038 Mc Millin
Summerly
LLC
DDA pledges a
portion of
property tax
revenues
through 2038.
Total
outstanding
debt or
obligation is
estimated
based on
projections of
tax revenue
growth at 2%
per annum. If
Project
II and
III
8,409,949 N $919,278 - - - 160,075 - $160,075 - 593,042 - 166,161 - $759,203
A B C D E F G H I J K L M N O P Q R S T U V W
Item
# Project Name Obligation
Type
Agreement
Execution
Date
Agreement
Termination
Date
Payee Description Project
Area
Total
Outstanding
Obligation
Retired ROPS
23-24 Total
ROPS 23-24A (Jul - Dec)
23-24A
Total
ROPS 23-24B (Jan - Jun)
23-24B
Total
Fund Sources Fund Sources
Bond
Proceeds
Reserve
Balance
Other
Funds RPTTF Admin
RPTTF
Bond
Proceeds
Reserve
Balance
Other
Funds RPTTF Admin
RPTTF
property values
and
corresponding
revenues grow
at a higher or
lower rate than
2% per annum,
the total
obligation will
similarly
increase or
decreased.
DDA pledges a
portion of tax
increment for
so long as the
Agency
receives tax
increment.
18 City
Reimbursement
LERA
Bonds Issued
After 12/31/10
07/01/
2000
02/01/2032 City of Lake
Elsinore
City
Reimbursement
LERA - Debt
Service
All 11,291,350 N $1,130,200 - - - 565,100 - $565,100 - - - 565,100 - $565,100
20 Housing Fund
Loan
Third-Party
Loans
12/01/
1995
09/08/2038 Housing
Fund
Payments on
principal and
interest on loan
of bond
proceeds from
the housing
fund. Payments
made in any
given fiscal
year are
calculated and
disbursed
based on
available
property tax
revenue funds
after
deductions for
payment of all
other debts and
obligations of
the Agency.
All 20,377,079 N $5,939,965 - - - 3,086,971 - $3,086,971 - - - 2,852,994 - $2,852,994
22 Legal Services Fees 09/27/
2005
06/30/2023 Leibold
McClendon
& Mann
Legal services
for projects,
bonds & DDA/
Stadium
Agreement
compliance.
All 40,000 N $40,000 - - - 20,000 - $20,000 - - - 20,000 - $20,000
23 Consultant
Fees
Fees 10/23/
2007
09/08/2023 HdL Coren
& Cone
Tax Projections
for bond & DDA
compliance
All 21,890 N $21,890 - - - 10,945 - $10,945 - - - 10,945 - $10,945
A B C D E F G H I J K L M N O P Q R S T U V W
Item
# Project Name Obligation
Type
Agreement
Execution
Date
Agreement
Termination
Date
Payee Description Project
Area
Total
Outstanding
Obligation
Retired ROPS
23-24 Total
ROPS 23-24A (Jul - Dec)
23-24A
Total
ROPS 23-24B (Jan - Jun)
23-24B
Total
Fund Sources Fund Sources
Bond
Proceeds
Reserve
Balance
Other
Funds RPTTF Admin
RPTTF
Bond
Proceeds
Reserve
Balance
Other
Funds RPTTF Admin
RPTTF
28 Estimated
Admin Cost
Admin Costs 02/01/
2012
09/08/2038 City of Lake
Elsinore
City Staff
Support/other
admin
reimbursement
All 414,315 N $414,315 - - - - 207,158 $207,158 - - - - 207,157 $207,157
29 Stadium
License
Agreement
Miscellaneous 03/15/
2001
12/31/2026 Lake
Elsinore
Storm, LP
License to use
stadium for
baseball games
Project
III
2,718,875 N $584,743 - - 289,533 - - $289,533 - - 295,210 - - $295,210
30 Stadium
Maintenance
Agreement
Property
Maintenance
03/15/
2001
12/31/2026 Lake
Elsinore
Storm, LP
Agreement to
maintain
baseball field
and facilities
Project
III
- N $- - - - - - $- - - - - - $-
31 Stadium
Concession
Agreement
Miscellaneous 01/30/
2002
12/31/2026 Golden
State
Concessions
and
Catering
Provision of
concessions for
baseball games
Project
III
- N $- - - - - - $- - - - - - $-
32 Stadium
Operation and
Maintenance
Property
Maintenance
01/01/
2013
09/08/2038 Various Operation and
maintenance of
the baseball
stadium
Project
III
35,000,000 N $- - - - - - $- - - - - - $-
33 Interim Stadium
Management
Agmt.
