HomeMy WebLinkAbout0003_3_PA 2021-26 - Exhibit B - CofA
Applicant’s Initials: _____ Page 1 of 13
CONDITIONS OF APPROVAL
PROJECT: PA 2021-26/CDR 2021-12
PROJECT NAME: Ortega BESS
PROJECT LOCATION: APN: 377-200-045
APPROVAL DATE:
EFFECTIVE DATE:
EXPIRATION DATE:
GENERAL
1. Planning Application No. 2021-26 (Commercial Design Review No. 2021-12) proposes to
construct a 20-megawatt battery energy storage system (BESS) on a 1.79-acre site in the
C-2 General Commercial zoning district. The project site is located southeast of the
intersection of Camino Del Norte and O Hana Circle (APN: 377-200-045).
2. The applicant shall defend (with counsel acceptable to the City), indemnify, and hold
harmless the City, its Officials, Officers, Employees, Agents, and its Consultants
(Indemnitees) from any claim, action, or proceeding against the Indemnitees to attack, set
aside, void, or annul an approval of the City, its advisory agencies, appeal boards, or
legislative body concerning approval, implementation and construction of CDR 2021-12,
which action is bought within the time period provided for in California Government Code
Sections 65009 and/or 66499.37, and Public Resources Code Section 21167, including the
approval, extension or modification of CDR 2021-12 or any of the proceedings, acts or
determinations taken, done, or made prior to the decision, or to determine the
reasonableness, legality or validity of any condition attached thereto. The Applicant's
indemnification is intended to include, but not be limited to, damages, fees and/or costs
awarded against or incurred by Indemnitees and costs of suit, claim or litigation, including
without limitation attorneys' fees, penalties and other costs, liabilities and expenses incurred
by Indemnitees in connection with such proceeding. The City will promptly notify the
applicant of any such claim, action, or proceeding against the City. If the project is
challenged in court, the City and the applicant shall enter into formal defense and indemnity
agreement, consistent with this condition.
3. Within 30 days of project approval, the applicant shall sign and complete an
"Acknowledgment of Conditions" and shall return the executed original to the Community
Development Department for inclusion in the case records.
PLANNING DIVISION
4. Commercial Design Review No. 2021-12 shall lapse and become void two years following
the date on which the design review became effective, unless one of the following: (1) prior
to the expiration of two years, a building permit related to the design review is issued and
construction commenced and diligently pursued toward completion; or (2) prior to the
expiration of two years, the applicant has applied for and has been granted an extension of
the design review approval pursuant to subsections (1) and (2) of Lake Elsinore Municipal
Code (LEMC) Section 17.415.050.I.1. Notwithstanding conditions to the contrary, a design
review granted pursuant to LEMC Section 17.415.050.I.2 shall run with the land for this two-
year period, subject to any approved extensions, and shall continue to be valid upon a
change of ownership of the site, which was the subject of the design review application.
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 2 of 13
5. All Conditions of Approval shall be reproduced on page one of building plans prior to their
acceptance by the Building and Safety Division, Community Development Department. All
Conditions of Approval shall be met prior to the issuance of a Certificate of Occupancy and
release of utilities.
6. All future development proposals shall be reviewed by the City on a project-by-project basis.
If determined necessary by the Community Development Director or designee, additional
environmental analysis will be required.
7. Any proposed minor revisions to approved plans shall be reviewed and approved by the
Community Development Director or designee. Any proposed substantial revisions to the
approved plans shall be reviewed according to the provisions of the Municipal Code in a
similar manner as a new application. Grading plan revisions shall be reviewed by the City
Engineer.
8. A detailed on-site lighting plan, including a photometric diagram, shall be reviewed to ensure
that all exterior on-site lighting shall be shielded and directed on-site so as not to create
glare onto neighboring property and streets or allow illumination above the horizontal plane
of the fixture.
9. The applicant shall provide all project-related on-site and off-site improvements as required
by these Conditions of Approval.
Provisions of the City's Noise Ordinance (LEMC Chapter 17.176) shall be satisfied during all site
preparation and construction activity. Site preparation activity and construction shall not
commence before 7:00 AM and shall cease no later than 5:00 PM, Monday through
Friday. Only finish work and similar interior construction may be conducted on Saturdays
and may commence no earlier than 8:00 am and shall cease no later than 4:00 p.m.
