File Number: TMP 22-396
Agenda Date: 8/23/2022 Status: Approval FinalVersion: 1
File Type: Council Consent
Calendar
In Control: City Council / Successor Agency
Agenda Number: 7)
Change Order No. 1 to Public Works’ Construction Agreement with Cotter Construction Inc. for
the ADA Ramp Project, at Launch Pointe Recreation Destination & RV Park (CIP Project
#Z20024)
Approve and authorize the City Manager to execute Change Order No. 1 in the not to exceed amount of
$19,100.00 with Cotter Construction Inc. for the ADA Ramp Project, at Launch Pointe Recreation
Destination & RV Park (CIP PROJECT #Z20024) in final form as approved by the City Attorney.
Page 1 City of Lake Elsinore Printed on 8/19/2022
REPORT TO CITY COUNCIL
To: Honorable Mayor and Members of the City Council
From: Jason Simpson, City Manager
Prepared by: Shannon Buckley, Assistant City Manager
Date: August 23, 2022
Subject: Change Order No. 1 to Public Works’ Construction Agreement with Cotter
Construction Inc. for the ADA Ramp Project, at Launch Pointe Recreation
Destination & RV Park (CIP PROJECT #Z20024)
Recommendations
Approve and authorize the City Manager to execute Change Order No. 1 in the amount not to
exceed $19,100.00 with Cotter Construction Inc. for the ADA Ramp Project at Launch Pointe
Recreation Destination & RV Park (CIP PROJECT #Z20024) in final form as approved by the City
Attorney.
Background
The City prepared a request for proposal (RFP) document and advertised it following the
requirements outlined in the California Public Contract Code. On May 23, 2022, the City posted
on PlanetBids the RFP for the ADA Ramp Project at Launch Pointe Recreation Destination & RV
Park Project (CIP PROJECT # Z20024). On June 14, 2022, a construction agreement was
awarded to Cotter Construction Inc.
Discussion
The scope of additional work contained in this change order is needed to complete a safety rail
for the entire ADA ramp. The railing will satisfy all building code requirements and match the RV
resort's existing railing. This added requirement has been discussed with the building official and
identified as a needed safety element of the ADA ramp. Also, it has been determined cost-
effective to have Cotter Construction Inc. complete the safety rail in conjunction with the current
contracted scope of work. The change order will provide a customized galvanized two-rail system
mounted into the concrete ramp on the downhill side of the ramp. This will prevent accidental
passage and falls from the ramp where there is more than a 15-inch drop on the downhill side.
Fiscal Impact
The cost of this Change Order No. 1 to the ADA Ramp Project is included in the Fiscal Year
22/23-26/27 Capital Improvement Plan (CIP) budget.
Exhibits
A - Change Order No. 1 (w/proposal dated 8/15/2022)
1
DATE:
QUANTITY UNIT
Lump Sum 1.00
TOTAL
SUM OF
1
Review by: Initials Date Date
EXTENSION
THE AMOUNT OF THE CONTRACT WILL BE (INCREASED) BY THE
$19,100.00
None
QUANTITY
PROJECT CHANGE ORDER CHANGE ORDER #
THIS CHANGE ORDER IS APPLICABLE TO:
CONTRACT AWARDED TO:
City Manager:
$19,100.00
Approved by:
Contractor
Change Order No.
Assistant City Manager
Authorized by: Shannon Buckley TOTAL AMOUNT OF CONTRACT
$69,000.00
QUANTITIES INCREASED
CITY OF LAKE ELSINORE
130 S. MAIN STREET
LAKE ELSINORE, CA 92530
(951) 674-3124
August 23, 2022
CITY PROJECT #
June 14, 2022DATE AWARDED:
PROJECT TITLE: Launch Pointe ADA Ramp Cotter Construction Inc.
#Z20024
ITEM
QUANTITIES DECREASED
$19,100.00$19,100.00
UNIT PRICE
PRIOR TO THIS CHANGE ORDER
CONTRACTOR IS AUTHORIZED TO MAKE THE FOLLOWING CHANGES:
Assistant City Manager
UNIT PRICE EXTENSIONITEM
See Attached Proposal Dated 8/15/2022
Cotter Construction
Andrew Cotter
Business Number 951-833-7842
General Engineering Contractor
Lic#1046653
Canyon Lake CA
cotter-construcion.com
cotter-construction@outlook.com
ESTIMATE
EST0064
DATE
08/15/2022
TOTAL
USD $19,100.00
TO
City of Lake Elsinore
DESCRIPTION RATE QTY AMOUNT
Approx 350 lineal feet of handrail per ADA spec.$19,100.00 1 $19,100.00