Miscellaneous 01/01/
2013
09/30/2023 Lake
Elsinore
Storm, LP
Stadium
Maintenance
and
Management
Project
III
2,295,870 N $2,295,870 - - - 1,185,164 - $1,185,164 - - - 1,110,706 - $1,110,706
35 Administrative
Reimbursement
RPTTF
Shortfall
02/01/
2012
09/08/2038 City of Lake
Elsinore
Repayment for
City Staff
Support/other
All - N $- - - - - - $- - - - - - $-
39 Bond
Disclosure
Services
Fees 01/28/
2015
02/15/2038 Urban
Futures
Bond
disclosure
compliance
All 196,300 N $18,050 - - - - - $- - - - 18,050 - $18,050
40 Property
Maintenance
Property
Maintenance
09/13/
2009
06/30/2019 Various Maintenance
cost on Agency
property
Project
III
- N $- - - - - - $- - - - - - $-
41 Subordinated
Tax Allocation
Refunding
Bonds, Series
2015
Bonds Issued
After 12/31/10
08/25/
2015
09/01/2038 Wilmington
Trust
Bond issue to
refund Tax
Allocation
Revenue
Bonds, 2011
Series A and
Local Agency
Revenue
Bonds, 2011
Series A
All 4,374,222 N $461,256 - 112,500 - 172,878 - $285,378 - - - 175,878 - $175,878
42 Fiscal Agent
Fees
Fees 08/01/
2015
09/01/2038 Wilmington
Trust
Annual fiscal
agent fees for
bonds issues
All 136,100 N $13,900 - - - 6,500 - $6,500 - - - 7,400 - $7,400
44 Reconveyance
Cost
Property
Dispositions
05/01/
2015
06/30/2023 Various Appraisals,
Title Insurance,
Escrow and
Closing Cost
All 12,000 N $12,000 - - - 6,000 - $6,000 - - - 6,000 - $6,000
A B C D E F G H I J K L M N O P Q R S T U V W
Item
# Project Name Obligation
Type
Agreement
Execution
Date
Agreement
Termination
Date
Payee Description Project
Area
Total
Outstanding
Obligation
Retired ROPS
23-24 Total
ROPS 23-24A (Jul - Dec)
23-24A
Total
ROPS 23-24B (Jan - Jun)
23-24B
Total
Fund Sources Fund Sources
Bond
Proceeds
Reserve
Balance
Other
Funds RPTTF Admin
RPTTF
Bond
Proceeds
Reserve
Balance
Other
Funds RPTTF Admin
RPTTF
45 Arbitrage Fees Fees 01/28/
2015
02/15/2038 Various Arbitrage fees
for bonds
All 54,500 N $4,500 - - - - - $- - - - 4,500 - $4,500
46 Third Lien Tax
Allocation
Bonds, Series
2018A
Bonds Issued
After 12/31/10
03/05/
2018
03/01/2038 Wilmington
Trust
Bond issue to
refund
Developer
Obligation
II and
III
2,527,113 N $160,026 - - - 80,013 - $80,013 - - - 80,013 - $80,013
47 Third Lien Tax
Allocation
Bonds, Series
2018B
(Federally
Taxable)
Bonds Issued
After 12/31/10
03/05/
2018
03/01/2038 Wilmington
Trust
Bond issue to
refund
Developer
Obligation
II and
III
8,386,006 N $591,932 - - - 295,966 - $295,966 - - - 295,966 - $295,966
48 Subordinated
Tax Allocation
Refunding
Bonds, Series
2019A
Bonds Issued
After 12/31/10
03/05/
2018
03/01/2038 Wilmington
Trust
Bond issue to
refund
Developer
Obligation
II and
III
12,501,500 N $876,750 - 150,000 - 363,375 - $513,375 - - - 363,375 - $363,375
49 Interim Stadium
Management
Agmt.
RPTTF
Shortfall
01/01/
2013
06/30/2038 Lake
Elsinore
Storm, LP
Stadium
Maintenance
and
Management
Project
III
- N $- - - - - - $- - - - - - $-
50 Tax Allocation
Refunding
Bonds, Series
2019B
(Housing-Set-
Aside)
Bonds Issued
After 12/31/10
10/04/
2019
09/01/2025 Wilmington
Trust,
National
Association
Bond issue to
refund Tax
Allocation
Revenue
Bonds, 2010
Series B
ALL 2,855,594 N $722,126 - - - 360,696 - $360,696 - - - 361,430 - $361,430
52 Tax Allocation
Refunding
Bonds, Series
2020A
Bonds Issued
After 12/31/10
04/01/
2020
09/01/2030 Wilmington
Trust,
National
Association
Bond issue to
refund the Tax
Allocation
Revenue
Bonds, 2010
Series C
Project
I and
Project
II
15,840,100 N $1,150,000 - - - 257,500 - $257,500 - - - 892,500 - $892,500
54 Third Lien Tax
Allocation
Bonds, Series
2020B
Bonds Issued
After 12/31/10
12/23/
2020
03/01/2038 Wilmington
Trust,
National
Association
Bond issue to
refund
Developer
Obligation
Project
II and
Project
III
6,701,250 N $304,800 - - - 152,400 - $152,400 - - - 152,400 - $152,400
55 Third Lien Tax
Allocation
Bonds, Series
2020C
(Federally
Taxable)
Bonds Issued
After 12/31/10
12/23/
2020
03/01/2038 Wilmington
Trust,
National
Association
Bonds issue to
refund
Developer
Obligation
Project
II and
Project
III
3,985,247 N $458,306 - - - 229,153 - $229,153 - - - 229,153 - $229,153
57 City
Reimbursement
LERA
Bonds Issued
After 12/31/10
12/29/
2021
02/01/2032 City of Lake
Elsinore
City
Reimbursement
LERA - Debt
Service
All - Y $- - - - - - $- - - - - - $-
Lake Elsinore
Recognized Obligation Payment Schedule (ROPS 23-24) - Report of Cash Balances
July 1, 2020 through June 30, 2021
(Report Amounts in Whole Dollars)
Pursuant to Health and Safety Code section 34177 (l), Redevelopment Property Tax Trust Fund (RPTTF) may be listed as a source of payment on the ROPS, but only to the extent no other
funding source is available or when payment from property tax revenues is required by an enforceable obligation.