Construction activity shall not take place on Sunday, or any Legal Holidays.
10. No individual signs are approved as part of this approval. The applicant or designee shall
submit an application for a sign permit, pay appropriate fees and receive approval from the
Community Development Department for any sign(s) installed at the project site.
11. Graffiti shall be removed within 24 hours.
12. All materials and colors depicted on the approved plans shall be used. If the applicant
wishes to modify any of the approved materials or colors depicted on the plans, the applicant
shall submit a proposal setting forth the modifications for review by the Community
Development Director or his designee
13. The entire site shall be kept free from trash and debris at all times and in no event shall
trash and debris remain for more than 24 hours.
14. If any of the conditions of approval set forth herein fail to occur, or if they are, by their terms,
to be implemented and maintained over time, if any of such conditions fail to be so
implemented and maintained according to their terms, the City shall have the right to revoke
or modify all approvals herein granted, deny or further condition issuance of all future
building permits, deny revoke, or further condition all certificates of occupancy issued under
the authority of approvals herein granted; record a notice of violation on the property title;
institute and prosecute litigation to compel their compliance with said conditions or seek
damages for their violation
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 3 of 13
Prior to Issuance of Grading Permits/Building Permits
15. Prior to issuance of a building permit, the applicant shall pay Development Impact Fees
(DIF) and MSHCP Fees per LEMC Section 16.85, at the rate in effect at the time of payment.
16. The project shall meet all requirements of the Elsinore Valley Municipal Water District
(EVMWD). The applicant shall submit water and sewer plans to the EVMWD and shall
incorporate all district conditions and standards.
17. The property address (in numerals at least six inches high) shall be displayed near the
entrance and be easily visible from the front of the subject property and public right-of-way.
18. Prior to issuance of a building permit, one (1) set of the Final Landscaping / Irrigation Detail
Plans along with a digital copy (i.e. PDF format) shall be submitted to the Community
Development Department with appropriate fees, for review and approval by the Community
Development Director or designee.
a. All planting areas shall have permanent and automatic sprinkler system with 50% plant
coverage using a drip irrigation method.
b. All planting areas shall be separated from paved areas with a six inch (6”) high and six
inch (6”) wide concrete curb. Runoff shall be allowed from paved areas into landscape
areas.
c. Planting within fifteen feet (15’) of ingress/egress points shall be no higher than twenty-
four inches (24”).
d. Landscape planters shall be planted with an appropriate parking lot shade tree
pursuant to the LEMC and Landscape Design Guidelines.
e. No required tree planting bed shall be less than 5 feet wide.
f. Root barriers shall be installed for all trees planted within 10 feet of hardscape areas
to include sidewalks.
g. Any transformers and mechanical or electrical equipment shall be indicated on
landscape plan and screened as part of the landscaping plan.
h. The landscape plan shall provide for ground cover, shrubs, and trees and meet all
requirements of the City’s adopted Landscape Guidelines.
i. All landscaping and irrigation shall be installed within affected portion of any phase at
the time a Certificate of Occupancy is requested for any building.
j. Final landscape plan must be consistent with approved site plan.
k. Final landscape plans to include planting and irrigation details.
l. Final landscape plans shall include drought tolerant planting consistent with Elsinore
Valley Municipal Water District standards subject to plan check and approval by the
City’s landscape plan check consultant.
m. No turf shall be permitted.
19. Landscaping installed for the project shall be continuously maintained to the reasonable
satisfaction of the Community Development Director. If it is determined that the landscaping
is not being maintained, the Director of Community Development shall have the authority to
require the property owner to bring the landscaping into conformance with the approved
landscape plan. The continued maintenance of all landscaped areas shall be the
responsibility of the developer or any successors in interest.
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 4 of 13
20. The proposed location of on-site construction trailers shall be approved by the Community
Development Director or designee. A cash bond of $1,000 shall be required for any
construction trailers placed on the site and used during construction. Bonds will be released
after removal of trailers and restoration of the site to an acceptable state, subject to approval
of the Community Development Director or designee. Such trailer(s) shall be fully on private
property and outside the public right of way.
BUILDING DIVISION
General Conditions
21. Final Building and Safety Conditions. Final Building and Safety Conditions will be addressed
when building construction plans are submitted to Building and Safety for review. These
conditions will be based on occupancy, use, the California Building Code (CBC), and related
codes which are enforced at the time of building plan submittal.
22. Compliance with Code. All design components shall comply with applicable provisions of
the 2019 edition of the California Building, Plumbing and Mechanical Codes: 2019 California
Electrical Code; California Administrative Code, 2019 California Energy Codes, 2019
California Green Building Standards, California Title 24 Disabled Access Regulations, and
Lake Elsinore Municipal Code.
23. Green Measures. The application shall provide 10% voluntary green measures on the
project, as stipulated by the 2019 California Green Building Standards.
24. Disabled Access. Applicant shall provide details of all applicable disabled access provisions
and building setbacks on plans to include:
a. All ground floor units to be adaptable.
b. Disabled access from the public way to the entrance of the building.
c. Van accessible parking located as close as possible to the main entry.
d. Path of accessibility from parking to furthest point of improvement.
e. Path of travel from public right-of-way to all public areas on site, such as club house,
trach enclosure tot lots and picnic areas.
25. Street Addressing. Applicant must obtain street addressing for all proposed buildings by
requesting street addressing and submitting a site plan for commercial or multi-family
residential projects or a recorded final map for single- family residential projects. It takes 10
days to issue address and notify other agencies. Please contact Sonia Salazar at
ssalazar@lake-elsinore.org or 951-674-3124 X 277.
26. Clearance from LEUSD. A receipt or clearance letter from the Lake Elsinore School District
shall be submitted to the Building and Safety Department to ensure the payment or
exemption from School Mitigation Fees.
27. Obtain Approvals Prior to Construction. Applicant must obtain all building plans and permit
approvals prior to commencement of any construction work.
28. Obtaining Separate Approvals and Permits. Trash enclosures, patio covers, light standards,
and any block walls will require separate approvals and permits.
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 5 of 13
29. Sewer and Water Plan Approvals. On-site sewer and water plans will require separate
approvals and permits. Septic systems will need to be approved from Riverside County
Environmental Health Department before permit issuance.
30. House Electrical Meter. Applicant shall provide a house electrical meter to provide power
for the operation of exterior lighting, irrigation pedestals and fire alarm systems for each
building on the site. Developments with single user buildings shall clearly show on the plans
how the operation of exterior lighting and fire alarm systems when a house meter is not
specifically proposed.
At Plan Review Submittal
31. Submitting Plans and Calculations. Applicant must submit to Building and Safety four (4)
complete sets of plans and two (2) sets of supporting calculations for review and approval
including:
a. An electrical plan including load calculations and panel schedule, plumbing schematic,
and mechanical plan applicable to scope of work.
b. A Sound Transmission Control Study in accordance with the provisions of the Section
5.507, of the 2019 edition of the California Building Code.
c. A precise grading plan to verify accessibility for the persons with disabilities.
d. Truss calculations that have been stamped by the engineer of record of the building and
the truss manufacturer engineer.
Prior to Issuance of Grading Permit(s)
32. Onsite Water and Sewer Plans. Onsite water and sewer plans, submitted separately from
the building plans, shall be submitted to Building and Safety for review and approval.
33. Demolition Permits. A demolition permit shall be obtained if there is an existing structure to
be removed as part of the project. Asbestos report and lead base paint reports are required
before demo permit will be issued.
Prior to Issuance of Building Permit(s)
34. Plans Require Stamp of Registered Professional. Applicant shall provide appropriate stamp
of a registered professional with original signature on the plans. Provid e C.D. of approved
plans to the Building Division.
Prior to Beginning of Construction
35. Pre-Construction Meeting. A pre-construction meeting is required with the building inspector
prior to the start of the building construction.
ENGINEERING DIVISION
GENERAL
36. All new submittals for plan check or permit shall be made using the City’s online Citizen
Service Portal (CSSP).