A B C D E F G H
ROPS 20-21 Cash Balances
(07/01/20 - 06/30/21)
Fund Sources
Comments
Bond Proceeds Reserve Balance Other Funds RPTTF
Bonds issued
on or before
12/31/10
Bonds issued
on or after
01/01/11
Prior ROPS
RPTTF and
Reserve
Balances retained
for future
period(s)
Rent, grants,
interest, etc.
Non-Admin
and Admin
1 Beginning Available Cash Balance (Actual 07/01/20)
RPTTF amount should exclude "A" period distribution
amount.
2,640,405 1,867,941 Amounts shown in Col. G1 includes Prior
Period Adjustments for ROPS 17-18
($118,173), ROPS 18-19 ($1,556,619) and
ROPS 19-20 ($193,149).
2 Revenue/Income (Actual 06/30/21)
RPTTF amount should tie to the ROPS 20-21 total
distribution from the County Auditor-Controller
548,923 14,225,666 Amount shown in Col. G2 includes the
RPTTF received for ROPS 20-21A and
ROPS 20-21B
3 Expenditures for ROPS 20-21 Enforceable Obligations
(Actual 06/30/21)
2,640,405 548,923 13,736,363 Amounts shown on Col. G3 reflects
expenditures paid during ROPS 20-21 and
does not reflect amounts reserved for future
periods as shown on Col. G4
4 Retention of Available Cash Balance (Actual 06/30/21)
RPTTF amount retained should only include the amounts
distributed as reserve for future period(s)
537,500 Col. G4 - Please see ROPS 20-21 PPA
5 ROPS 20-21 RPTTF Prior Period Adjustment
RPTTF amount should tie to the Agency's ROPS 20-21 PPA
form submitted to the CAC
No entry required 69,976 Amount ties to ROPS 20-21 PPA Form
6 Ending Actual Available Cash Balance (06/30/21) $- $- $- $- $1,749,768 Amounts shown in Col. G6 includes Prior
Pursuant to Health and Safety Code section 34177 (l), Redevelopment Property Tax Trust Fund (RPTTF) may be listed as a source of payment on the ROPS, but only to the extent no other
funding source is available or when payment from property tax revenues is required by an enforceable obligation.
A B C D E F G H
ROPS 20-21 Cash Balances
(07/01/20 - 06/30/21)
Fund Sources
Comments
Bond Proceeds Reserve Balance Other Funds RPTTF
Bonds issued
on or before
12/31/10
Bonds issued
on or after
01/01/11
Prior ROPS
RPTTF and
Reserve
Balances retained
for future
period(s)
Rent, grants,
interest, etc.
Non-Admin
and Admin
C to F = (1 + 2 - 3 - 4), G = (1 + 2 - 3 - 4 - 5) Period Adjustments forROPS 18-19
($1,556,619) and ROPS 19-20 ($193,149).
Lake Elsinore
Recognized Obligation Payment Schedule (ROPS 23-24) - Notes
July 1, 2023 through June 30, 2024
Item # Notes/Comments
12
13
18
20
22
23
28
29 Stadium License Fee is due to Successor Agency pursuant to Stadium License Agreement. The
License Fee for the twelve month period covered by ROPS 23-24 is credited under the terms of the
Interim Stadium Management Agreement
30 The obligations for Item 30 for the twelve month period covered by ROPS 23-24 are incorporated into
Line 33 in accordance with the terms of the Interim Stadium Management Agreement.
31 The obligations for Item 31 for the twelve month period covered by ROPS 23-24 are incorporated into
Line 33 in accordance with the terms of the Interim Stadium Management Agreement.
32 The obligations for Item 32 for the twelve month period covered by ROPS 23-24 are incorporated into
Line 33 in accordance with the terms of the Interim Stadium Management Agreement.
33 Line 33 includes the Successor Agency obligations for Maintenance Fee, Interim Management Fee
and estimated Capital Repairs under the Eighth Amendment and the First Amendment thereto and the
Ninth Amendment to the Interim Stadium Management Agreement for the period July 1, 2023 through
June 30, 2024.
35
39
40
41
42
44
45
46
47
48
49
50
52
54
55
Lake Elsinore
Recognized Obligation Payment Schedule (ROPS 23-24) - Notes
July 1, 2023 through June 30, 2024
Item # Notes/Comments
57