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 6 of 13
37. All plans (Street, Storm Drain, Improvement, Grading) shall be prepared by a Registered
Civil Engineer using the City’s standard title block.
38. All required soils, geology, hydrology and hydraulic and seismic reports shall be prepared
by a Registered Civil Engineer.
39. All slopes and landscaping within the public right-of-way shall be maintained by the property
owner, owner’s association, firms contracted by the property owner’s association, or another
maintenance entity approved by the City Council.
40. All open space and slopes outside the public right-of-way shall be owned and maintained
by the property owner.
41. In accordance with the City’s Franchise Agreement for waste disposal & recycling, the
applicant shall be required to contract with CR&R, Inc. for removal and disposal of all waste
material, debris, vegetation and other rubbish generated both during cleaning, demolition,
clear and grubbing or all other phases of construction and during occupancy.
42. All required public right-of-way dedications and easements shall be prepared by the
Applicant and shall be submitted to the Engineering Department for review and approval.
43. Any grading that affects “Waters of the United States”, wetlands or jurisdictional streambeds,
shall require approval and necessary permits from respective Federal and/or State
Agencies.
44. Applicant shall submit a detailed hydrology and hydraulic study for review for the sufficie nt
containment and conveyance of the storm water to a safe and adequate point as approved
by the City Engineer.
45. The site will accommodate all construction activity, building activity, vehicles, etc. No staging
on public streets, or private property belonging to others shall be conducted without the
written permission of the property owner.
46. Minimum good housekeeping and erosion and sediment control Best Management
Practices (BMPs) as identified by the City shall be implemented.
FEES
47. Applicant shall pay all applicable permit application and Engineering assessed fees,
including without limitation plan check and construction inspection fees, at the prevalent rate
at time of payment in full.
48. Applicant shall pay all applicable Mitigation and Development Impact Fees at the prevalent
rate at time of payment in full. Fees are subject to change. Engineering assessed Mitigation
and Development Impact Fees include without limitation:
Master Plan of Drainage Fee – Due prior to Grading Permit issuance
Traffic Infrastructure Fee (TIF) – Due prior to Building Permit issuance
Transportation Uniform Mitigation Fee (TUMF) – Due prior to Occupancy
Stephens’ Kangaroo Rat Habitat Fee (K-Rat) – Due prior to Grading Permit
Issuance
STORM WATER MANAGEMENT / POLLUTION PREVENTION / NPDES
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 7 of 13
Design
49. The project is responsible for complying with the Santa Ana Region National Pollutant
Discharge Elimination System (NPDES) Permits as warranted based on the nature of
development and/or activity.
50. Parking lot landscaping areas shall be designed to provide for treatment, retention or
infiltration of runoff.
51. Project hardscape areas shall be designed and constructed to provide for drainage into
adjacent landscape.
52. Project trash enclosure shall be covered, bermed, and designed to divert drainage from
adjoining paved areas and regularly maintained.
53. If CEQA identifies resources requiring Clean Water Act Section 401 Permitting, the applicant
shall obtain certification through the Santa Ana Regional Water Quality Control Board and
provide a copy to the Engineering Department.
54. All storm drain inlet facilities shall be appropriately marked “Only Rain in the Storm Drain”
using the City authorized marker.
55. The project site shall implement full trash capture methods/devices approved by the Region
Water Quality Control Board.
Construction
56. A Storm Water Pollution Prevention Plan (SWPPP) (as required by the NPDES General
Construction Permit) and compliance with the Green Building Code for sediment and
erosion control are required for this project.
57. Prior to grading or building permit for construction or demolition and/or weed abatement
activity, projects subject to coverage under the NPDES General Construction Permit shall
demonstrate that compliance with the permit has been obtained by providing a copy of the
Notice of Intent (NOI) submitted to the State Water Resources Control Board and a copy of
the notification of the issuance of a Waste Discharge Identification (WDID) Number or other
proof of filing to the satisfaction of the City Engineer. A copy of the SWPPP shall be kept at
the project site, updated, and be available for review upon request.
58. Erosion & Sediment Control – Prior to the issuance of any grading or building permit for
construction or demolition, the applicant shall submit for review and approval by the City
Engineer, an Erosion and Sediment Control Plan as a separate sheet of the grading plan
submittal to demonstrate compliance with the City’s NPDES Program and state water quality
regulations for grading and construction activities. A copy of the plan shall be incorporated
into the SWPPP, kept updated as needed to address changing circumstances of the project
site, be kept at the project site, and available for review upon request.
UTILITIES
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 8 of 13
59. All arrangements for relocation of utility company facilities (power poles, vaults, etc.) out of
the roadway and away from an access point shall be the responsibility of the applicant,
property owner, and/or his agent.
60. Overhead utilities (34.5 kV or lower) shall be undergrounded (Section 16.64 of LEMC).
61. Underground water rights shall be dedicated to the City pursuant to the provisions of LEMC
Section 16.52.030, and consistent with the City’s agreement with the Elsinore Valley
Municipal Water District.
62. Applicant shall apply for, obtain and submit to the City Engineering Department a letter from
Southern California Edison (SCE) indicating that the construction activity will not interfere
with existing SCE facilities. Non-Interference Letter (NIL) shall be provided prior to issuance
of Grading Permit.
63. Applicant shall submit a “Will Serve” letter to the City Engineering Department from the
applicable water agency stating that water and sewer arrangements have been made for
this project and specify the technical data for the water service at the location, such as water
pressure, volume, etc. Will Serve letters shall be provided prior to issuance of Grading
Permit.
IMPROVEMENTS
64. Applicant shall be responsible to design and construct the half-width street improvements
along the property’s frontage on Camino del Norte such that the ultimate right-of-way width
conforms to the General Plan Circulation Element. Camino del Norte is classified as a
Secondary Highway.
Improvements include, but are not limited to road pavement widening, curb, gutter,
sidewalk, signing and striping, street lighting (LS-2B system), and driveway.
Applicant shall be responsible to relocate the culvert headwall and overhead power
poles (as approved by the utility provider) for the construction of the ultimate road
widening.
65. Project will be responsible to design and install streetlights along the property’s frontage.
Streetlight system shall be designed as LS-2B system. Streetlight plans shall include details
such as location, pole and luminaire type, and pull box design. Streetlight plans shall be
included as part of the Street Improvement Plans.
66. Sight distance into and out and throughout the project location shall comply with City or
Caltrans standards. Project shall ensure facilities, if any, are installed in the line of sight of
drivers.
67. Applicant shall install permanent bench marks per City of Lake Elsinore Standards and at
locations to be determined by the City Engineer.
68. If existing improvements are to be modified, the existing improvement plans on file shall be
revised accordingly and approved by the City Engineer prior to issuance of a building permit.
69. A California Registered Civil Engineer shall prepare street improvement plans as required
for this project. All improvements shall be designed and constructed to City Standards and
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 9 of 13
Codes (LEMC 12.04 and 16.34). Any deviation from City standards shall be approved by
the City Engineer.
70. 10-year storm runoff shall be contained within the curb and the 100-year storm runoff shall
be contained within the street right-of-way. When either of these criteria are exceeded,
drainage facilities shall be provided.
71. All drainage facilities in this project shall be constructed to Riverside County Flood Control
District Standards. Storm drain easements will be required for facilities constructed on
private property.
72. A drainage study shall be provided. The study shall identify the following: identify storm
water runoff from and upstream of the site; show existing and proposed off-site and on-site
drainage facilities; and include a capacity analysis verifying the adequacy of the facilities.
The drainage system shall be designed to ensure that runoff from a 10-year storm of 6 hours
and 24 hours duration under developed condition is equal or less than the runoff under
existing conditions of the same storm frequency. Both 6-hour and 24-hour storm duration
shall be analyzed to determine the detention.
73. All natural drainage traversing the site shall be conveyed through the site, or shall be
collected and conveyed by a method approved by the City Engineer. All off-site drainage, if
different from historic flow, shall be conveyed to a public facility.
74. Roof drains shall not be allowed to outlet directly through coring in the street curb. Roofs
should drain to a landscaped area.
75. The site shall be planned and developed to keep surface water from entering buildings
(California Green Building Standards Code 4.106.3).
76. All existing storm drain inlet facilities adjacent to the subject properties shall be retrofitted
with a storm drain filter; all new storm drain inlet facilities constructed by this project shall
include a storm drain filter.
Permit/Construction
77. An Encroachment Permit shall be obtained prior to any work on City right-of-way. The
developer shall submit the permit application, required fees, and executed agreements,
security and other required documentation prior to issuance.
78. All compaction reports, grade certification, monument certification (with tie notes delineated
on 8 ½” X 11” Mylar) shall be submitted to the Engineering Department before final
inspection of public works improvements will be scheduled and approved.
Acceptance of Improvements
79. As-built plans shall be completed and signed by the City Engineer.
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 10 of 13
PRIOR TO GRADING PERMIT
Design
80. A grading plan signed and stamped by a California Registered Civil Engineer shall be
submitted for City review and approval for all addition and/or movement of soil (grading) on
site. The plan shall include separate sheets for erosion control, haul route and traffic control.
The grading submittal shall include all supporting documentation and be prepared using City
standard title block, standard drawings and design manual.
81. All grading plan contours shall extend to minimum of 50 feet beyond property lines t o
indicate existing drainage pattern.
82. The grading plan shall show that no structures, landscaping, or equipment are located near
the project entrances that could reduce sight distance.
83. If the grading plan identifies alterations in the existing drainage patterns as they exit the site,
a Hydrology and Hydraulic Report for review and approval by City Engineer shall be required
prior to issuance of grading permits. All grading that modifies the existing flow patterns
and/or topography shall be in compliance with Federal, State and Local law and be approved
by the City Engineer.
84. A seismic study shall be performed on the site to identify any hidden earthquake faults,
liquefaction and/or subsidence zones present on-site. A certified letter from a registered
geologist or geotechnical engineer shall be submitted confirming the absence of this hazard
prior to grading permit. The location of faults, active or inactive shall be shown on the plan
sets.
85. Applicant shall obtain all necessary off-site easements and/or permits for off-site grading
and the applicant shall accept drainage from the adjacent property owners.
86. Applicant shall mitigate to prevent any flooding and/or erosion downstream caused by
development of the site and/or diversion of drainage.
87. All natural drainage traversing the site (historic flow) shall be conveyed through the site in a
manner consistent with the historic flow or to one or a combination of the following: to a
public facility; accepted by adjacent property owners by a letter of drainage acceptance; or
conveyed to a drainage easement as approved by the City Engineer.
Permit/Construction
88. Applicant shall execute and submit grading and erosion control agreement, post grading
security and pay permit fees as a condition of grading permit issuance.
89. No grading shall be performed without first having obtained a Grading Permit. A grading
permit does not include the construction of retaining walls or other structures for which a
Building Permit is required.
90. A preconstruction meeting with the City Engineering Inspector (Engineering Department) is
required prior to commencement of any grading activity.
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 11 of 13
91. Prior to commencement of grading operations, Applicant shall provide to the City a map of
all proposed haul routes to be used for movement of export material. All such routes shall
be subject to the review and approval of the City Engineer. Haul route shall be submitted
prior to issuance of a grading permit. Hauling in excess of 5,000 cubic yards shall be
approved by the City Council (LEMC Section 15.72.065). All required documents shall be
submitted and approved prior to scheduling for City Council.
92. Export sites located within the Lake Elsinore City limits must have an active grading permit.
93. Applicant to provide to the City a video record of the condition of all proposed public City
haul roads. In the event of damage to such roads, the applicant shall pay full cost of restoring
public roads to the baseline condition. A bond may be required to ensure payment of
damages to the public right-of-way, subject to approval of the City Engineer.
94. All grading shall be done under the supervision of a geotechnical engineer. Slopes steeper
than 2 to 1 shall be evaluated for stability and proper erosion control and approved by the
City.
95. Review and approval of the project sediment and erosion control plan shall be completed.
As warranted, a copy of the current SWPPP shall be kept at the project site and be available
for review upon request.
96. Applicant shall obtain and submit applicable environmental clearance document to the
Engineering Department. This approval shall specify that the project is in compliance with
any and all required environmental mitigation triggered by the proposed grading activity.
PRIOR TO BUILDING PERMIT
97. Provide soils, geology and seismic report, including recommendations for parameters for
seismic design of buildings, and walls prior to building permit.
98. All street improvement plans shall be completed and approved by the City Engineer.
99. All required public right-of-way dedications and easements shall be prepared by the
developer or his agent and shall be submitted to the Engineering Department for review and
approval prior to issuance of the building permit.
100. Applicant shall pay all Capital Improvement, TIF, and Master Drainage Fees and any
outstanding plan check fees (LEMC 16.34).
PRIOR TO OCCUPANCY / FINAL APPROVAL
101. All public improvements shall be constructed in accordance with the approved plans or as
condition of this development to the satisfaction of the City Engineer prior to issuance of first
occupancy.
102. Proof of acceptance of maintenance responsibility of slopes, open spaces, landscape areas,
and drainage facilities shall be provided.
103. In the event of damage to City roads from hauling or other construction related activity,
applicant shall pay full cost of restoring public roads to the baseline condition.
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 12 of 13
104. Final soils report showing compliance with recommendations, compaction reports, grade
certifications, monument certification (with tie notes delineated on 8 ½ X 11” Mylar) shall be
submitted in .tif format on a USB flash drive or electronically to the Engineering Department
before final inspection will be scheduled.
105. All required public right-of-way dedications, easements, vacations and easement
agreement(s) shall be recorded with a recorded copy provided to the City prior to first
occupancy.
106. Applicant shall pay all outstanding applicable processing and development fees prior to
occupancy and/or final approval.
107. Applicant shall submit documentation pursuant to City’s Security Release handout.
108. Applicant shall submit as-built all Engineering Department approved project plan sets. After
City approval of paper copy, the developer/owner is responsible for revising the original
mylar plans. Once the original mylars have been approved, the developer shall provide the
City with a digital copy of the “as-built” plans in .tif format.
109. Applicant shall provide AutoCAD and GIS Shape files of all Street and Storm Drain plans.
All data must be in projected coordinate system: NAD 83 State Plane California Zone VI
U.S. Fleet. All parts and elements of the designed system shall be represented discretely.
Include in the attribute table basic data for each feature, such as diameter and length, as
applicable, and for pipes include material (PVC, RCP, etc.) and slope.
CITY OF LAKE ELSINORE FIRE MARSHAL
110. The applicant/operator shall comply with all requirements of the Riverside County Fire
Department Lake Elsinore Office of the Fire Marshal. Questions should be directed to the
Riverside County Fire Department, Lake Elsinore Office of the Fire Marshal at 130 S. Main
St., Lake Elsinore, CA 92530. Phone: (951) 671-3124 Ext. 225.
DEPARTMENT OF ADMINISTRATIVE SERVICES
Annex into the City of Lake Elsinore Community Facilities District No. 2015-2 (Maintenance
Services)
111. Prior to issuance of a building permit, the applicant shall annex into the Community Facilities
District No. 2015-2 (Maintenance Services) or current Community Facilities District in place
at the time of annexation to fund the on-going operation and maintenance of the public right-
of -way landscaped areas and neighborhood parks to be maintained by the City and for street
lights in the public right-of -way for which the City will pay for electricity and a maintenance
fee to Southern California Edison, including parkways, street maintenance, open space and
public storm drains constructed within the development and federal NPDES requirements
to offset the annual negative fiscal impacts of the project. Alternatively, the applicant may
propose alternative financing mechanisms to fund the annual negative fiscal impacts of the
project with respect to Maintenance Services. Applicant shall make a non-refundable
deposit of $15,000 or at the current rate in place at the time of annexation toward the cost
of annexation, formation or other mitigation process, as applicable.
PA 2021-26/ CDR 2021-12 PC: July 19, 2022
Conditions of Approval
Applicant’s Initials: _____ Page 13 of 13
I hereby state that I acknowledge receipt of the approved Conditions of Approval for the above
named project and do hereby agree to accept and abide by all Conditions of Approval as approved
by the Planning Commission of the City of Lake Elsinore on July 19, 2022. I also acknowledge
that all Conditions shall be met as indicated.
Date:
Applicant’s Signature:
Print Name:
Address:
Phone Number: