Loading...
HomeMy WebLinkAbout0003_3_CIP Budget - Exhibit B - CIP PlanCITY OF LAKE ELSINORE Capital Improvement Plan Budget FY2022‐23 - FY2026-27 Table of Contents Introduction ............................................................................................................................... 1 Transmittal Message ................................................................................................................................................... 1  Resolution Adopting Capital Improvement Plan ......................................................................................................... 5  Circulation Projects ................................................................................................................... 8 Annual Citywide Programs .......................................................................................................................................... 8  Crack Seal & Pothole .......................................................................................................................................... 8  Dirt Road Paving .............................................................................................................................................. 11  Intersection Signal Upgrades ........................................................................................................................... 14  Landscape Renovation ..................................................................................................................................... 17  Sidewalk Improvement Program ..................................................................................................................... 20  Sidewalk Survey Program ................................................................................................................................ 23  Sign Inventory .................................................................................................................................................. 26  Slurry Seal Program ......................................................................................................................................... 29  Surface & Minor Drainage Improvements ....................................................................................................... 32  Traffic Striping Program ................................................................................................................................... 35  Auto Center Drive Bridge Seismic Retrofit ................................................................................................................ 38  Chaney Bicycle Lanes – SB 821 .................................................................................................................................. 41  Downtown Pavement Rehabilitation Phase II – SB 1 ................................................................................................ 44  Downtown Sidewalk Improvements – SB 821 .......................................................................................................... 47  Gedge Avenue & Treleven Avenue Pavement Resurfacing ...................................................................................... 51  Highway Safety Improvements (HSIP Cycle 8) .......................................................................................................... 54  Highway Safety Improvements (HSIP Cycle 9) .......................................................................................................... 58  I‐15/Nichols Road Interchange .................................................................................................................................. 61  I‐15/State Route 74 Interchange ............................................................................................................................... 64  Lakeshore/Machado Sidewalk Improvements  ‐ SB 821 ........................................................................................... 67  Main Street Interchange ........................................................................................................................................... 70  Pope Circle Improvements ........................................................................................................................................ 73  SB1 Pavement Rehabilitation Program FY 22/23 ...................................................................................................... 76  Summerhill Drive Extension ...................................................................................................................................... 79  Temescal Canyon Bridge Replacement & Road Widening Phase I ........................................................................... 82  Facility Projects ...................................................................................................................... 85 Building Facilities Renovation ................................................................................................................................... 85  City Hall ..................................................................................................................................................................... 88  City Library ................................................................................................................................................................ 91  Diamond Stadium Tourism Improvements ............................................................................................................... 95  Emergency Operations Center .................................................................................................................................. 98  Fire Station Building Renovations ........................................................................................................................... 101  Mechanic Office Remodel ....................................................................................................................................... 104  Mechanic Shop Expansion & Storage ...................................................................................................................... 107  The Anchor Renovations ......................................................................................................................................... 110  Infrastructure Projects .......................................................................................................... 113 Avenues Drainage Improvements ........................................................................................................................... 113  Camino Del Norte Improvements ........................................................................................................................... 116  Collier Avenue Culvert Drainage Improvements ..................................................................................................... 119  Murrieta Creek Regional Trail Connection .............................................................................................................. 122  Rice Canyon Revetment .......................................................................................................................................... 125  Storm Drain Catch Basin Inlet Filter Installation ..................................................................................................... 128  Park Projects ........................................................................................................................ 131 Aquatic Ecosystem Restoration Project .................................................................................................................. 131  Boat Dock Additions ................................................................................................................................................ 134  Boat Launch Mitigation Restoration ....................................................................................................................... 137  Canyon Hills Park Upgrades .................................................................................................................................... 140  City Park Improvements .......................................................................................................................................... 143  Citywide Park Improvements .................................................................................................................................. 146  Lakepoint Park Fencing ........................................................................................................................................... 149  Lakepoint Park Improvements ................................................................................................................................ 152  Launch Pointe – ADA Ramp ..................................................................................................................................... 155  Launch Pointe Dock Extension and Floating Wave Attenuators ............................................................................. 158  Launch Pointe Sound Wall ...................................................................................................................................... 161  Summerly Park Improvements ................................................................................................................................ 164  Tuscany Hills Park Improvements ........................................................................................................................... 167  Future Projects ..................................................................................................................... 170 Circulation ............................................................................................................................................................... 170  East Lake Circulation ...................................................................................................................................... 170  La Strada Extension........................................................................................................................................ 173  Lake Street Widening ..................................................................................................................................... 176  Main Street Bollards ...................................................................................................................................... 179  Main Street Mill and Overlay ......................................................................................................................... 182  Nichols Road Improvements .......................................................................................................................... 185  SB1 Pavement Rehabilitation Program FY23‐24 ............................................................................................ 188  SB1 Pavement Rehabilitation Program FY24‐25 ............................................................................................ 191  SB1 Pavement Rehabilitation Program FY25‐26 ............................................................................................ 194  SB1 Pavement Rehabilitation Program FY26‐27 ............................................................................................ 197  State Route 74 Widening ............................................................................................................................... 200  Facilities ................................................................................................................................................................... 203  Aquatics Center ............................................................................................................................................. 203  Community Center ........................................................................................................................................ 207  Main Street Archway ..................................................................................................................................... 211  Senior Center Improvements ........................................................................................................................ 214  Aquatics Center ............................................................................................................................................. 203  Infrastructure .......................................................................................................................................................... 217  Third Street Drainage Improvements Phase III .............................................................................................. 217  Parks ........................................................................................................................................................................ 220  Alberhill Village Sports Park ........................................................................................................................... 220  Lake Revitalization Plan ................................................................................................................................. 223  Launch Pointe – The Reserve ......................................................................................................................... 227  Serenity Park Fitness Trail .............................................................................................................................. 232  Snack Bar Improvements ............................................................................................................................... 235  Splash Pad Installation ................................................................................................................................... 237        1 53"/4.*55"-.&44"(& June 14, 2022 The Honorable Mayor and Members of the City Council: On behalf of City Staff, it is my privilege to submit the City of Lake Elsinore’s Capital Improvement Plan (CIP) Budget for Fiscal Years 2022-23 through 2026-27. All Projects presented in this five-year budget have been carefully programmed to ensure the community’s capital improvement needs are met both now and in the future. $*5:0'-",&&-4*/03&130'*-& The City of Lake Elsinore is a community comprised of approximately 63,453 citizens. The City maintains 20 parks on 71 acres throughout the community, which provide recreation opportunities for both the citizens of Lake Elsinore, as well as surrounding communities. The City maintains approximately 189.3 miles of streets within its boundaries. The Lake Elsinore Unified School District provides 25 schools for 21,919 students. The City of Lake Elsinore prides itself on its community focus and quality of life by focusing on public safety, improving recreational opportunities and neighborhoods, delivering the highest quality of public services, preserving and enhancing the City’s economic prosperity, and by meeting the City’s capital improvement needs, we have outlined plans that make the City of Lake Elsinore the desirable place to live, work, and play. &$0/0.*$%&7&-01.&/510-*$: The City’s economic development policy centers on providing a broad range of infrastructure improvements to induce both tourism and business investment. By providing a commercial and residential core that is attractive and possesses adequate infrastructure to support the residential, business, and tourist population, the City of Lake Elsinore is a desirable place to live, work, and play. Notable attractions in this budget document include the Main Street Interchange, Lake Community Center Rehabilitation and significant upgrades to the City’s parks. These projects will provide additional opportunities and access to the City and improve the overall quality of life. -0$"-&$0/0.:"/%-&(*4-"5*7&*.1"$54 On November 3, 2020, residents of the City of Lake Elsinore voted in favor of Measure Z, a locally controlled one percent increase to the transactions and use tax that created additional revenue to address City services, public safety and local recovery needs.   On March 12, 2021, the American Rescue Plan Act of 2021 was signed into law and included an allocation of $350 billion in emergency funding for state, local, territorial, and Tribal governments to respond to the COVID-19 public health emergency or its negative economic impacts. The City of Lake Elsinore is expected to receive $14,967,198 over the next two fiscal years. Both of these events positively impacted the City’s ability to complete the projects identified in the Capital Improvement Program. The projects contained within this document take advantage of these additional sources of revenue. 2 53"/4.*55"-.&44"(&$POUJOVFE $"1*5"-#6%(&510-*$: The purpose of the CIP Budget Document is to serve as a planning tool, which coordinates the financing and scheduling of major projects undertaken and revised annually to address changing needs, priorities, and financial conditions. The capital improvements presented in this document are the City’s major projects, which exceed $20,000 in cost, have long-term life spans, and are generally non-recurring. These projects include land and right-of-way acquisition, design, construction or rehabilitation of public buildings or facilities, public infrastructure design and construction, and park design and construction. The City’s goal in providing a CIP Budget is to develop a multi-year plan for capital improvement, update it annually, and follow through with all capital improvements in accordance with the plan. In determining the relative merit of a proposed project, key management team members evaluate projects for feasibility, community enhancement, infrastructure and historic preservation, and safety. $"1*5"-*.1307&.&/51-"/46.."3: The purpose of the CIP Budget Document is to serve as a planning tool, which co-ordinates the financing and scheduling of major projects undertaken by the City. The CIP document is prepared in accordance with generally accepted accounting principles. This document is dynamic and, consequently, must be revised annually to address changing needs, priorities, and financial conditions. The capital improvements presented in this document are the City’s major projects, which exceed $20,000 in cost, have long-term life spans, and are generally non-recurring. These projects include land and right-of-way acquisition, design, construction or rehabilitation of public buildings or facilities, public infrastructure design and construction, and park design and construction. The City’s goal in providing a CIP Budget is to develop a multi-year plan for capital improvement, update it annually, and follow through with all capital improvements in accordance with the plan. In determining the relative merit of a proposed project, key management team members evaluate projects for feasibility, community enhancement, and safety. 1-"/%&7&-01.&/5 This CIP budget document was developed by incorporating input from key management team members, based on community comments and feedback received throughout the year. This team then, identified and evaluated community needs in the areas of roads/streets, bridges, public buildings, and parks and recreation facilities projects. Each proposed project was reviewed and discussed to ensure funding, timing, and necessity were appropriately addressed. All projects were evaluated by the City’s Planning Commission to ensure consistency with the City of Lake Elsinore General Plan, while considering the City’s long-term vision as developed by the City Council. Projects in this document have been scheduled in each of the five fiscal years based on community needs, as determined by the City Council and availability of funding. The fiscal years 2022-23 through 2026-27 CIP identifies a total of 77 projects consisting of 38 Circulation Projects totaling $312,358,217, 13 Facilities Projects totaling $96,127,531, 7 Infrastructure Projects totaling $13,931,800; and 19 Park Projects totaling $73,238,627. The total cost to complete all of the proposed projects is $495,656,175 of which $87,607,584 is programmed for FY2022-23. Also of note, in this document, there is over $15 million in project costs with unspecified funding sources. These projects have been identified as necessary infrastructure of the City, and will require that funding sources be identified before the projects can commence. 3  53"/4.*55"-.&44"(&$POUJOVFE #6%(&5$"-&/%"3 JANUARY Mid-year budget analysis and revision Council adoption of mid-year operating and CIP budgets FEBRUARY Development of budget parameters/strategic goals Distribution of Budget Preparation Guidelines Budget workshop with key City staff Proposed CIP ("Capital Improvement Plan") projects submitted to Finance MARCH All revenue estimates completed by Finance Budget analysis prepared for review by City Manager APRIL Preliminary operating and CIP budgets prepared CIP project timing and priorities modified based on available revenues MAY Public budget workshop with City Council allowing for public input Public Hearing Planning Commission - CIP Conformance with General Plan JUNE Council adoption of final operating and CIP budgets $*1#6%(&5*/'03."5*0/1307*%&% Information included in this document is as follows: Description of Priorities provides the guidelines used in prioritizing projects. Parameters for CIP Budget Costs Estimates provides standard estimating criteria for project costs. Description of Revenue Sources provides a general description of sources of revenue for the CIP. Projected Revenue Summary provides five-year projections for each of the major sources of funds to be utilized for capital improvements. Project Summary by Type of Project provides summary information of the CIP projects arrayed on spreadsheets by the type project and priority. Comparison Between Projected Revenue and Costs provides summary information of costs versus revenue in each fiscal year by source of funds. Project Descriptions provide a description of each project which includes the scope of the project, costs, sources of funds, the fiscal year(s) in which the project is anticipated to be constructed, and a location map. Future Year Projects provide an opportunity for long range planning that exceeds the five- year period in each of the major groupings (Circulation, Facilities & Infrastructure, Parks and Successor Agency/Housing). 4 53"/4.*55"-.&44"(&$POUJOVFE $0/$-64*0/ The revenue estimates, although conservative, are strictly estimates. The actual amount of funds available for construction will vary based upon the state of the economy. The City’s major revenue sources are primarily received from various county programs, state programs and grants, and development impact fees. The City Council will be updated throughout the year on the status of projects and corresponding revenue sources. The fiscal years 2023-27 Capital Improvement Plan is a result of a total team effort of both City staff and City Council. There are 52 projects which are scheduled to begin design, construction and/or be completed in fiscal year 2022-23. These projects are intended to enhance the safety and quality of life for all citizens in the community. I would like to thank staff and the City Council for all of the contributions that were made in developing the capital budget that will serve as the footprint for the City’s future. Sincerely, Jason Simpson, City Manager 5 3&40-65*0/ RESOLUTION NO. 2022 - XXX RESOLUTION OF THE CITY COUNCIL OF THE CITY OF LAKE ELSINORE, CALIFORNIA, ADOPTING THE CAPITAL IMPROVEMENT PLAN FOR FISCAL YEARS 2022-23 TO 2026-27. WHEREAS, the City of Lake Elsinore annually adopts and updates a long-range program of proposed capital improvement projects with single and multiple-year capital expenditures to guide the planning, scheduling and budgeting of capital improvement projects during the next five-year period; and, WHEREAS, staff has prepared a proposed Capital Improvement Plan (CIP) for Fiscal Years 2022-23 to 2026-27 which includes appropriations for each capital improvement project presented in the budget, with some projects spanning multiple fiscal years; and, WHEREAS, the proposed CIP for Fiscal Years 2022-23 to 2026-27 was submitted to the Lake Elsinore Planning Commission at its regularly scheduled public meeting of May 17, 2022; and, WHEREAS, in accordance with Government Code Section 65401, the Lake Elsinore Planning Commission made a finding at their meeting of May 17, 2022, that the CIP for Fiscal Years 2022-23 to 2026-27 conforms to the Lake Elsinore General Plan; and, WHEREAS, the Planning Commission has caused to be transmitted to the City Council a copy of its report and resolution finding that the CIP for Fiscal Years 2022-23 to 2026-27 conforms to the Lake Elsinore General Plan; and, WHEREAS, the proposed CIP for Fiscal Years 2022-23 to 2026-27 was submitted to the City Council at a noticed public hearing on June 14, 2022; and, WHEREAS, the City Council considered testimony and evidence presented at the public hearing on June 14, 2022, and reviewed the proposed CIP for Fiscal Years 2022-23 through 2026-27 in light of all information presented. NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF LAKE ELSINORE DOES HEREBY RESOLVES, DETER- MINES AND ORDERS AS FOLLOWS: SECTION 1. The Council confirms and accepts the finding of the Lake Elsinore Planning Commission that the CIP for Fiscal Years 2022-23 to 2026-27 conforms to the Lake Elsinore General Plan. 6  3&40-65*0/$POUJOVFE SECTION 2. The City Council finds that the CIP for Fiscal Years 2022-23 to 2026-27 demonstrates the efficient appropriation of public funds relating to the implementation of capital improvement projects anticipated to be undertaken throughout the City over the course of the ensuing five years. The Council further finds that the CIP is a governmental fiscal activity which does not involve a commitment to a specific project that may result in potentially significant impacts on the environment and that the adoption of the CIP is not a "project" within the meaning of California Environmental Quality Act (CEQA). Individual projects developed pursuant to the CIP will be subject to CEQA. SECTION 3. The CIP for Fiscal Years 2022-23 to 2026-27 is hereby approved and adopted. A copy of the CIP for Fiscal Years 2022-23 to 2026-27 hereby adopted and certified by the City Clerk, shall be filed with the City Manager or a designated representative, and a further copy so certified shall be placed and shall remain on file in the Office of the City Clerk where it shall be available for inspection. SECTION 4. This Resolution shall take effect from and after the date of its passage and adoption. PASSED AND ADOPTED on the 14th day of June, 2022. ______________________________ Timothy J. Sheridan, Mayor ATTEST: ____________________________ Candice Alvarez City Clerk 7 3&40-65*0/$POUJOVFE STATE OF CALIFORNIA ) COUNTY OF RIVERSIDE ) ss. CITY OF LAKE ELSINORE ) I, Candice Alvarez, City Clerk of the City of Lake Elsinore, California, hereby certify that Resolution No. 2022-XXX was adopted by the City Council of the City of Lake Elsinore, California, at the regular meeting of June 14, 2022, and that the same was adopted by the following vote: AYES: NOES: ABSENT: ABSTAIN: Candice Alvarez City Clerk ANNUAL CITYWIDE CRACK SEAL & POTHOLE IMPROVEMENTS PROGRAM Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Administration - Public Works Type Capital Improvement Description This project includes annual crack sealing and pothole repair services throughout the city. Images City Zones City map used for various city projects. Details If funding source is other, please explain. None Type of Project Resurface Current Road Location Benet to Community This project represents the City's efforts to proactively maintain and extend the useful life of aging asphalt roadway surfaces. The project is annual and ongoing. 8 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $10,000 $10,000 $10,000 $10,000 $10,000 Construction/Maintenance $890,000 $490,000 $490,000 $490,000 $490,000 Total $900,000 $500,000 $500,000 $500,000 $500,000 Capital Cost FY2023 Budget $900,000 Total Budget $2.9M Capital Cost by Year Administration Construction/Mai… 2023 2024 2025 2026 2027 $900,000.00 $500,000.00 $500,000.00 $500,000.00 $500,000.00 $0 $250K$500K$750K Capital Cost for Budgeted Years TOTAL $2,900,000.00 Administration (2%)$50,000.00 Construction/Maintenance (98 9 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Measure A $900,000 $500,000 $500,000 $500,000 $500,000 Total $900,000 $500,000 $500,000 $500,000 $500,000 Funding Sources FY2023 Budget $900,000 Total Budget $2.9M Funding Sources by Year Measure A 2023 2024 2025 2026 2027 $900,000.00 $500,000.00 $500,000.00 $500,000.00 $500,000.00 $0 $250K$500K$750K Funding Sources for Budgeted Years TOTAL $2,900,000.00 Measure A (100%)$2,900,000.0 10 ANNUAL CITYWIDE DIRT ROAD PAVING PROGRAM Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 06/30/2022 Est. Completion Date 06/30/2027 Department Administration - Public Works Type Capital Improvement Description Pave the dirt road portions of Morton Avenue and Hill Avenue off Chaney Street; Miller Street between Palm Drive and Strickland Avenue; Herbert, Morton, Lucerne, and Marian off East Lakeshore Drive; Dawes Street from Avenue 6 to the end of the street; Acacia Street from Country Club Boulevard to the end of the street; and Baker, Bromley, and Bunker off Riverside Drive. E. Hill Street cul-de-sac. Images Morton and Hill Avenue Miller Street Herbert, Morton Avenue and Lucerne, Marian Street East Hill Street Baker Street, Bunker Street and Bromley Avenue Details If funding source is other, please explain.Unspecied Type of Project New Road Benet to Community This project will eliminate the remaining dirt roads within the city. This project is annual and ongoing. 11 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $20,000 $20,000 $20,000 $20,000 $20,000 Construction/Maintenance $980,000 $980,000 $980,000 $980,000 $980,000 Total $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 Capital Cost FY2023 Budget $1,000,000 Total Budget $5M Capital Cost by Year Administration Construction/Mai… 2023 2024 2025 2026 2027 $1,000,000.00 $1,000,000.00 $1,000,000.00 $1,000,000.00 $1,000,000.00 $0 $250 $500$750$… Capital Cost for Budgeted Years TOTAL $5,000,000.00 Administration (2%)$100,000.0 Construction/Maintenance (98 12 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Gas Tax $49,771 Measure Z $853,822 Other $96,407 $1,000,000 $1,000,000 $1,000,000 $1,000,000 Total $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 Funding Sources FY2023 Budget $1,000,000 Total Budget $5M Funding Sources by Year Gas Tax Measure Z Other 2023 2024 2025 2026 2027 $1,000,000.00 $1,000,000.00 $1,000,000.00 $1,000,000.00 $1,000,000.00 $0 $250 $500$750$… Funding Sources for Budgeted Years TOTAL $5,000,000.00 Gas Tax (1%) $49,771.00 Measure Z (17%) $853,822.00 Other (82%) $4,096,407.00 13 ANNUAL CITYWIDE INTERSECTION SIGNAL UPGRADES Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Circulation Type Capital Improvement Description Signal controller upgrades at various intersections within the City. The upgrades include video detection, controllers, wireless communications, and other safety improvements. Details If funding source is other, please explain. None Type of Project Other Location Benet to Community Upgrading trafc signals to modern equipment will decrease maintenance costs, improve functionality, and increase safety. 14 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Design $1,000 $1,000 $1,000 $1,000 $1,000 Construction/Maintenance $200,000 $200,000 $200,000 $200,000 $200,000 Total $201,000 $201,000 $201,000 $201,000 $201,000 Capital Cost FY2023 Budget $201,000 Total Budget $1.005M Capital Cost by Year Design Construction/Mai… 2023 2024 2025 2026 2027 $201,000.00 $201,000.00 $201,000.00 $201,000.00 $201,000.00 $0 $50K$100K$150K$… Capital Cost for Budgeted Years TOTAL $1,005,000.00 Design (0%) $5,000.00 Construction/Maintenance (10 15 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Trafc Impact Fee $201,000 $201,000 $201,000 $201,000 $201,000 Total $201,000 $201,000 $201,000 $201,000 $201,000 Funding Sources FY2023 Budget $201,000 Total Budget $1.005M Funding Sources by Year Trafc Impact Fee 2023 2024 2025 2026 2027 $201,000.00 $201,000.00 $201,000.00 $201,000.00 $201,000.00 $0 $50K$100K$150K$… Funding Sources for Budgeted Years TOTAL $1,005,000.00 Trafc Impact Fee (100%)$1,005 16 ANNUAL CITYWIDE LANDSCAPE RENOVATION PROGRAM Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Administration - Public Works Type Capital Improvement Description This project provides for the rehabilitation of landscaping, median, and irrigation equipment within city-maintained right-of-way areas. Lakeshore Drive, Lincoln Street, Terra Cotta Road, Via De La Valle and Rail Road Canyon Road. Images Lakeshore Drive Lincoln Street Terra Cotta Road Via De La Valle Rail Road Canyon Road Details If funding source is other, please explain. None Type of Project Other Location 17 Benet to Community This project improves landscaping and irrigation within specic right-of-way areas, including the installation of drought- tolerant plant materials and water-efcient irrigation equipment. Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $20,000 $20,000 $20,000 $20,000 $20,000 Construction/Maintenance $2,000,000 $400,000 $400,000 $400,000 $400,000 Total $2,020,000 $420,000 $420,000 $420,000 $420,000 Capital Cost FY2023 Budget $2,020,000 Total Budget $3.7M Capital Cost by Year Administration Construction/Mai… 2023 2024 2025 2026 2027 $2,020,000.00 $420,000.00 $420,000.00 $420,000.00 $420,000.00 $0 $50…$1M $1.5M$… Capital Cost for Budgeted Years TOTAL $3,700,000.00 Administration (3%)$100,000.0 Construction/Maintenance (97 18 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Capital Improvement Fund $420,000 $420,000 $420,000 $420,000 $420,000 Total $420,000 $420,000 $420,000 $420,000 $420,000 Funding Sources FY2023 Budget $420,000 Total Budget $2.1M Funding Sources by Year Capital Improve… 2023 2024 2025 2026 2027 $420,000.00 $420,000.00 $420,000.00 $420,000.00 $420,000.00 $0 $120K$240K$360K Funding Sources for Budgeted Years TOTAL $2,100,000.00 Capital Improvement Fund (10 19 ANNUAL CITYWIDE SIDEWALK IMPROVEMENT PROGRAM Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Infrastructure Type Capital Improvement Description This project includes the design and construction of sidewalk improvements at various locations within the City. Details If funding source is other, please explain. None New Facility or Replacement New Location Benet to Community This project will construct ADA compliant sidewalk, curb, and gutter along with safe and continuous sidewalk for students and the community. 20 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $20,000 $10,000 $10,000 $10,000 $10,000 Design $70,000 $35,000 $35,000 $35,000 $35,000 Engineering $10,000 $10,000 $10,000 $10,000 $10,000 Construction $780,000 $150,000 $150,000 $150,000 $150,000 Total $880,000 $205,000 $205,000 $205,000 $205,000 Capital Cost FY2023 Budget $880,000 Total Budget $1.7M Capital Cost by Year Administration Design Engineering Construction 2023 2024 2025 2026 2027 $880,000.00 $205,000.00 $205,000.00 $205,000.00 $205,000.00 $0 $250K$500K$750K Capital Cost for Budgeted Years TOTAL $1,700,000.00 Administration (4%)$60,000.00 Design (12%) $210,000.00 Engineering (3%) $50,000.00 Construction (81%)$1,380,000. 21 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Measure A $100,000 $100,000 $100,000 $100,000 Measure Z $880,000 $105,000 $105,000 $105,000 $105,000 Total $880,000 $205,000 $205,000 $205,000 $205,000 Funding Sources FY2023 Budget $880,000 Total Budget $1.7M Funding Sources by Year Measure A Measure Z 2023 2024 2025 2026 2027 $880,000.00 $205,000.00 $205,000.00 $205,000.00 $205,000.00 $0 $250K$500K$750K Funding Sources for Budgeted Years TOTAL $1,700,000.00 Measure A (24%) $400,000.00 Measure Z (76%)$1,300,000.00 22 ANNUAL CITYWIDE SIDEWALK SURVEY PROGRAM Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Administration - Public Works Type Capital Improvement Description As part of the City's Sidewalk Inspection Program, ALL sidewalks are to be inspected yearly and construction will be done, if necessary. The contractor performs documents, provides repair recommendations, and a cost analysis for repairs which would identify the potential hazards citywide. The survey will be the basis for construction. Images City Zones Details If funding source is other, please explain. None Type of Project Other Location Benet to Community Safer sidewalks that provide a better walking path with no trip hazards, remain ADA-compliant, and improve and provide a better quality of life for the public. 23 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 FY2025 FY2026 FY2027 Administration $20,000 $20,000 $20,000 $20,000 $20,000 Construction/Maintenance $135,884 $535,000 $535,000 $535,000 $535,000 $535,000 Total $135,884 $555,000 $555,000 $555,000 $555,000 $555,000 Capital Cost Total To Date $135,884 FY2023 Budget $555,000 Total Budget $2.775M Capital Cost by Year Administration Construction/Mai… 2023 2024 2025 2026 2027 $555,000.00 $555,000.00 $555,000.00 $555,000.00 $555,000.00 $0 $150K$300K$450K Capital Cost for Budgeted Years TOTAL $2,775,000.00 Administration (4%)$100,000.0 Construction/Maintenance (96 24 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Measure A $310,000 $310,000 $310,000 $310,000 $319,600 Trafc Impact Fee $245,000 Other $245,000 $245,000 $245,000 $235,400 Total $555,000 $555,000 $555,000 $555,000 $555,000 Funding Sources FY2023 Budget $555,000 Total Budget $2.775M Funding Sources by Year Measure A Trafc Impact Fee Other 2023 2024 2025 2026 2027 $555,000.00 $555,000.00 $555,000.00 $555,000.00 $555,000.00 $0 $150K$300K$450K Funding Sources for Budgeted Years TOTAL $2,775,000.00 Measure A (56%)$1,559,600.00 Trafc Impact Fee (9%)$245,00 Other (35%) $970,400.00 25 ANNUAL CITYWIDE SIGN INVENTORY Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Administration - Public Works Type Capital Improvement Description Check reectivity and inventory/GIS/on all Citywide street signs. With surveys in place, staff can begin to replace signs that are not in compliance. Images City Zones Details If funding source is other, please explain. None Type of Project None Location Benet to Community Keeping drivers safe is the biggest benet of trafc signs. City to be in compliance with Minimum Sign Retroreectivity requirements. 26 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 FY2025 FY2026 FY2027 Administration $10,000 $10,000 $10,000 $10,000 $10,000 Engineering $30,000 $30,000 $30,000 $30,000 $30,000 Construction/Maintenance $101,469 $100,000 $100,000 $100,000 $100,000 $100,000 Total $101,469 $140,000 $140,000 $140,000 $140,000 $140,000 Capital Cost Total To Date $101,469 FY2023 Budget $140,000 Total Budget $700K Capital Cost by Year Administration Engineering Construction/Mai… 2023 2024 2025 2026 2027 $140,000.00 $140,000.00 $140,000.00 $140,000.00 $140,000.00 $0 $40K $80K$120K Capital Cost for Budgeted Years TOTAL $700,000.00 Administration (7%)$50,000.00 Engineering (21%) $150,000.00 Construction/Maintenance (71 27 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Trafc Impact Fee $140,000 $140,000 $140,000 $140,000 $140,000 Total $140,000 $140,000 $140,000 $140,000 $140,000 Funding Sources FY2023 Budget $140,000 Total Budget $700K Funding Sources by Year Trafc Impact Fee 2023 2024 2025 2026 2027 $140,000.00 $140,000.00 $140,000.00 $140,000.00 $140,000.00 $0 $40K $80K$120K Funding Sources for Budgeted Years TOTAL $700,000.00 Trafc Impact Fee (100%)$700, 28 ANNUAL CITYWIDE SLURRY SEAL PROGRAM Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Circulation Type Capital Improvement Description This project includes the design, inspection, striping, monument preservation, and slurry seal of asphalt paved roadways maintained by the City. Selected roadways are programmed annually for slurry seal in accordance with the City's Pavement Management Plan. Details If funding source is other, please explain. None Type of Project Resurface Current Road Location Benet to Community The Citywide Slurry Seal Program provides for the maintenance and protection of existing asphalt pavement surfaces by lling surface cracks and voids. Slurry seal is one of the most versatile and cost-effective methods to extend the useful life of the City's paved roadways. 29 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $10,000 $10,000 $10,000 $10,000 $10,000 Design $12,000 $12,000 $12,000 $12,000 $12,000 Construction/Maintenance $1,430,000 $480,000 $480,000 $480,000 $480,000 Total $1,452,000 $502,000 $502,000 $502,000 $502,000 Capital Cost FY2023 Budget $1,452,000 Total Budget $3.46M Capital Cost by Year Administration Design Construction/Mai… 2023 2024 2025 2026 2027 $1,452,000.00 $502,000.00 $502,000.00 $502,000.00 $502,000.00 $0 $400K$800K$1.2M Capital Cost for Budgeted Years TOTAL $3,460,000.00 Administration (1%)$50,000.00 Design (2%) $60,000.00 Construction/Maintenance (97 30 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Measure A $707,000 $390,010 $427,635 $471,200 $502,000 Measure Z $745,000 $111,990 $74,365 $30,800 $0 Total $1,452,000 $502,000 $502,000 $502,000 $502,000 Funding Sources FY2023 Budget $1,452,000 Total Budget $3.46M Funding Sources by Year Measure A Measure Z 2023 2024 2025 2026 2027 $1,452,000.00 $502,000.00 $502,000.00 $502,000.00 $502,000.00 $0 $400K$800K$1.2M Funding Sources for Budgeted Years TOTAL $3,460,000.00 Measure A (72%)$2,497,845.00 Measure Z (28%) $962,155.00 31 ANNUAL CITYWIDE SURFACE AND MINOR DRAINAGE IMPROVEMENTS Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Circulation Type Capital Improvement Description This ongoing project provides for the installation of new or replacement drainage facilities located within City right-of-way areas.  The location will be determined by the updated Master Drainage Plan that depicts 12 different locations that will need to be upgraded.  Images Annual Roadway Drainage Details If funding source is other, please explain. OTHER - NPDES FUNDS Type of Project Other Location Benet to Community This project ensures that drainage facilities are functioning properly to support the integrity of the roadways during inclement weather. 32 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $5,000 $5,000 $5,000 $5,000 $5,000 Design $25,000 $30,000 $35,000 $35,000 $35,000 Engineering $10,000 $10,000 $10,000 $10,000 $10,000 Construction/Maintenance $905,000 $900,000 $900,000 $900,000 $900,000 Total $945,000 $945,000 $950,000 $950,000 $950,000 Capital Cost FY2023 Budget $945,000 Total Budget $4.74M Capital Cost by Year Administration Design Engineering Construction/Mai… 2023 2024 2025 2026 2027 $945,000.00 $945,000.00 $950,000.00 $950,000.00 $950,000.00 $0 $250K$500K$750K Capital Cost for Budgeted Years TOTAL $4,740,000.00 Administration (1%)$25,000.00 Design (3%) $160,000.00 Engineering (1%) $50,000.00 Construction/Maintenance (95 33 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Measure A $215,000 $230,000 $230,000 $230,000 Storm Drain $195,000 Other $750,000 $730,000 $720,000 $720,000 $720,000 Total $945,000 $945,000 $950,000 $950,000 $950,000 Funding Sources FY2023 Budget $945,000 Total Budget $4.74M Funding Sources by Year Measure A Storm Drain Other 2023 2024 2025 2026 2027 $945,000.00 $945,000.00 $950,000.00 $950,000.00 $950,000.00 $0 $250K$500K$750K Funding Sources for Budgeted Years TOTAL $4,740,000.00 Measure A (19%) $905,000.00 Storm Drain (4%) $195,000.00 Other (77%) $3,640,000.00 34 ANNUAL CITYWIDE TRAFFIC STRIPPING PROGRAM Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Administration - Public Works Type Capital Improvement Description This project provides for repairing and/or replacing pavement markings, street striping and legends throughout the city. Our goal is to restripe Stop Bar & Legends in a thermal plastic coating which will extend the life of the striping for up to ve years instead of one to two years with regular striping paint. Images City Zones Details If funding source is other, please explain. None Type of Project Resurface Current Road Location Benet to Community This project maintains markings that identify travel lanes and other guidance markings for motorists, pedestrians, bicyclists, and other forms of transportation. 35 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $10,000 $10,000 $10,000 $10,000 $10,000 Construction/Maintenance $320,000 $320,000 $320,000 $320,000 $320,000 Total $330,000 $330,000 $330,000 $330,000 $330,000 Capital Cost FY2023 Budget $330,000 Total Budget $1.65M Capital Cost by Year Administration Construction/Mai… 2023 2024 2025 2026 2027 $330,000.00 $330,000.00 $330,000.00 $330,000.00 $330,000.00 $0 $80K$160K$240K$… Capital Cost for Budgeted Years TOTAL $1,650,000.00 Administration (3%)$50,000.00 Construction/Maintenance (97 36 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Measure A $330,000 $330,000 $330,000 $330,000 $330,000 Total $330,000 $330,000 $330,000 $330,000 $330,000 Funding Sources FY2023 Budget $330,000 Total Budget $1.65M Funding Sources by Year Measure A 2023 2024 2025 2026 2027 $330,000.00 $330,000.00 $330,000.00 $330,000.00 $330,000.00 $0 $80K$160K$240K$… Funding Sources for Budgeted Years TOTAL $1,650,000.00 Measure A (100%)$1,650,000.00 37 AUTO CENTER DRIVE BRIDGE SEISMIC RETROFIT Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 01/01/2019 Est. Completion Date 12/30/2025 Department Circulation Type Capital Improvement Description This project includes the seismic retrot of the bridge over the San Jacinto River at Auto Center Drive. Images Auto Center Drive Bridge Details If funding source is other, please explain. Unspecied *Measure Z construction possible otherwise Unspecied Type of Project Other Location Benet to Community This project will improve trafc and safety circulation. 38 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 FY2025 Administration $28,241 $10,000 $10,000 $20,000 Design $48,285 Engineering $307,194 $365,000 $261,615 Construction/Maintenance $4,027,000 Total $383,720 $375,000 $271,615 $4,047,000 Capital Cost Total To Date $383,720 FY2023 Budget $375,000 Total Budget $4.694M Capital Cost by Year Administration Engineering Construction/Mai… 2023 2024 2025 $375,000.00 $271,615.00 $4,047,000.00 $0 $1M $2M $3M$… Capital Cost for Budgeted Years TOTAL $4,693,615.00 Administration (1%)$40,000.00 Engineering (13%) $626,615.00 Construction/Maintenance (86 39 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 Grants $1,532,000 Measure Z $375,000 $271,615 $2,515,000 Total $375,000 $271,615 $4,047,000 Funding Sources FY2023 Budget $375,000 Total Budget $4.694M Funding Sources by Year Grants Measure Z 2023 2024 2025 $375,000.00 $271,615.00 $4,047,000.00 $0 $1M $2M $3M$… Funding Sources for Budgeted Years TOTAL $4,693,615.00 Grants (33%) $1,532,000.00 Measure Z (67%) $3,161,615.00 40 CHANEY BICYCLE LANES - SB 821 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 04/18/2022 Est. Completion Date 06/30/2025 Department Circulation Type Capital Improvement Description Install Class II bicycle lanes on Chaney Street between Flint Street and Collier Avenue in both directions. Images SB 821 CHANEY BIKE LANES Details If funding source is other, please explain. OTHER STARTS FY 21/22 Type of Project Other Location Benet to Community Accommodates bicycle safety, comfort, usability. Class II bicycle lanes on Chaney Street provides continuity to future bicycle facilities project. 41 Capital Cost Breakdown Capital Cost To Date FY2023 Administration $10,000 Design $25,100 Engineering $4,900 Construction/Maintenance $39,000 Total $25,100 $53,900 Capital Cost Total To Date $25,100 FY2023 Budget $53,900 Total Budget $53.9K Capital Cost by Year Administration Engineering Construction/Mai… 2023 $53,900.00 $0 $15K $30K $45K Capital Cost for Budgeted Years TOTAL $53,900.00 Administration (19%)$10,000.00 Engineering (9%) $4,900.00 Construction/Maintenance (72 42 Funding Sources Breakdown Funding Sources To Date FY2023 Measure A $14,400 SB821 $39,500 Other $25,100 Total $25,100 $53,900 Funding Sources Total To Date $25,100 FY2023 Budget $53,900 Total Budget $53.9K Funding Sources by Year Measure A SB821 2023 $53,900.00 $0 $15K $30K $45K Funding Sources for Budgeted Years TOTAL $53,900.00 Measure A (27%) $14,400.00 SB821 (73%) $39,500.00 43 DOWNTOWN PAVEMENT REHABILITATION PHASE 2 - SB1 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 06/01/2022 Est. Completion Date 06/30/2023 Department Infrastructure Type Capital Improvement Description The City receives Road Maintenance and Rehabilitation funds annually as part of the Road Repair and Accountability Act of 2017. Each year, the City must declare a specic project in May. The selected project is based on Pavement Conditions Indices (PCI) and Average Daily Trafc (ADT) demand. Details If funding source is other, please explain. None New Facility or Replacement Replacement Location Benet to Community This project represents the City's efforts to proactively maintain and extend the useful life of aging asphalt roadway surfaces. 44 Capital Cost Breakdown Capital Cost FY2023 Administration $15,000 Design $20,000 Construction $2,506,109 Total $2,541,109 Capital Cost FY2023 Budget $2,541,109 Total Budget $2.541M Capital Cost by Year Administration Design Construction 2023 $2,541,109.00 $0 $800K $1.6M$2.… Capital Cost for Budgeted Years TOTAL $2,541,109.00 Administration (1%)$15,000.00 Design (1%) $20,000.00 Construction (99%)$2,506,109.0 45 Funding Sources Breakdown Funding Sources FY2023 Gas Tax $620,544 SB 1 $1,920,565 Total $2,541,109 Funding Sources FY2023 Budget $2,541,109 Total Budget $2.541M Funding Sources by Year Gas Tax SB 1 2023 $2,541,109.00 $0 $800K $1.6M$2.… Funding Sources for Budgeted Years TOTAL $2,541,109.00 Gas Tax (24%) $620,544.00 SB 1 (76%) $1,920,565.00 46 DOWNTOWN SIDEWALK IMPROVEMENTS - SB 821 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 04/25/2022 Est. Completion Date 06/30/2025 Department Circulation Type Capital Improvement Description Construct ADA compliant sidewalk, curb, gutter and curb ramps on Sumner Avenue, Chestnut Street, Lakeshore Drive and other in-ll locations through Downtown area, and Class II bicycle lanes on Sumner Ave to provide safe path of travel and connectivty for pedestrians and bicyclists. Images SB 821 DOWNTOWN SIDEWALK IMPROVEMENTS Details If funding source is other, please explain. DESIGN WILL START THIS CURRENT FY AND CARRY OVER. DESIGN COST WILL BE OVER THE 50% MATCH WHICH IS CITY OBLIGATION Type of Project None Location Benet to Community Improvements will separate the pedestrians and motorists from sharing the roadway and provide safer travel way for pedestrians. Bicycle lanes on Sumner Avenue will better accommodate bicyclist safety, comfort, and usability, and provide continuity to existing routes and future bicycle facilities project. 47 Capital Cost Breakdown Capital Cost To Date FY2023 Administration $5,000 Design $28,000 $17,000 Engineering $1,000 Construction/Maintenance $397,965 Total $28,000 $420,965 Capital Cost Total To Date $28,000 FY2023 Budget $420,965 Total Budget $420.965K Capital Cost by Year Administration Design Engineering Construction/Mai… 2023 $420,965.00 $0 $120K$240K$360K Capital Cost for Budgeted Years TOTAL $420,965.00 Administration (1%) $5,000.00 Design (4%) $17,000.00 Engineering (0%) $1,000.00 Construction/Maintenance (95 48 Funding Sources Breakdown Funding Sources To Date FY2023 Measure A $204,982 SB821 $215,983 Other $28,000 Total $28,000 $420,965 Funding Sources Total To Date $28,000 FY2023 Budget $420,965 Total Budget $420.965K Funding Sources by Year Measure A SB821 2023 $420,965.00 $0 $120K$240K$360K Funding Sources for Budgeted Years TOTAL $420,965.00 Measure A (49%) $204,982.00 SB821 (51%) $215,983.00 49 Operational Costs Breakdown Operational Costs FY2025 FY2026 FY2027 General Maintenance $10,000 $10,000 $10,000 Total $10,000 $10,000 $10,000 Operational Costs Total Budget $30K Operational Costs by Year General Maintena… 2025 2026 2027 $10,000.00 $10,000.00 $10,000.00 $0 $2.5K $5K $7.5K$… Operational Costs for Budgeted Years TOTAL $30,000.00 General Maintenance (100%)$3 50 GEDGE AVE AND TRELEVEN AVE PAVEMENT RESURFACING Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 08/01/2022 Est. Completion Date 12/29/2022 Department Circulation Type Capital Improvement Description Elsinore Valley Municipal Water District is constructing a parking lot adjacent to Gedge Avenue and Treleven Avenue, along with resurfacing the pavement on Gedge Avenue and Treleven Avenue. Details If funding source is other, please explain. None Type of Project New Road Location Benet to Community The City will share in the cost with Elsinore Valley Municipal Water District to repave deteriorated surface streets. This project meets the Citywide Paving Plan recommendations. 51 Capital Cost Breakdown Capital Cost FY2023 Construction/Maintenance $250,000 Total $250,000 Capital Cost FY2023 Budget $250,000 Total Budget $250K Capital Cost by Year Construction/Mai… 2023 $250,000.00 $0 $2…$60K$120K$180K Capital Cost for Budgeted Years TOTAL $250,000.00 Construction/Maintenance (10 52 Funding Sources Breakdown Funding Sources FY2023 Measure Z $250,000 Total $250,000 Funding Sources FY2023 Budget $250,000 Total Budget $250K Funding Sources by Year Measure Z 2023 $250,000.00 $0 $2…$60K$120K$180K Funding Sources for Budgeted Years TOTAL $250,000.00 Measure Z (100%)$250,000.00 53 HIGHWAY SAFETY IMPROVEMENTS (HSIP CYCLE 8) Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 02/14/2022 Est. Completion Date 06/20/2022 Department Engineering Type Capital Improvement Description Install advanced delemma zone detection, ashing warning beacons, and left turn phasing at eight (8) intersections within the City. Intersections are as follows: Railroad Canyon Road & Church Road, Lake Street & Alberhill Ranch Road, Lake Street & Lakeshore Drive, Lincoln Street & Machado Street, Railroad Canyon Road & Summerhill Drive, Railroad Canyon Road & Canyon Hills Road, Diamond Drive & Auto Center Drive, Diamond Drive & Lakeshore Drive/Mission Trail. Images HSIP CYCLE 8 VICINITY MAP Details If funding source is other, please explain. None Type of Project Other Location Benet to Community Installing advanced dilemma zone detections for high-speed approaches increases safety. 54 Capital Cost Breakdown Capital Cost To Date FY2023 Design $74,987 Engineering $267 $50,046 Construction/Maintenance $700,000 Total $75,254 $750,046 Capital Cost Total To Date $75,254 FY2023 Budget $750,046 Total Budget $750.046K Capital Cost by Year Engineering Construction/Mai… 2023 $750,046.00 $0 $200K$400K$600K Capital Cost for Budgeted Years TOTAL $750,046.00 Engineering (7%) $50,046.00 Construction/Maintenance (93 55 Funding Sources Breakdown Funding Sources To Date FY2023 Grants $75,254 $750,046 Total $75,254 $750,046 Funding Sources Total To Date $75,254 FY2023 Budget $750,046 Total Budget $750.046K Funding Sources by Year Grants 2023 $750,046.00 $0 $200K$400K$600K Funding Sources for Budgeted Years TOTAL $750,046.00 Grants (100%) $750,046.00 56 Operational Costs Breakdown Operational Costs FY2024 FY2025 FY2026 FY2027 General Maintenance $250 $250 $250 $250 Total $250 $250 $250 $250 Operational Costs Total Budget $1K Operational Costs by Year General Maintena… 2024 2025 2026 2027 $250.00 $250.00 $250.00 $250.00 $0 $2…$60 $120$180 Operational Costs for Budgeted Years TOTAL $1,000.00 General Maintenance (100%)$1, 57 HIGHWAY SAFETY IMPROVEMENTS (HSIP CYCLE 9) Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 09/01/2021 Est. Completion Date 06/28/2024 Department Circulation Type Capital Improvement Description Install advanced dilemma zone detection, protected left turns, and pedestrian countdown heads at ten (10) various intersections throughout the City. Details If funding source is other, please explain. None Type of Project Other Location Benet to Community Installing advanced dilemma zone detections for high-speed approaches increases safety. 58 Capital Cost Breakdown Capital Cost To Date FY2023 Administration $708 Construction/Maintenance $112,735 $1,235,457 Total $113,443 $1,235,457 Capital Cost Total To Date $113,443 FY2023 Budget $1,235,457 Total Budget $1.235M Capital Cost by Year Construction/Mai… 2023 $1,235,457.00 $0 $1…$30…$60…$90… Capital Cost for Budgeted Years TOTAL $1,235,457.00 Construction/Maintenance (10 59 Funding Sources Breakdown Funding Sources To Date FY2023 Grants $113,443 $1,235,457 Total $113,443 $1,235,457 Funding Sources Total To Date $113,443 FY2023 Budget $1,235,457 Total Budget $1.235M Funding Sources by Year Grants 2023 $1,235,457.00 $0 $1…$30…$60…$90… Funding Sources for Budgeted Years TOTAL $1,235,457.00 Grants (100%) $1,235,457.00 60 I-15 NICHOLS ROAD INTERCHANGE Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 05/16/2022 Est. Completion Date 05/27/2025 Department Circulation Type Capital Improvement Description This project will initiate the Project Study Report (PSR) and Plan Approval/Environmental Document (PA&ED) phase of work for future modications to the existing I-15/Nichols Road Interchange.  Scope of work for the phase includes: preparation of preliminary engineering alternative analysis, preparation of preliminary environmental analysis report (PEAR), trafc engineering performance assessment (TEPA), development of a cost estimate and project schedule, trafc impact analysis, value analysis, right-of-way engineering and appraisal, preparation of environmental studies, project management and coordination, preparation of nal project report preparation of nal environmental assessment report, and other reports as needed. Images I15/Nichols Road Interchange Details If funding source is other, please explain. Other = Unspecied New Facility or Replacement Replacement Location Benet to Community This project improves trafc circulation and reduces trafc congestion at the I-15/Nichols Road Interchange.  61 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $20,000 $10,000 $10,000 $3,000,000 Design $4,500,000 Engineering $2,500,000 Construction $35,000,000 Total $2,520,000 $10,000 $10,000 $7,500,000 $35,000,000 Capital Cost FY2023 Budget $2,520,000 Total Budget $45.04M Capital Cost by Year Administration Design Engineering Construction 2023 2024 2025 2026 2027 $2,520,000.00 $10,000.00 $10,000.00 $7,500,000.00 $35,000,000.00 $0 $10M $20M$30M Capital Cost for Budgeted Years TOTAL $45,040,000.00 Administration (7%)$3,040,000 Design (10%) $4,500,000.00 Engineering (6%)$2,500,000.00 Construction (78%)$35,000,00 62 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Gas Tax $20,000 TUMF $2,500,000 NPDES $10,000 $10,000 $7,500,000 $35,000,000 Total $2,520,000 $10,000 $10,000 $7,500,000 $35,000,000 Funding Sources FY2023 Budget $2,520,000 Total Budget $45.04M Funding Sources by Year Gas Tax TUMF NPDES 2023 2024 2025 2026 2027 $2,520,000.00 $10,000.00 $10,000.00 $7,500,000.00 $35,000,000.00 $0 $10M $20M$30M Funding Sources for Budgeted Years TOTAL $45,040,000.00 Gas Tax (0%) $20,000.00 TUMF (6%) $2,500,000.00 NPDES (94%) $42,520,000.00 63 I15/STATE ROUTE 74 INTERCHANGE Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 01/01/2019 Est. Completion Date 12/30/2024 Department Circulation Type Capital Improvement Description This project will initiate the Plan Approval/Environmental Document (PA&ED) phase of work for future modications to the existing I- 15/SR 74 Interchange at Central Avenue. Proposed improvements include the construction of a northbound loop entry ramp with acceleration/deceleration lanes; realignment of the northbound entry/exit ramps; widening of the southbound entry/exit ramps, including acceleration/deceleration lanes; widening of SR 74 from Riverside Drive to Central Avenue from two (2) to four (4) lanes; widening of Collier Avenue to Cambern Avenue from six (6) to eight (8) lanes; and construction of the Riverside Drive overcrossing and road extensions. Images I15/State Route 74 Interchange Details If funding source is other, please explain. Unspecied Type of Project Other Location Benet to Community This project improves trafc circulation and reduces trafc congestion at the I-15/SR 74 interchange. 64 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 FY2026 Administration $69,386 Design $51,302 $2,500,000 $1,500,000 Engineering $1,848,085 Land/Right-of-way $3,000,000 Construction/Maintenance $35,000,000 Total $1,968,773 $5,500,000 $1,500,000 $35,000,000 Capital Cost Total To Date $1,968,773 FY2023 Budget $5,500,000 Total Budget $42M Capital Cost by Year Design Land/Right-of-w… Construction/Mai… 2023 2024 2026 $5,500,000.00 $1,500,000.00 $35,000,000.00 $0 $10M $20M$30M Capital Cost for Budgeted Years TOTAL $42,000,000.00 Design (10%) $4,000,000.00 Land/Right-of-way (7%)$3,000 Construction/Maintenance (83 65 Funding Sources Breakdown Funding Sources To Date FY2023 FY2024 FY2027 Measure A $187,674 $178,335 TUMF $1,781,099 $5,000,000 Measure Z $321,665 Other $1,500,000 $35,000,000 Total $1,968,773 $5,500,000 $1,500,000 $35,000,000 Funding Sources Total To Date $1,968,773 FY2023 Budget $5,500,000 Total Budget $42M Funding Sources by Year Measure A TUMF Measure Z Other 2023 2024 2027 $5,500,000.00 $1,500,000.00 $35,000,000.00 $0 $10M $20M$30M Funding Sources for Budgeted Years TOTAL $42,000,000.00 Measure A (0%) $178,335.00 TUMF (12%) $5,000,000.00 Measure Z (1%) $321,665.00 Other (87%) $36,500,000.00 66 LAKESHORE MACHADO SIDEWALK IMPROVEMENTS - SB 821 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 04/18/2022 Est. Completion Date 06/30/2025 Department CIP Type Capital Improvement Description Construct ADA compliant sidewalk, curb, gutter and curb ramps on Lakeshore Drive and Machado Street. Work will include removal of existing AC berms, minor grading behind pavement, and installation of curb, gutter, sidewalk, and ramps. Images SB 821 LAKESHORE MACHADO Details If funding source is other, please explain. ALL SB 821, DESIGN WILL START 21/22 FY AND CARRY OVER. 50% MATCH BY CITY DESIGN WILL BE OVER THE 50% MATCH WHICH IS CITY OBLIGATION Type of Project None Location Benet to Community Provide safe path of travel and connecitivty for pedestrians. 67 Capital Cost Breakdown Capital Cost To Date FY2023 Administration $5,000 Design $20,000 $25,000 Engineering $1,000 Construction/Maintenance $380,565 Total $20,000 $411,565 Capital Cost Total To Date $20,000 FY2023 Budget $411,565 Total Budget $411.565K Capital Cost by Year Administration Design Engineering Construction/Mai… 2023 $411,565.00 $0 $100K$200K$300K$… Capital Cost for Budgeted Years TOTAL $411,565.00 Administration (1%) $5,000.00 Design (6%) $25,000.00 Engineering (0%) $1,000.00 Construction/Maintenance (92 68 Funding Sources Breakdown Funding Sources To Date FY2023 Measure A $203,282 SB821 $208,283 Other $20,000 Total $20,000 $411,565 Funding Sources Total To Date $20,000 FY2023 Budget $411,565 Total Budget $411.565K Funding Sources by Year Measure A SB821 2023 $411,565.00 $0 $100K$200K$300K$… Funding Sources for Budgeted Years TOTAL $411,565.00 Measure A (49%) $203,282.00 SB821 (51%) $208,283.00 69 MAIN STREET INTERCHANGE IMPROVEMENTS Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 03/14/2022 Est. Completion Date 06/30/2024 Department Infrastructure Type Capital Improvement Description This project provides for improvements to Main Street from two (2) lane to four (4) lane, Northbound on & off improvements, Southbound off-ramp widening at the intersection, and installation of a trafc signal at the ramps & intersection of Camino Del Norte and Main Street. Images MAIN STREET INTERCHANGE Details If funding source is other, please explain. OTHER = MARA FUNDS New Facility or Replacement Replacement Location Benet to Community The project will accommodate any temporary detour during the construction of the Railroad Canyon Interchange. 70 Capital Cost Breakdown Capital Cost To Date FY2023 Administration $30,823 $40,000 Design $492,751 Engineering $50,000 $200,000 Construction $3,539,401 $5,769,025 Total $4,112,975 $6,009,025 Capital Cost Total To Date $4,112,975 FY2023 Budget $6,009,025 Total Budget $6.009M Capital Cost by Year Administration Engineering Construction 2023 $6,009,025.00 $0 $…$1.5M$3M$4.5M Capital Cost for Budgeted Years TOTAL $6,009,025.00 Administration (1%)$40,000.00 Engineering (3%) $200,000.00 Construction (96%)$5,769,025. 71 Funding Sources Breakdown Funding Sources To Date FY2023 Measure A $283,591 Grant(s)$3,729,261 $4,309,025 Measure Z $1,700,000 NPDES $100,123 Total $4,112,975 $6,009,025 Funding Sources Total To Date $4,112,975 FY2023 Budget $6,009,025 Total Budget $6.009M Funding Sources by Year Grant(s)Measure Z 2023 $6,009,025.00 $0 $…$1.5M$3M$4.5M Funding Sources for Budgeted Years TOTAL $6,009,025.00 Grant(s) (72%) $4,309,025.00 Measure Z (28%)$1,700,000.00 72 POPE CIRCLE IMPROVEMENTS Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2023 Est. Completion Date 06/30/2024 Department Circulation Type Capital Improvement Description Pope Circle is subject to a large amount of ponding during rainstorms and creates a vector issue.  This project seeks to address the ponding on Pope Circle through various design options.  An in-depth design with cost/benet analysis is desired to identify the best construction option.  Images Pope Circle Details If funding source is other, please explain. None Type of Project Other Location Benet to Community The drainage design and implementation will alleviate the constant ooding and ponding on Pope Circle and encourage development.  73 Capital Cost Breakdown Capital Cost FY2023 Design $30,000 Land/Right-of-way $50,000 Construction/Maintenance $200,000 Total $280,000 Capital Cost FY2023 Budget $280,000 Total Budget $280K Capital Cost by Year Design Land/Right-of-w… Construction/Mai… 2023 $280,000.00 $0 $80K$160K$240K Capital Cost for Budgeted Years TOTAL $280,000.00 Design (11%) $30,000.00 Land/Right-of-way (18%)$50,0 Construction/Maintenance (71 74 Funding Sources Breakdown Funding Sources FY2023 Storm Drain $280,000 Total $280,000 Funding Sources FY2023 Budget $280,000 Total Budget $280K Funding Sources by Year Storm Drain 2023 $280,000.00 $0 $80K$160K$240K Funding Sources for Budgeted Years TOTAL $280,000.00 Storm Drain (100%)$280,000.0 75 SB 1 PAVEMENT REHABILITATION PROGRAM FY22.23 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Infrastructure Type Capital Improvement Description The City receives Road Maintenance and Rehabilitation funds annually as part of the Road Repair and Accountability Act of 2017. Each year, the City must declare a specic project in May. The selected project is based on Pavement Conditions Indices (PCI) and Average Daily Trafc (ADT) demand. Details If funding source is other, please explain. None New Facility or Replacement Replacement Location Benet to Community This project represents the City's efforts to proactively maintain and extend the useful life of aging asphalt roadway surfaces. 76 Capital Cost Breakdown Capital Cost FY2023 Administration $15,000 Design $20,000 Construction $1,220,538 Total $1,255,538 Capital Cost FY2023 Budget $1,255,538 Total Budget $1.256M Capital Cost by Year Administration Design Construction 2023 $1,255,538.00 $0 $400K$800K$1.2… Capital Cost for Budgeted Years TOTAL $1,255,538.00 Administration (1%)$15,000.00 Design (2%) $20,000.00 Construction (97%)$1,220,538.0 77 Funding Sources Breakdown Funding Sources FY2023 Grant(s)$1,255,538 Total $1,255,538 Funding Sources FY2023 Budget $1,255,538 Total Budget $1.256M Funding Sources by Year Grant(s) 2023 $1,255,538.00 $0 $400K$800K$1.2… Funding Sources for Budgeted Years TOTAL $1,255,538.00 Grant(s) (100%) $1,255,538.00 78 SUMMERHILL DRIVE EXTENSION Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2019 Est. Completion Date 12/30/2024 Department Circulation Type Capital Improvement Description Summerhill Drive will be extended north to Greenwald Avenue per the General Plan with two (2) lanes in each direction along its entire length and a painted median. Images Summerhill Drive Extension Details If funding source is other, please explain. Unspecied Type of Project New Road Location Benet to Community If extended, it has the potential to complete the connection for residents to Greenwald Avenue and improve safety for residents in the Summerhill/La Strada corridor. 79 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 Administration $2,066 $162,342 Design $59,553 Engineering $340,620 $96,397 Land/Right-of-way $13,834 $1,084,000 Construction/Maintenance $25,787 $7,630,646 $23,369,354 Total $441,860 $8,811,043 $23,531,696 Capital Cost Total To Date $441,860 FY2023 Budget $8,811,043 Total Budget $32.343M Capital Cost by Year Administration Engineering Land/Right-of-w…Construction/Mai… 2023 2024 $8,811,043.00 $23,531,696.00 $0 $6M $12M$18M Capital Cost for Budgeted Years TOTAL $32,342,739.00 Administration (1%)$162,342.00 Engineering (0%) $96,397.00 Land/Right-of-way (3%)$1,084 Construction/Maintenance (96 80 Funding Sources Breakdown Funding Sources To Date FY2023 FY2024 Capital Improvement Fund $441,860 $6,763,768 Measure Z $2,047,275 Other $31,162,342 Total $441,860 $8,811,043 $31,162,342 Funding Sources Total To Date $441,860 FY2023 Budget $8,811,043 Total Budget $39.973M Funding Sources by Year Capital Improve…Measure Z Other 2023 2024 $8,811,043.00 $31,162,342.00 $0 $8M $16M$24M Funding Sources for Budgeted Years TOTAL $39,973,385.00 Capital Improvement Fund (17 Measure Z (5%) $2,047,275.00 Other (78%) $31,162,342.00 81 TEMESCAL CANYON BRIDGE REPLACEMENT & ROAD WIDENING PHASE I Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 01/01/2016 Est. Completion Date 12/31/2024 Department Circulation Type Capital Improvement Description This project includes the design, right-of-way acquisition, and construction of a four-lane bridge across Temescal Canyon wash. Images TEMESCAL CANYON BRIDGE Details If funding source is other, please explain. RCFCD FUNDING - GRANT IS HBP GRANT Type of Project Other Location Benet to Community This project will resolve ooding issues in the immediate area so that the roadway and bridge will be functional during storm events. 82 Capital Cost Breakdown Capital Cost To Date FY2023 FY2025 Administration $295,908 $200,000 Design $1,707,344 Engineering $906,301 Land/Right-of-way $642,400 Construction/Maintenance $20,800,000 Total $2,909,553 $642,400 $21,000,000 Capital Cost Total To Date $2,909,553 FY2023 Budget $642,400 Total Budget $21.642M Capital Cost by Year Administration Land/Right-of-w… Construction/Mai… 2023 2025 $642,400.00 $21,000,000.00 $0 $6M $12M $18M Capital Cost for Budgeted Years TOTAL $21,642,400.00 Administration (1%)$200,000.0 Land/Right-of-way (3%)$642,4 Construction/Maintenance (96 83 Funding Sources Breakdown Funding Sources To Date FY2023 FY2025 Grants $2,225,039 $642,400 $21,000,000 Gas Tax $132,312 TUMF $552,202 Total $2,909,553 $642,400 $21,000,000 Funding Sources Total To Date $2,909,553 FY2023 Budget $642,400 Total Budget $21.642M Funding Sources by Year Grants 2023 2025 $642,400.00 $21,000,000.00 $0 $6M $12M $18M Funding Sources for Budgeted Years TOTAL $21,642,400.00 Grants (100%) $21,642,400.00 84 BUILDING FACILITIES RENOVATION Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Administration - Public Works Type Capital Improvement Description This will make improvements to city facilities, but not limited to renovations. LED parking lot light installation, roof repair, fencing, parking lots, interior walls, plumbing, landscape etc. Facilities renovation will improve visitations to City Facilities, make the current operations more efcient, accommodate the addition of new equipment. Improve health and benet employees and citizens who occupy these facilities. Details If funding source is other, please explain. None Type of Project Refurbishment Location 85 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 FY2025 FY2026 FY2027 Administration $15,000 $20,000 $20,000 $20,000 $20,000 Design $59 Construction/Maintenance $1,730,655 $1,390,000 $1,220,000 $905,000 $890,000 $1,630,000 Furniture, Fixtures and Equipment $585,490 Total $2,331,204 $1,390,000 $1,240,000 $925,000 $910,000 $1,650,000 Capital Cost Total To Date $2,331,204 FY2023 Budget $1,390,000 Total Budget $6.115M Capital Cost by Year Administration Construction/Mai… 2023 2024 2025 2026 2027 $1,390,000.00 $1,240,000.00 $925,000.00 $910,000.00 $1,650,000.00 $0 $40…$80…$1.2M$1… Capital Cost for Budgeted Years TOTAL $6,115,000.00 Administration (1%)$80,000.00 Construction/Maintenance (99 86 Funding Sources Breakdown Funding Sources To Date FY2023 FY2024 FY2025 FY2026 FY2027 Capital Improvement Fund $2,331,204 $1,390,000 $1,240,000 $925,000 $910,000 $1,650,000 Total $2,331,204 $1,390,000 $1,240,000 $925,000 $910,000 $1,650,000 Funding Sources Total To Date $2,331,204 FY2023 Budget $1,390,000 Total Budget $6.115M Funding Sources by Year Capital Improve… 2023 2024 2025 2026 2027 $1,390,000.00 $1,240,000.00 $925,000.00 $910,000.00 $1,650,000.00 $0 $40…$80…$1.2M$1… Funding Sources for Budgeted Years TOTAL $6,115,000.00 Capital Improvement Fund (10 87 CITY HALL Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 09/01/2022 Est. Completion Date 01/31/2024 Department Infrastructure Type Capital Improvement Description The existing City Hall Facility requires major repairs and upgrades for Americans with Disabilities Act (ADA) compliance, mechanical, electrical, and security systems. There are four separate buildings with adjoining modications comprising City administrative ofces. Previous efforts have exhausted expansion possibilities as current ofce spaces are insufcient. The new facility will be approximately 35,000 square feet and connect to the existing City Hall. It will include the following amenities: . Open two-story glass entrance steel moment frame with wood stud walls/roof. . Fire engine in lobby. . Sliding glass entrance doors with metal detectors. . Interior elevator. . Public counters. . Council Chambers on 3rd oor with view of Lake.  . Use red thin brick on exterior walls. . Restrooms. . Conference Room Details If funding source is other, please explain. None Type of Project None Location 88 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 Design $47,747 $1,000,000 Construction/Maintenance $20,000,000 $6,810,902 Furniture, Fixtures and Equipment $8,561 $1,000,000 Land Acquisition $1,132,790 Total $1,189,098 $21,000,000 $7,810,902 Capital Cost Total To Date $1,189,098 FY2023 Budget $21,000,000 Total Budget $28.811M Capital Cost by Year Design Construction/Mai… Furniture, Fixture… 2023 2024 $21,000,000.00 $7,810,902.00 $0 $6M $12M $18M Capital Cost for Budgeted Years TOTAL $28,810,902.00 Design (3%) $1,000,000.00 Construction/Maintenance (93 Furniture, Fixtures and Equipm 89 Funding Sources Breakdown Funding Sources To Date FY2023 FY2024 Capital Improvement Fund $1,189,098 $7,935,660 Other $12,818,301 $7,810,902 DIF Funds $246,039 Total $1,189,098 $21,000,000 $7,810,902 Funding Sources Total To Date $1,189,098 FY2023 Budget $21,000,000 Total Budget $28.811M Funding Sources by Year Capital Improve…Other DIF Funds 2023 2024 $21,000,000.00 $7,810,902.00 $0 $6M $12M $18M Funding Sources for Budgeted Years TOTAL $28,810,902.00 Capital Improvement Fund (28 Other (72%) $20,629,203.00 DIF Funds (1%) $246,039.00 90 CITY LIBRARY Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Expenditures Type Capital Improvement Description This project includes the design and construction of a new City Library for the residents of Lake Elsinore. Details If funding source is other, please explain. None Type of Project New Construction Location 91 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 Administration $63,264 Design $1,301,159 Construction/Maintenance $9,000,000 Furniture, Fixtures and Equipment $1,000,000 Land Acquisition $641,904 Total $705,168 $1,301,159 $10,000,000 Capital Cost Total To Date $705,168 FY2023 Budget $1,301,159 Total Budget $11.301M Capital Cost by Year Design Construction/Mai… Furniture, Fixture… 2023 2024 $1,301,159.00 $10,000,000.00 $0 $2.5M$5M $7.5M$… Capital Cost for Budgeted Years TOTAL $11,301,159.00 Design (12%) $1,301,159.00 Construction/Maintenance (80 Furniture, Fixtures and Equipm 92 Funding Sources Breakdown Funding Sources To Date FY2023 FY2024 Grant(s)$10,000,000 DIF Funds $705,168 $1,301,159 Total $705,168 $1,301,159 $10,000,000 Funding Sources Total To Date $705,168 FY2023 Budget $1,301,159 Total Budget $11.301M Funding Sources by Year Grant(s)DIF Funds 2023 2024 $1,301,159.00 $10,000,000.00 $0 $2.5M$5M $7.5M$… Funding Sources for Budgeted Years TOTAL $11,301,159.00 Grant(s) (88%) $10,000,000.00 DIF Funds (12%) $1,301,159.00 93 Operational Costs Breakdown Operational Costs FY2024 FY2025 FY2026 FY2027 General Maintenance $30,000 $30,000 $30,000 $30,000 Utilities $10,000 $10,000 $10,000 $10,000 Total $40,000 $40,000 $40,000 $40,000 Operational Costs Total Budget $160K Operational Costs by Year General Maintena…Utilities 2024 2025 2026 2027 $40,000.00 $40,000.00 $40,000.00 $40,000.00 $0 $10K$20K$30K$… Operational Costs for Budgeted Years TOTAL $160,000.00 General Maintenance (75%)$120 Utilities (25%) $40,000.00 94 DIAMOND STADIUM TOURISM IMPROVEMENTS Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Parks Type Capital Improvement Description This project will include audio/visual enhancements to Diamond Stadium. The enhancements will increase functionality for holding events at the Stadium. Details If funding source is other, please explain. None Type of Project Refurbishment Location 95 Capital Cost Breakdown Capital Cost FY2023 Administration $20,000 Construction/Maintenance $2,500,000 Furniture, Fixtures and Equipment $1,480,000 Total $4,000,000 Capital Cost FY2023 Budget $4,000,000 Total Budget $4M Capital Cost by Year Administration Construction/Mai… Furniture, Fixture… 2023 $4,000,000.00 $0 $1M $2M $3M$… Capital Cost for Budgeted Years TOTAL $4,000,000.00 Administration (1%)$20,000.00 Construction/Maintenance (63 Furniture, Fixtures and Equipm 96 Funding Sources Breakdown Funding Sources FY2023 Grant(s)$4,000,000 Total $4,000,000 Funding Sources FY2023 Budget $4,000,000 Total Budget $4M Funding Sources by Year Grant(s) 2023 $4,000,000.00 $0 $1M $2M $3M$… Funding Sources for Budgeted Years TOTAL $4,000,000.00 Grant(s) (100%) $4,000,000.00 97 EMERGENCY OPERATIONS CENTER Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description This project will make improvements to the EOC facility. The EOC is the centralized location of emergency response and recovery support operations during incidents. While tactical on-scene operations are conducted by the Incident Command Post, the EOC supports and helps coordinate ICP operations and any other adjacent incident operations.  Details If funding source is other, please explain. None Type of Project Refurbishment Location 98 Capital Cost Breakdown Capital Cost FY2023 Administration $20,000 Construction/Maintenance $1,100,000 Total $1,120,000 Capital Cost FY2023 Budget $1,120,000 Total Budget $1.12M Capital Cost by Year Administration Construction/Mai… 2023 $1,120,000.00 $0 $300K$600K$900K Capital Cost for Budgeted Years TOTAL $1,120,000.00 Administration (2%)$20,000.00 Construction/Maintenance (98 99 Funding Sources Breakdown Funding Sources FY2023 Grant(s)$820,000 Measure Z $300,000 Total $1,120,000 Funding Sources FY2023 Budget $1,120,000 Total Budget $1.12M Funding Sources by Year Grant(s)Measure Z 2023 $1,120,000.00 $0 $300K$600K$900K Funding Sources for Budgeted Years TOTAL $1,120,000.00 Grant(s) (73%) $820,000.00 Measure Z (27%) $300,000.00 100 FIRE STATION BUILDING RENOVATIONS Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Infrastructure Type Capital Improvement Description Lake Elsinore Fire Stations 85 and 94 require roof repairs. In addition, a new tankless water heater will be installed at Station 94. Details If funding source is other, please explain. None Type of Project None Location 101 Capital Cost Breakdown Capital Cost FY2023 Construction/Maintenance $365,000 Total $365,000 Capital Cost FY2023 Budget $365,000 Total Budget $365K Capital Cost by Year Construction/Mai… 2023 $365,000.00 $0 $100K$200K$300K Capital Cost for Budgeted Years TOTAL $365,000.00 Construction/Maintenance (10 102 Funding Sources Breakdown Funding Sources FY2023 Capital Improvement Fund $365,000 Total $365,000 Funding Sources FY2023 Budget $365,000 Total Budget $365K Funding Sources by Year Capital Improve… 2023 $365,000.00 $0 $100K$200K$300K Funding Sources for Budgeted Years TOTAL $365,000.00 Capital Improvement Fund (10 103 MECHANIC OFFICE REMODEL Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description This will make improvements to the city's mechanic's ofce. This renovation will  improve the functionality of the building, give it a more usable space, improve productivity, and allow more room for growth. Details If funding source is other, please explain. None Type of Project Refurbishment Location 104 Capital Cost Breakdown Capital Cost FY2023 Administration $20,000 Construction/Maintenance $120,000 Total $140,000 Capital Cost FY2023 Budget $140,000 Total Budget $140K Capital Cost by Year Administration Construction/Mai… 2023 $140,000.00 $0 $40K $80K$120K Capital Cost for Budgeted Years TOTAL $140,000.00 Administration (14%)$20,000.0 Construction/Maintenance (86 105 Funding Sources Breakdown Funding Sources FY2023 Capital Improvement Fund $140,000 Total $140,000 Funding Sources FY2023 Budget $140,000 Total Budget $140K Funding Sources by Year Capital Improve… 2023 $140,000.00 $0 $40K $80K$120K Funding Sources for Budgeted Years TOTAL $140,000.00 Capital Improvement Fund (10 106 MECHANIC SHOP EXPANSION AND STORAGE Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description Currently, the mechanics shop is used for storage and to maintain all city-owned vehicles and equipment. It is non-functional for conducting general maintenance of heavy equipment as it has become full of city-owned supplies and equipment. Expansion of new shop and storage will allow more space to store machinery, tools and supplies. It will increase productivity by allowing mechanics to work on more than one heavy piece of equipment at a time.   Details If funding source is other, please explain. None Type of Project New Construction Location 107 Capital Cost Breakdown Capital Cost FY2023 Administration $20,000 Construction/Maintenance $350,000 Total $370,000 Capital Cost FY2023 Budget $370,000 Total Budget $370K Capital Cost by Year Administration Construction/Mai… 2023 $370,000.00 $0 $100K$200K$300K Capital Cost for Budgeted Years TOTAL $370,000.00 Administration (5%)$20,000.00 Construction/Maintenance (95 108 Funding Sources Breakdown Funding Sources FY2023 Capital Improvement Fund $370,000 Total $370,000 Funding Sources FY2023 Budget $370,000 Total Budget $370K Funding Sources by Year Capital Improve… 2023 $370,000.00 $0 $100K$200K$300K Funding Sources for Budgeted Years TOTAL $370,000.00 Capital Improvement Fund (10 109 THE ANCHOR RENOVATIONS Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description The current kitchen is outdated with inefcient kitchen xtures, appliances and lighting. Kitchen remodeling will be a cost savings due to the installation of water-efcient kitchen xtures, energy-saving appliances, and LED lighting. This remodel will also include sewer line replacement.  Details If funding source is other, please explain. None Type of Project Refurbishment Location 110 Capital Cost Breakdown Capital Cost FY2023 Administration $20,000 Construction/Maintenance $680,000 Total $700,000 Capital Cost FY2023 Budget $700,000 Total Budget $700K Capital Cost by Year Administration Construction/Mai… 2023 $700,000.00 $0 $200K$400K$600K Capital Cost for Budgeted Years TOTAL $700,000.00 Administration (3%)$20,000.00 Construction/Maintenance (97 111 Funding Sources Breakdown Funding Sources FY2023 Grant(s)$700,000 Total $700,000 Funding Sources FY2023 Budget $700,000 Total Budget $700K Funding Sources by Year Grant(s) 2023 $700,000.00 $0 $200K$400K$600K Funding Sources for Budgeted Years TOTAL $700,000.00 Grant(s) (100%) $700,000.00 112 AVENUES DRAINAGE IMPROVEMENTS Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2021 Est. Completion Date 12/29/2023 Department Infrastructure Type Capital Improvement Description Installation of roadway and drainage improvements on Country Club Blvd/Mill Street from the intersection of Lakeshore Drive to Avenue 2.  Images Avenues Drainage Improvements Details If funding source is other, please explain. OTHER = NPDES New Facility or Replacement Replacement Location Benet to Community This project design will direct ows from the hillside down to Lakeshore Drive.  113 Capital Cost Breakdown Capital Cost FY2023 Administration $15,000 Design $20,000 Engineering $30,000 Construction $1,700,515 Total $1,765,515 Capital Cost FY2023 Budget $1,765,515 Total Budget $1.766M Capital Cost by Year Administration Design Engineering Construction 2023 $1,765,515.00 $0 $500K $1M $1.5M Capital Cost for Budgeted Years TOTAL $1,765,515.00 Administration (1%)$15,000.00 Design (1%) $20,000.00 Engineering (2%) $30,000.00 Construction (96%)$1,700,515.0 114 Funding Sources Breakdown Funding Sources FY2023 Storm Drain $941,763 NPDES $823,752 Total $1,765,515 Funding Sources FY2023 Budget $1,765,515 Total Budget $1.766M Funding Sources by Year Storm Drain NPDES 2023 $1,765,515.00 $0 $500K $1M $1.5M Funding Sources for Budgeted Years TOTAL $1,765,515.00 Storm Drain (53%) $941,763.00 NPDES (47%) $823,752.00 115 CAMINO DEL NORTE IMPROVEMENTS Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 06/30/2022 Est. Completion Date 06/30/2023 Department Infrastructure Type Capital Improvement Description dRAINAGE IMPROVEMENTS Details If funding source is other, please explain. None New Facility or Replacement New Location Benet to Community NECESSARY IMPROVEMENTS TO PROMOTE DEVELOPMENT ALONG CAMINO DEL NORTE.  116 Capital Cost Breakdown Capital Cost FY2023 Administration $30,000 Design $500,000 Construction $1,600,000 Total $2,130,000 Capital Cost FY2023 Budget $2,130,000 Total Budget $2.13M Capital Cost by Year Administration Design Construction 2023 $2,130,000.00 $0 $600K$1.2M $1.8M Capital Cost for Budgeted Years TOTAL $2,130,000.00 Administration (1%)$30,000.00 Design (23%) $500,000.00 Construction (75%)$1,600,000. 117 Funding Sources Breakdown Funding Sources FY2023 Grant(s)$911,806 Measure Z $918,194 Other $300,000 Total $2,130,000 Funding Sources FY2023 Budget $2,130,000 Total Budget $2.13M Funding Sources by Year Grant(s)Measure Z Other 2023 $2,130,000.00 $0 $600K$1.2M $1.8M Funding Sources for Budgeted Years TOTAL $2,130,000.00 Grant(s) (43%) $911,806.00 Measure Z (43%) $918,194.00 Other (14%) $300,000.00 118 COLLIER AVENUE CULVERT DRAINAGE IMPROVEMENTS Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Infrastructure Type Capital Improvement Description Reconstruct the existing undersized 3' x 5' box culvert and headwalls with a 4' x 8' box culvert which crosses under Collier Avenue. Upsized culvert to alleviate recurring ooding in the area. Details If funding source is other, please explain. None New Facility or Replacement Replacement Location Benet to Community  This project will enhance drainage in the area on Collier Avenue north of Central Avenue. Existing culvert has been identied as being undersized leading to repeated ooding. 119 Capital Cost Breakdown Capital Cost FY2023 Construction $600,000 Total $600,000 Capital Cost FY2023 Budget $600,000 Total Budget $600K Capital Cost by Year Construction 2023 $600,000.00 $0 $150K$300$450$… Capital Cost for Budgeted Years TOTAL $600,000.00 Construction (100%)$600,000. 120 Funding Sources Breakdown Funding Sources FY2023 Storm Drain $600,000 Total $600,000 Funding Sources FY2023 Budget $600,000 Total Budget $600K Funding Sources by Year Storm Drain 2023 $600,000.00 $0 $150K$300$450$… Funding Sources for Budgeted Years TOTAL $600,000.00 Storm Drain (100%)$600,000.0 121 MURRIETA CREEK REGIONAL TRAIL CONNECTION Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 01/01/2019 Est. Completion Date 06/28/2024 Department Infrastructure Type Capital Improvement Description Acquire easement behind Serenity neighborhood to establish a connection from the MCRT to the Levee Trail (completing the City's connections for the MCRT). Develop easement and Levee Trail with 10' paved bike path and decomposed granite shoulders with solar lighting and retaining wall with screening (vegetation or artist mural). Implement waynding signage along MCRT and Levee Trail in accordance with ATP sign guidelines. Images MURRIETA CREEK REGIONAL TRAIL Details If funding source is other, please explain. Unspecied Type of Project Other Location Benet to Community Supports regional trail plans, active transportation plans, as well as local City of Lake Elsinore General Plan, East Lake Specic Plan, Healthy LE Intiative, and Active LE Plan (Active Transportation Plan). 122 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 Administration $16,293 Design $356,944 Land/Right-of-way $650,000 Construction/Maintenance $3,904,000 Total $373,237 $650,000 $3,904,000 Capital Cost Total To Date $373,237 FY2023 Budget $650,000 Total Budget $4.554M Capital Cost by Year Land/Right-of-w…Construction/Mai… 2023 2024 $650,000.00 $3,904,000.00 $0 $1M $2M $3M Capital Cost for Budgeted Years TOTAL $4,554,000.00 Land/Right-of-way (14%)$650,0 Construction/Maintenance (86 123 Funding Sources Breakdown Funding Sources To Date FY2023 FY2024 Capital Improvement Fund $650,000 Grants $373,237 $3,904,000 Total $373,237 $650,000 $3,904,000 Funding Sources Total To Date $373,237 FY2023 Budget $650,000 Total Budget $4.554M Funding Sources by Year Capital Improve…Grants 2023 2024 $650,000.00 $3,904,000.00 $0 $1M $2M $3M Funding Sources for Budgeted Years TOTAL $4,554,000.00 Capital Improvement Fund (14 Grants (86%) $3,904,000.00 124 RICE CANYON REVETMENT Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2021 Est. Completion Date 06/29/2029 Department Infrastructure Type Capital Improvement Description The project will provide rock slope protection that would tie into the high ground southwest of Dale Court and continue along the right bank of Rice Canyon watercourse as it travels northeast behind homes serviced by Dale Court. The slope protection would tie into the revetment project along Lincoln Street extension adjacent to the future Running Deer community. Images Rice Canyon Details If funding source is other, please explain. FUTURE YEARS CONSTRUCTION @ $2,000,000 New Facility or Replacement New Location Benet to Community The project will provide ood protection against erosive velocities and debris potential for the neighboring communities and schools. 125 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Administration $20,000 $30,000 $50,000 $30,000 $30,000 Design $470,000 $470,000 Engineering $615,000 $580,000 $205,000 Total $635,000 $610,000 $255,000 $500,000 $500,000 Capital Cost FY2023 Budget $635,000 Total Budget $2.5M Capital Cost by Year Administration Design Engineering 2023 2024 2025 2026 2027 $635,000.00 $610,000.00 $255,000.00 $500,000.00 $500,000.00 $0 $200K$400K$60… Capital Cost for Budgeted Years TOTAL $2,500,000.00 Administration (6%)$160,000.0 Design (38%) $940,000.00 Engineering (56%)$1,400,000.0 126 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Grant(s)$90,000 $30,000 $255,000 $500,000 $500,000 Measure Z $545,000 $580,000 Total $635,000 $610,000 $255,000 $500,000 $500,000 Funding Sources FY2023 Budget $635,000 Total Budget $2.5M Funding Sources by Year Grant(s)Measure Z 2023 2024 2025 2026 2027 $635,000.00 $610,000.00 $255,000.00 $500,000.00 $500,000.00 $0 $200K$400K$60… Funding Sources for Budgeted Years TOTAL $2,500,000.00 Grant(s) (55%) $1,375,000.00 Measure Z (45%) $1,125,000.00 127 STORM DRAIN CATCH BASIN INLET FILTER INSTALLATION Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Infrastructure Type Capital Improvement Description INSTALL MS4 INLET FILTERS TO COMPLY WITH THE MANDATE OF THE MS4 PERMIT SYSTEM Images Storm Drain Catch Basin Inlet Filter Details If funding source is other, please explain. NPDES FUNDS New Facility or Replacement New Location Benet to Community CLEANS THE RUN OFF WATER FILTERING OUT WHAT GOES INTO THE LAKE 128 Capital Cost Breakdown Capital Cost FY2023 FY2024 FY2025 FY2026 FY2027 Engineering $75,000 $75,000 $75,000 $75,000 $75,000 Total $75,000 $75,000 $75,000 $75,000 $75,000 Capital Cost FY2023 Budget $75,000 Total Budget $375K Capital Cost by Year Engineering 2023 2024 2025 2026 2027 $75,000.00 $75,000.00 $75,000.00 $75,000.00 $75,000.00 $0 $20K $40K $60K Capital Cost for Budgeted Years TOTAL $375,000.00 Engineering (100%)$375,000.0 129 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2025 FY2026 FY2027 Measure Z $75,000 $75,000 $75,000 $75,000 $75,000 Total $75,000 $75,000 $75,000 $75,000 $75,000 Funding Sources FY2023 Budget $75,000 Total Budget $375K Funding Sources by Year Measure Z 2023 2024 2025 2026 2027 $75,000.00 $75,000.00 $75,000.00 $75,000.00 $75,000.00 $0 $20K $40K $60K Funding Sources for Budgeted Years TOTAL $375,000.00 Measure Z (100%) $375,000.00 130 AQUATIC ECOSYSTEM RESTORATION PROJECT Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Parks Type Capital Improvement Description This project will initiate the Lake Elsinore Aquatic Ecosystem Restoration Project, which will be completed under the authority of the Continuing Authority Program (CAP) Section 206 program of the Water Resources Development Act of 1986 in partnership with the Army Corps of Engineers, Elsinore Valley Municipal Water District, and the Riverside County Flood Control and Conservation District. The objective of this CAP Authority is to study, design, and construct aquatic ecosystem and riparian habitat restoration projects. The purpose of the Lake Elsinore CAP Section 206 study is to determine and eventually construct a project that will help restore degraded aquatic ecosystem structure, function, and dynamic processes of Lake Elsinore to a less degraded, more natural condition. This involves consideration of the ecosystem’s natural integrity, productivity, stability, and biological diversity. Details If funding source is other, please explain. None New Facility or Replacement Replacement Location Benet to Community This project is necessary to initate a long-term project to improve the water quality, riparian habitat, and aquatic habitat of Lake Elsinore. Lake Elsinore is Southern California’s largest natural, freshwater lake that serves as a signicant environmental asset for the entire state. It is home to over 250 bird species and serves as an important stopover along the Pacic Flyway. The Lake also supports a wide variety of sports sh including Bass, Crappie, Blue Gill and Channel Catsh, and many other types of wildlife. It is one of the City's primary focuses as part of the Dream Extreme 2040 Plan and this project could lead to additional funding and project opportunities for the Lake. 131 Capital Cost Breakdown Capital Cost FY2023 FY2024 Design $125,000 $125,000 Total $125,000 $125,000 Capital Cost FY2023 Budget $125,000 Total Budget $250K Capital Cost by Year Design 2023 2024 $125,000.00 $125,000.00 $0 $1…$30K$60K$90K Capital Cost for Budgeted Years TOTAL $250,000.00 Design (100%) $250,000.00 132 Funding Sources Breakdown Funding Sources FY2023 FY2024 FY2027 Capital Improvement Fund $125,000 $125,000 Other $1,250,000 Total $125,000 $125,000 $1,250,000 Funding Sources FY2023 Budget $125,000 Total Budget $1.5M Funding Sources by Year Capital Improve…Other 2023 2024 2027 $125,000.00 $125,000.00 $1,250,000.00 $0 $1.…$30…$60…$90… Funding Sources for Budgeted Years TOTAL $1,500,000.00 Capital Improvement Fund (17 Other (83%) $1,250,000.00 133 BOAT DOCK ADDITIONS Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description Replace 2 docks at Seaport Boat Launch that were moved to Launch Pointe, add an additional 2 docks at Launch Pointe Resort. Images Boat Dock Additions Details If funding source is other, please explain. $500,000 Type of Project Other improvement Location Benet to Community Replacing these docks and adding additional to Launch pointe Resort will help to allow the reopening of Seaport boat launch when the water is deep enough and provide additional shing facilities for public use. 134 Capital Cost Breakdown Capital Cost FY2023 Construction/Maintenance $500,000 Total $500,000 Capital Cost FY2023 Budget $500,000 Total Budget $500K Capital Cost by Year Construction/Mai… 2023 $500,000.00 $0 $120K$240K$360K$4… Capital Cost for Budgeted Years TOTAL $500,000.00 Construction/Maintenance (10 135 Funding Sources Breakdown Funding Sources FY2023 Capital Improvement Fund $500,000 Total $500,000 Funding Sources FY2023 Budget $500,000 Total Budget $500K Funding Sources by Year Capital Improve… 2023 $500,000.00 $0 $120K$240K$360K$4… Funding Sources for Budgeted Years TOTAL $500,000.00 Capital Improvement Fund (10 136 BOAT LAUNCH MITIGATION RESTORATION Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 07/01/2022 Est. Completion Date 06/30/2027 Department Parks Type Capital Improvement Description The City in 2010 entered into Streambed Alteration Agreement #1600-2007-0210-R6 (SAA) with the California Department of Fish and Wildlife (CDFW) to mitigate for impacts resulting from the original excavation of the 11.5-acre Boat Launch Borrow Site (BLBS) as part of the Lake Elsinore Boat Launch Facility Project, completed in 2012. The previous efforts to mitigate impacts to the BLBS were incomplete and therefore failed to achieve performance standards for the habitat mitigation and resulted in the necessity to prepare a new Habitat Mitigation and Monitoring Plan (HMMP) subject to review and approval by CDFW. This project implements the recently approved HMMP for the site and when completed will satisfy the City's obligation pursuant to the SAA. Details If funding source is other, please explain.None Type of Project Other improvement Benet to Community The proposed CIP project is required in order for the City to comply with the mitigation for the Lake Elsinore Boat Launch Facility Project. 137 Capital Cost Breakdown Capital Cost To Date FY2023 FY2024 FY2025 FY2026 FY2027 Construction/Maintenance $1,077,000 $82,262 $73,065 $69,676 $57,850 $57,850 Total $1,077,000 $82,262 $73,065 $69,676 $57,850 $57,850 Capital Cost Total To Date $1,077,000 FY2023 Budget $82,262 Total Budget $340.703K Capital Cost by Year Construction/Mai… 2023 2024 2025 2026 2027 $82,262.00 $73,065.00 $69,676.00 $57,850.00 $57,850.00 $0 $20K$40K$60K$… Capital Cost for Budgeted Years TOTAL $340,703.00 Construction/Maintenance (10 138 Funding Sources Breakdown Funding Sources To Date FY2023 FY2024 FY2025 FY2026 FY2027 Capital Improvement Fund $1,077,000 $82,262 $73,065 $69,676 $57,850 $57,850 Total $1,077,000 $82,262 $73,065 $69,676 $57,850 $57,850 Funding Sources Total To Date $1,077,000 FY2023 Budget $82,262 Total Budget $340.703K Funding Sources by Year Capital Improve… 2023 2024 2025 2026 2027 $82,262.00 $73,065.00 $69,676.00 $57,850.00 $57,850.00 $0 $20K$40K$60K$… Funding Sources for Budgeted Years TOTAL $340,703.00 Capital Improvement Fund (10 139 CANYON HILLS PARK UPGRADES Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 06/30/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description This project will make improvements to Canyon Hills Park including, but not limited to: Arti cial turf for at least one soccer/football eld, sports eld landscape renovation, cement repairs, automatic bathroom door locks, trash enclosures, fresh mulch in landscape planters; replacement of drinking fountains, picnic tables, benches, trash cans and BBQ grills, bleachers and dugouts. Install palm trees to enhance the aesthetics of the park and provide additional shade and add additional lighting to the dog parks. Details If funding source is other, please explain. None Type of Project Other improvement Location Benet to Community Renovating Canyon Hills Park will create a more aesthetically pleasing environment and provide a safe play area while encouraging many residents to utilize the city parks. 140 Capital Cost Breakdown Capital Cost To Date FY2023 Construction/Maintenance $1,304,060 $2,588,000 Equipment/Vehicle/Furnishings $42,703 Other $5,625 Total $1,352,388 $2,588,000 Capital Cost Total To Date $1,352,388 FY2023 Budget $2,588,000 Total Budget $2.588M Capital Cost by Year Construction/Mai… 2023 $2,588,000.00 $0 $800K$1.6M$2.4M Capital Cost for Budgeted Years TOTAL $2,588,000.00 Construction/Maintenance (10 141 Funding Sources Breakdown Funding Sources To Date FY2023 Capital Improvement Fund $1,352,388 $2,332,000 Other $256,000 Total $1,352,388 $2,588,000 Funding Sources Total To Date $1,352,388 FY2023 Budget $2,588,000 Total Budget $2.588M Funding Sources by Year Capital Improve…Other 2023 $2,588,000.00 $0 $800K$1.6M$2.4M Funding Sources for Budgeted Years TOTAL $2,588,000.00 Capital Improvement Fund (90 Other (10%) $256,000.00 142 CITY PARK IMPROVEMENTS Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 10/01/2022 Est. Completion Date 06/30/2023 Department Expenditures Type Capital Improvement Description The project will include approximately 2,100 feet of ADA compliant sidewalk from the Library Street Parking Lot through City Park all the way to Main Street and Graham Avenue. Some of this sidewalk will need new curb, gutter and ramping at roadway intersections. Included in this project will be the design and construction of approximately 75 new parking spaces in a new parking lot area connected to City Park. The parking lot will include appropriate security lighting and connect lighting to the existing park lighting. The parking lot will incorporate underground electrical conduits for electric vehicle charging stations at each new parking space. Within the existing City Park, an outdoor live entertainment area will be developed to support special events that are commonly held at the park. The remaining elements of this project will include removal of large, dangerous eucalyptus trees and the installation of drought-tolerant landscaping throughout. Security fencing will be installed to separate neighboring properties and to assist with directing pedestrian trafc to Main Street. Details If funding source is other, please explain. None Type of Project Refurbishment Location Benet to Community The project will improve current dilapidated park facilities and surrounding areas, making it safer and more enjoyable for residents.  143 Capital Cost Breakdown Capital Cost FY2023 Design $30,000 Construction/Maintenance $750,000 Other $45,000 Total $825,000 Capital Cost FY2023 Budget $825,000 Total Budget $825K Capital Cost by Year Design Construction/Mai… Other 2023 $825,000.00 $0 $20…$40…$60…$… Capital Cost for Budgeted Years TOTAL $825,000.00 Design (4%) $30,000.00 Construction/Maintenance (91 Other (5%) $45,000.00 144 Funding Sources Breakdown Funding Sources FY2023 Grant(s)$429,120 Other $395,880 Total $825,000 Funding Sources FY2023 Budget $825,000 Total Budget $825K Funding Sources by Year Grant(s)Other 2023 $825,000.00 $0 $20…$40…$60…$… Funding Sources for Budgeted Years TOTAL $825,000.00 Grant(s) (52%) $429,120.00 Other (48%) $395,880.00 145 CITYWIDE PARKS IMPROVEMENTS Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 06/30/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description This project will make improvements to City parks including, but not limited to: fresh mulch in landscape planters; replacement of drinking fountains, picnic tables, benches, trash cans and BBQ grills; remove and replace rubberized playground surfacing; resurfacing of basketball courts; shade structures for splash pads, picnic areas, bleachers, and dugouts; repair of roong, fencing, and cement; LED upgrades, baseball eld renovations, snack bar improvements to allow preparation and serving of hot food items, and install automatic door locks on park restrooms. Details If funding source is other, please explain.None Type of Project Refurbishment Benet to Community Renovating the city parks would not only create a more aesthetically pleasing environment, but also bring the city into compliance with current rules and regulations and provide a safe play area, encouraging many residents to utilize the city parks and continue in the tradition of the Action Sports Capital of the World. 146 Capital Cost Breakdown Capital Cost To Date FY2023 Design $49,160 Construction/Maintenance $1,421,897 $3,283,600 Equipment/Vehicle/Furnishings $850,706 Other $27,533 Total $2,349,296 $3,283,600 Capital Cost Total To Date $2,349,296 FY2023 Budget $3,283,600 Total Budget $3.284M Capital Cost by Year Construction/Mai… 2023 $3,283,600.00 $0 $80…$1.6M$2.4M$… Capital Cost for Budgeted Years TOTAL $3,283,600.00 Construction/Maintenance (10 147 Funding Sources Breakdown Funding Sources To Date FY2023 Capital Improvement Fund $2,349,296 $3,027,166 Other $256,434 Total $2,349,296 $3,283,600 Funding Sources Total To Date $2,349,296 FY2023 Budget $3,283,600 Total Budget $3.284M Funding Sources by Year Capital Improve…Other 2023 $3,283,600.00 $0 $80…$1.6M$2.4M$… Funding Sources for Budgeted Years TOTAL $3,283,600.00 Capital Improvement Fund (92 Other (8%) $256,434.00 148 LAKEPOINT PARK FENCE OPENING Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Department Community Services Type Capital Improvement Description Opening the west facing fences and creating a path to the lakeshore for park visitors to enjoy the lakefront at the Levee.  Fence and concrete work (Stairs with rails and landing) - $60,000 Fence and concrete work (ADA ramp and landing) - $250,000 Images Details If funding source is other, please explain. None Type of Project None Location Benet to Community Provides access to the lake shore for recreational activities that was not previously accessible.   149 Capital Cost Breakdown Capital Cost FY2023 Construction/Maintenance $310,000 Total $310,000 Capital Cost FY2023 Budget $310,000 Total Budget $310K Capital Cost by Year Construction/Mai… 2023 $310,000.00 $0 $80K$160K$240K Capital Cost for Budgeted Years TOTAL $310,000.00 Construction/Maintenance (10 150 Funding Sources Breakdown Funding Sources FY2023 Other $310,000 Total $310,000 Funding Sources FY2023 Budget $310,000 Total Budget $310K Funding Sources by Year Other 2023 $310,000.00 $0 $80K$160K$240K Funding Sources for Budgeted Years TOTAL $310,000.00 Other (100%) $310,000.00 151 LAKEPOINT PARK Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description This project includes restoration of restrooms and snack bar facilities, parking lot repairs, shade structure, cement repairs,roof repairs, trash enclosures, new amenities and LED sports eld lighting. Details If funding source is other, please explain. None Type of Project Refurbishment Location Benet to Community Renovating the city parks would not only provide an aesthetically pleasing environment, but also provide a safe play area, encouraging many residents to utilize the city parks and continue in the tradition of the Action Sports Capital of the World. 152 Capital Cost Breakdown Capital Cost To Date FY2023 FY2027 Construction/Maintenance $384,000 $321,800 $2,197,000 Total $384,000 $321,800 $2,197,000 Capital Cost Total To Date $384,000 FY2023 Budget $321,800 Total Budget $2.519M Capital Cost by Year Construction/Mai… 2023 2027 $321,800.00 $2,197,000.00 $0 $600K$1.2M$1.8M Capital Cost for Budgeted Years TOTAL $2,518,800.00 Construction/Maintenance (10 153 Funding Sources Breakdown Funding Sources To Date FY2023 FY2027 Capital Improvement Fund $384,000 $321,800 Other $2,197,000 Total $384,000 $321,800 $2,197,000 Funding Sources Total To Date $384,000 FY2023 Budget $321,800 Total Budget $2.519M Funding Sources by Year Capital Improve…Other 2023 2027 $321,800.00 $2,197,000.00 $0 $600K$1.2M$1.8M Funding Sources for Budgeted Years TOTAL $2,518,800.00 Capital Improvement Fund (13 Other (87%) $2,197,000.00 154 LAUNCH POINTE - ADA RAMP Overview Submitted By Johnathan Skinner, Director of Community Services Request Owner Johnathan Skinner, Director of Community Services Est. Start Date 06/30/2022 Est. Completion Date 06/30/2024 Department Community Services Type Capital Improvement Description Launch Pointe "Public Beach" receives many guests who have a challenging time getting to the beach and shing areas due to access.  The Community Services Department received funding from the State Department of Parks and Recreation Per Capita Grant to increase access to recreational areas.  This will be an added amenity to Launch Pointe, increasing accessibility for all. Images Launch Pointe ADA Ramp Public Beach Beach access ramp from parking lot to concrete walkway. Details If funding source is other, please explain. Unspecied Type of Project New Construction Location Benet to Community This project will benet visitors to Launch Pointe Public Beach area who have disabilities and challenges reaching the lake and enjoying the area. 155 Capital Cost Breakdown Capital Cost FY2023 Construction/Maintenance $200,000 Total $200,000 Capital Cost FY2023 Budget $200,000 Total Budget $200K Capital Cost by Year Construction/Mai… 2023 $200,000.00 $0 $50K$100K$150K$… Capital Cost for Budgeted Years TOTAL $200,000.00 Construction/Maintenance (10 156 Funding Sources Breakdown Funding Sources FY2023 Capital Improvement Fund $67,000 Grant(s)$133,000 Total $200,000 Funding Sources FY2023 Budget $200,000 Total Budget $200K Funding Sources by Year Capital Improve…Grant(s) 2023 $200,000.00 $0 $50K$100K$150K$… Funding Sources for Budgeted Years TOTAL $200,000.00 Capital Improvement Fund (34 Grant(s) (67%) $133,000.00 157 LAUNCH POINTE DOCK EXTENSION AND FLOATING WAVE ATTENUATORS Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description Extend existing boat docks at Launch Pointe Resort by adding approximately 440' of additional dock sections to the existing infrastructure and installing oating wave attenuators from the boat launch to the public beach area. Images Launch Pointe Dock Extension Floating Wave Attenuators Details If funding source is other, please explain. $440,000 Type of Project Other improvement Location Benet to Community By adding additional length to the existing docks, it will provide much needed access for the public staying at and utilizing the Launch Pointe Resort Facilities. Installing oating wave attenuators will protect against specic conditions (e.g., wind waves and boat wakes) to ensure more tranquil water conditions. 158 Capital Cost Breakdown Capital Cost FY2023 Design $20,000 Construction/Maintenance $1,340,000 Total $1,360,000 Capital Cost FY2023 Budget $1,360,000 Total Budget $1.36M Capital Cost by Year Design Construction/Mai… 2023 $1,360,000.00 $0 $400K$800K$1.2M Capital Cost for Budgeted Years TOTAL $1,360,000.00 Design (1%) $20,000.00 Construction/Maintenance (99 159 Funding Sources Breakdown Funding Sources FY2023 Capital Improvement Fund $440,000 Other $920,000 Total $1,360,000 Funding Sources FY2023 Budget $1,360,000 Total Budget $1.36M Funding Sources by Year Capital Improve…Other 2023 $1,360,000.00 $0 $400K$800K$1.2M Funding Sources for Budgeted Years TOTAL $1,360,000.00 Capital Improvement Fund (32 Other (68%) $920,000.00 160 LAUNCH POINTE - SOUND WALL Overview Submitted By Beau Davis, Assistant Community Services Director Request Owner Beau Davis, Assistant Community Services Director Est. Start Date 11/01/2022 Est. Completion Date 05/01/2023 Department Launch Pointe Resort Type Capital Improvement Description Launch Pointe has proven to be a world-class destination for families to escape to their RVs and enjoy the beauty Lake Elsinore has to offer. Over the nearly three years of operating as Launch Pointe, the guest reviews and feedback have afrmed guests do not enjoy being in close proximity to Riverside Drive. The road noise has driven many guests to demand being moved or refunded for their stay. While we make every effort to be transparent on the location in the park the disturbance from the noise has been too much for some guests. As a means to combat the noise, maximize the guest's enjoyment, and increase potential revenue for the sites that are adjacent to Riverside, an acoustic sound barrier is being recommended. The Federal Highway Administration lists the average cost of a sound wall to be approximately $31 per square foot. At approximately 1200 feet in length, the wall could cost as much as $300,000. This cost would be offset with an increase in RV site prices throughout Launch Pointe, but primarily to the ones that are Riverside Dr. adjacent. Images Sound Barrier Wall Details If funding source is other, please explain. Launch Pointe Revenues New Facility or Replacement New Location Address: 32040 Riverside Drive 161 Benet to Community It will provide an opportunity to book 40+ sites in an area of the park that has been deemed only available to long-term guests due to the inconvenience of the road noise. The rates for those specic sites could also be increased as the noise should be a reduced inconvenience.  Capital Cost Breakdown Capital Cost FY2023 Administration $10,000 Design $20,000 Engineering $20,000 Construction $300,000 Total $350,000 Capital Cost FY2023 Budget $350,000 Total Budget $350K Capital Cost by Year Administration Design Engineering Construction 2023 $350,000.00 $0 $100K$200K$300K Capital Cost for Budgeted Years TOTAL $350,000.00 Administration (3%)$10,000.00 Design (6%) $20,000.00 Engineering (6%) $20,000.00 Construction (86%)$300,000.0 162 Funding Sources Breakdown Funding Sources FY2023 Capital Improvement Fund $350,000 Total $350,000 Funding Sources FY2023 Budget $350,000 Total Budget $350K Funding Sources by Year Capital Improve… 2023 $350,000.00 $0 $100K$200K$300K Funding Sources for Budgeted Years TOTAL $350,000.00 Capital Improvement Fund (10 163 SUMMERLY PARK IMPROVEMENTS Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Department Community Services Type Capital Improvement Description Convert the lighting on the elds without LED lights to LED, add temporary fencing, and eld renovations including safety netting for small elds and digital scoreboards and new shade structures.  Additionally, as Summerly Park hosts more tournaments and weekend activities, adequate stafng for the facility to maintain amenities is imperative. Currently, there is no location for staff to have areas to have a base of operations with a phone, areas to have breaks, etc. The addition of a small dedicated staff area will meet that need. Staff/ofce area will allow staff to operate, have breaks, and store equipment necessary for park programs, events, and activities. Images Summerly Snack Bar Location of proposed staff area. Summerly Ballelds Field improvements to include new ineld mix and LED lights. Details If funding source is other, please explain. None Type of Project None Location Benet to Community Upgraded facilities will allow for better user experience and eld quality for events and programs, such as tournaments, community gatherings, youth leagues, and adult leagues. 164 Capital Cost Breakdown Capital Cost FY2023 FY2024 Construction/Maintenance $941,200 $580,000 Total $941,200 $580,000 Capital Cost FY2023 Budget $941,200 Total Budget $1.521M Capital Cost by Year Construction/Mai… 2023 2024 $941,200.00 $580,000.00 $0 $250K$500K$750K Capital Cost for Budgeted Years TOTAL $1,521,200.00 Construction/Maintenance (10 165 Funding Sources Breakdown Funding Sources FY2023 FY2024 Capital Improvement Fund $941,200 $580,000 Total $941,200 $580,000 Funding Sources FY2023 Budget $941,200 Total Budget $1.521M Funding Sources by Year Capital Improve… 2023 2024 $941,200.00 $580,000.00 $0 $250K$500K$750K Funding Sources for Budgeted Years TOTAL $1,521,200.00 Capital Improvement Fund (10 166 TUSCANY HILLS PARK Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2024 Department Administration - Public Works Type Capital Improvement Description This project includes upgrading the restroom facilities, sports elds landscape, fencing repairs, roong repairs, playground oor resurfacing and installation of shade structures, picnic tables, benches, BBQ grills, and trash cans. Details If funding source is other, please explain. None Type of Project Refurbishment Location Benet to Community Renovating Tuscany Hills Park will create a more aesthetically pleasing environment and provide a safe play area while encouraging many residents to utilize city parks. 167 Capital Cost Breakdown Capital Cost To Date FY2023 Construction/Maintenance $618,640 $300,000 Total $618,640 $300,000 Capital Cost Total To Date $618,640 FY2023 Budget $300,000 Total Budget $300K Capital Cost by Year Construction/Mai… 2023 $300,000.00 $0 $80K$160K$240K Capital Cost for Budgeted Years TOTAL $300,000.00 Construction/Maintenance (10 168 Funding Sources Breakdown Funding Sources FY2023 Capital Improvement Fund $300,000 Total $300,000 Funding Sources FY2023 Budget $300,000 Total Budget $300K Funding Sources by Year Capital Improve… 2023 $300,000.00 $0 $80K$160K$240K Funding Sources for Budgeted Years TOTAL $300,000.00 Capital Improvement Fund (10 169 EAST LAKE CIRCULATION Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2026 Est. Completion Date 06/30/2032 Department Circulation Type Capital Improvement Description Construct a four (4) lane road to provide access and circulation for the East Lake Specic Plan and Diamond Specic Plan. Images EAST LAKE CIRCULATION Details If funding source is other, please explain. UNSPECIFIED Type of Project New Road Location Benet to Community To improve access and stimulate economic development projects. 170 Capital Cost Breakdown Capital Cost FY2027 Administration $100,000 Design $388,667 Construction/Maintenance $9,700,018 Total $10,188,685 Capital Cost Total Budget $10.189M Capital Cost by Year Administration Design Construction/Mai… 2027 $10,188,685.00 $0 $2.5M$5M$7.5M$1… Capital Cost for Budgeted Years TOTAL $10,188,685.00 Administration (1%)$100,000.0 Design (4%) $388,667.00 Construction/Maintenance (95 171 Funding Sources Breakdown Funding Sources FY2027 Other $10,188,685 Total $10,188,685 Funding Sources Total Budget $10.189M Funding Sources by Year Other 2027 $10,188,685.00 $0 $2.5M$5M$7.5M$1… Funding Sources for Budgeted Years TOTAL $10,188,685.00 Other (100%) $10,188,685.00 172 LA STRADA EXTENSION Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2027 Est. Completion Date 06/30/2035 Department Infrastructure Type Capital Improvement Description This project will extend La Strada west to Camino Del Norte with two (2) lanes in each direction along its entire length with a painted median. Images La Strada Details If funding source is other, please explain. LA STRADA RBBD/ FY22.23 PRELIM DESIGN WORK UNSPECIFIED Type of Project None Location Benet to Community Extending La Strada will provide a secondary re access route for residents in the Summerhill/La Strada corridor, as well as potentially provide a connection to the future Franklin Interchange. 173 Capital Cost Breakdown Capital Cost FY2027 Administration $285,921 Design $763,370 Engineering $1,908,425 Land/Right-of-way $1,897,000 Construction/Maintenance $24,018,849 Total $28,873,565 Capital Cost Total Budget $28.874M Capital Cost by Year Administration Design Engineering Land/Right-of-w… Construction/Mai… 2027 $28,873,565.00 $0 $8M $16M $24M Capital Cost for Budgeted Years TOTAL $28,873,565.00 Administration (1%)$285,921.00 Design (3%) $763,370.00 Engineering (7%)$1,908,425.00 Land/Right-of-way (7%)$1,897, Construction/Maintenance (83 174 Funding Sources Breakdown Funding Sources FY2027 Other $28,873,565 Total $28,873,565 Funding Sources Total Budget $28.874M Funding Sources by Year Other 2027 $28,873,565.00 $0 $8M $16M $24M Funding Sources for Budgeted Years TOTAL $28,873,565.00 Other (100%) $28,873,565.00 175 LAKE STREET WIDENING Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2027 Est. Completion Date 12/31/2032 Department Circulation Type Capital Improvement Description This project will realign and widen Lake Street. This will be a multi-functional corridor, which provides wildlife linkage, meandering pedestrian and bicycle paths, utility easements, a perennial owing creek, ponds, and a native re-vegetated landscape. With the landscape corridors and edges on both sides of Lake Street, combined with the landscaped roadway median, this Lake Street entry will form a broad canopy of native landscape. Lake Street’s cross section will vary from six (6) to eight (8) lanes, the eight (8) lanes occurring near the Temescal Canyon Road intersection and transitioning to six (6) lanes as it approaches Nichols Road. Bike lanes will be provided on both sides of the street. In addition, a new widened bridge will extend over Temescal Creek along Lake Street. Details If funding source is other, please explain. UNSPECIFIED Type of Project Other Location Benet to Community Lake Street is already a major thoroughfare off the I-15 Freeway. Once the project is completed, it will serve as the main entrance into Alberhill Villages and the northern gateway to the City. 176 Capital Cost Breakdown Capital Cost FY2027 Administration $250,000 Design $4,000,000 Engineering $1,500,000 Land/Right-of-way $1,305,000 Construction/Maintenance $29,013,909 Total $36,068,909 Capital Cost Total Budget $36.069M Capital Cost by Year Administration Design Engineering Land/Right-of-w… Construction/Mai… 2027 $36,068,909.00 $0 $10M $20M$30M Capital Cost for Budgeted Years TOTAL $36,068,909.00 Administration (1%)$250,000.0 Design (11%) $4,000,000.00 Engineering (4%)$1,500,000.00 Land/Right-of-way (4%)$1,305, Construction/Maintenance (80 177 Funding Sources Breakdown Funding Sources FY2027 Other $36,068,909 Total $36,068,909 Funding Sources Total Budget $36.069M Funding Sources by Year Other 2027 $36,068,909.00 $0 $10M $20M$30M Funding Sources for Budgeted Years TOTAL $36,068,909.00 Other (100%) $36,068,909.00 178 MAIN STREET BOLLARDS Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Est. Start Date 07/01/2027 Est. Completion Date 06/30/2028 Department Community Services Type Capital Improvement Description This project provides for the design and installation of approximately 88 bollards to execute 11 closures within the unimproved segment of Main Street between Library Street and Heald Avenue.  The project would allow for the opportunity for versatility of closure for a variety of events. Details If funding source is other, please explain. None Type of Project Other Location Benet to Community This project supports the City's efforts to provide world class programs and events.  This project would be a catalyst for future economic development supported by arts and culture initiatives in the downtown area.  These improvements will also reduce City road closure costs for existing events. 179 Capital Cost Breakdown Capital Cost FY2027 Construction/Maintenance $450,000 Total $450,000 Capital Cost Total Budget $450K Capital Cost by Year Construction/Mai… 2027 $450,000.00 $0 $120K$240K$360K Capital Cost for Budgeted Years TOTAL $450,000.00 Construction/Maintenance (10 180 Funding Sources Breakdown Funding Sources FY2027 Other $450,000 Total $450,000 Funding Sources Total Budget $450K Funding Sources by Year Other 2027 $450,000.00 $0 $120K$240K$360K Funding Sources for Budgeted Years TOTAL $450,000.00 Other (100%) $450,000.00 181 MAIN STREET MILL AND OVERLAY Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/03/2023 Est. Completion Date 06/30/2025 Department Circulation Type Capital Improvement Description This project will be a grind and overlay between Lakeshore and I-15 Interchange on Main Street. Images Main Street Details If funding source is other, please explain. Unspecied Type of Project Resurface Current Road Location Benet to Community Maintenance 182 Capital Cost Breakdown Capital Cost FY2024 Administration $10,000 Engineering $20,000 Construction/Maintenance $800,000 Total $830,000 Capital Cost Total Budget $830K Capital Cost by Year Administration Engineering Construction/Mai… 2024 $830,000.00 $0 $20…$40…$60…$… Capital Cost for Budgeted Years TOTAL $830,000.00 Administration (1%)$10,000.00 Engineering (2%) $20,000.00 Construction/Maintenance (96 183 Funding Sources Breakdown Funding Sources FY2024 Other $830,000 Total $830,000 Funding Sources Total Budget $830K Funding Sources by Year Other 2024 $830,000.00 $0 $20…$40…$60…$… Funding Sources for Budgeted Years TOTAL $830,000.00 Other (100%) $830,000.00 184 NICHOLS ROAD IMPROVEMENTS Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 08/17/2027 Est. Completion Date 12/28/2029 Department Circulation Type Capital Improvement Description This project will widen Nichols Road into a four-lane divided road with wide medians that link Lake Street and Lincoln Street. There are two distinct cross sections for Nichols Road. The section that bisects Alberhill Town Center, which employs unique left turn pockets and a wide median; and the section that extends westerly between Lakeside and Ridgeview Villages. Both sections will have bike lanes and non-adjacent sidewalks along each of their sides in order to provide a safe and enjoyable experience for the residents. Details If funding source is other, please explain. UNSPECIFIED Type of Project None Location Benet to Community Once completed, Nichols Road will serve as one of the three main east-west links between Lake Street and Lincoln Street. When combined with other streets and the pedestrian/bicycle paths, an interlocking modied grid will allow residents and visitors a variety of choices when moving around, through, and among the Alberhill Villages. 185 Capital Cost Breakdown Capital Cost FY2027 Administration $150,000 Design $3,600,000 Engineering $1,300,000 Land/Right-of-way $1,800,531 Construction/Maintenance $14,955,060 Total $21,805,591 Capital Cost Total Budget $21.806M Capital Cost by Year Administration Design Engineering Land/Right-of-w… Construction/Mai… 2027 $21,805,591.00 $0 $6M $12M $18M Capital Cost for Budgeted Years TOTAL $21,805,591.00 Administration (1%)$150,000.00 Design (17%) $3,600,000.00 Engineering (6%)$1,300,000.00 Land/Right-of-way (8%)$1,800 Construction/Maintenance (69 186 Funding Sources Breakdown Funding Sources FY2027 Other $21,805,591 Total $21,805,591 Funding Sources Total Budget $21.806M Funding Sources by Year Other 2027 $21,805,591.00 $0 $6M $12M $18M Funding Sources for Budgeted Years TOTAL $21,805,591.00 Other (100%) $21,805,591.00 187 SB 1 PAVEMENT REHABILITATION PROGRAM FY23.24 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2022 Est. Completion Date 06/28/2024 Department Infrastructure Type Capital Improvement Description The City receives Road Maintenance and Rehabilitation funds annually as part of the Road Repair and Accountability Act of 2017. Each year, the City must declare a specic project in May. The selected project is based on Pavement Conditions Indices (PCI) and Average Daily Trafc (ADT) demand. Details If funding source is other, please explain. None New Facility or Replacement Replacement Location Benet to Community This project represents the City's efforts to proactively maintain and extend the useful life of aging asphalt roadway surfaces. 188 Capital Cost Breakdown Capital Cost FY2024 Administration $15,000 Design $20,000 Construction $1,245,649 Total $1,280,649 Capital Cost Total Budget $1.281M Capital Cost by Year Administration Design Construction 2024 $1,280,649.00 $0 $400K$800K$1.2… Capital Cost for Budgeted Years TOTAL $1,280,649.00 Administration (1%)$15,000.00 Design (2%) $20,000.00 Construction (97%)$1,245,649.0 189 Funding Sources Breakdown Funding Sources FY2024 Grant(s)$1,280,649 Total $1,280,649 Funding Sources Total Budget $1.281M Funding Sources by Year Grant(s) 2024 $1,280,649.00 $0 $400K$800K$1.2… Funding Sources for Budgeted Years TOTAL $1,280,649.00 Grant(s) (100%) $1,280,649.00 190 SB 1 PAVEMENT REHABILITATION PROGRAM FY24.25 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2024 Est. Completion Date 06/30/2025 Department Infrastructure Type Capital Improvement Description The City receives Road Maintenance and Rehabilitation funds annually as part of the Road Repair and Accountability Act of 2017. Each year, the City must declare a specic project in May. The selected project is based on Pavement Conditions Indices (PCI) and Average Daily Trafc (ADT) demand. Details If funding source is other, please explain. None New Facility or Replacement Replacement Location Benet to Community This project represents the City's efforts to proactively maintain and extend the useful life of aging asphalt roadway surfaces. 191 Capital Cost Breakdown Capital Cost FY2025 Administration $15,000 Design $20,000 Construction $1,271,262 Total $1,306,262 Capital Cost Total Budget $1.306M Capital Cost by Year Administration Design Construction 2025 $1,306,262.00 $0 $400K$800K$1.2M Capital Cost for Budgeted Years TOTAL $1,306,262.00 Administration (1%)$15,000.00 Design (2%) $20,000.00 Construction (97%)$1,271,262.0 192 Funding Sources Breakdown Funding Sources FY2025 Grant(s)$1,306,262 Total $1,306,262 Funding Sources Total Budget $1.306M Funding Sources by Year Grant(s) 2025 $1,306,262.00 $0 $400K$800K$1.2M Funding Sources for Budgeted Years TOTAL $1,306,262.00 Grant(s) (100%) $1,306,262.00 193 SB 1 PAVEMENT REHABILITATION PROGRAM FY25.26 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2025 Est. Completion Date 06/30/2026 Department Infrastructure Type Capital Improvement Description The City receives Road Maintenance and Rehabilitation funds annually as part of the Road Repair and Accountability Act of 2017. Each year, the City must declare a specic project in May. The selected project is based on Pavement Conditions Indices (PCI) and Average Daily Trafc (ADT) demand. Details If funding source is other, please explain. None New Facility or Replacement Replacement Location Benet to Community This project represents the City's efforts to proactively maintain and extend the useful life of aging asphalt roadway surfaces. 194 Capital Cost Breakdown Capital Cost FY2026 Administration $15,000 Design $20,000 Construction $1,297,387 Total $1,332,387 Capital Cost Total Budget $1.332M Capital Cost by Year Administration Design Construction 2026 $1,332,387.00 $0 $400K$800K$1.2M Capital Cost for Budgeted Years TOTAL $1,332,387.00 Administration (1%)$15,000.00 Design (2%) $20,000.00 Construction (97%)$1,297,387.0 195 Funding Sources Breakdown Funding Sources FY2026 Grant(s)$1,332,387 Total $1,332,387 Funding Sources Total Budget $1.332M Funding Sources by Year Grant(s) 2026 $1,332,387.00 $0 $400K$800K$1.2M Funding Sources for Budgeted Years TOTAL $1,332,387.00 Grant(s) (100%) $1,332,387.00 196 SB 1 PAVEMENT REHABILITATION PROGRAM FY26.27 Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2026 Est. Completion Date 06/30/2027 Department Infrastructure Type Capital Improvement Description The City receives Road Maintenance and Rehabilitation funds annually as part of the Road Repair and Accountability Act of 2017. Each year, the City must declare a specic project in May. The selected project is based on Pavement Conditions Indices (PCI) and Average Daily Trafc (ADT) demand. Details If funding source is other, please explain. None New Facility or Replacement Replacement Location Benet to Community This project represents the City's efforts to proactively maintain and extend the useful life of aging asphalt roadway surfaces. 197 Capital Cost Breakdown Capital Cost FY2027 Administration $15,000 Design $20,000 Construction $1,297,387 Total $1,332,387 Capital Cost Total Budget $1.332M Capital Cost by Year Administration Design Construction 2027 $1,332,387.00 $0 $400K$800K$1.2M Capital Cost for Budgeted Years TOTAL $1,332,387.00 Administration (1%)$15,000.00 Design (2%) $20,000.00 Construction (97%)$1,297,387.0 198 Funding Sources Breakdown Funding Sources FY2027 Grant(s)$1,332,387 Total $1,332,387 Funding Sources Total Budget $1.332M Funding Sources by Year Grant(s) 2027 $1,332,387.00 $0 $400K$800K$1.2M Funding Sources for Budgeted Years TOTAL $1,332,387.00 Grant(s) (100%) $1,332,387.00 199 STATE ROUTE 74 WIDENING Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 06/01/2026 Est. Completion Date 12/29/2028 Department Circulation Type Capital Improvement Description This project will widen State Route 74, west of I-15 to the Ortega mountains. The widening will increase the number of lanes from two (2) up to six (6) (A study is necessary to determine the feasibility of more than four (4) lanes) and include turn pockets and one trafc signal at the intersection of SR74 (Riverside Drive) and Grand Avenue. Details If funding source is other, please explain. None Type of Project None Location Benet to Community This project will improve trafc safety, operations, and capacity by minimizing trafc delays and reducing congestion. 200 Capital Cost Breakdown Capital Cost To Date FY2027 Administration $4,745 $50,000 Engineering $1,500,000 Land/Right-of-way $5,600,000 Construction/Maintenance $4,400,000 Total $4,745 $11,550,000 Capital Cost Total To Date $4,745 Total Budget $11.55M Capital Cost by Year Administration Engineering Land/Right-of-w…Construction/Mai… 2027 $11,550,000.00 $0 $3M $6M $9M Capital Cost for Budgeted Years TOTAL $11,550,000.00 Administration (0%)$50,000.00 Engineering (13%)$1,500,000.0 Land/Right-of-way (48%)$5,60 Construction/Maintenance (38 201 Funding Sources Breakdown Funding Sources To Date FY2027 TUMF $11,500,000 Other $4,745 $50,000 Total $4,745 $11,550,000 Funding Sources Total To Date $4,745 Total Budget $11.55M Funding Sources by Year TUMF Other 2027 $11,550,000.00 $0 $3M $6M $9M Funding Sources for Budgeted Years TOTAL $11,550,000.00 TUMF (100%) $11,500,000.00 Other (0%) $50,000.00 202 AQUATICS CENTER Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Department Community Services Type Capital Improvement Description Development of a state of the art 25x50 meter deep water pool that accommodate water polo, competitive swimming, scuba diving, paddle sports, high diving, recreational use.  Facility will host regional aquatic events while have a secured location for City sponsored programs.   Details If funding source is other, please explain.None Type of Project New Construction 203 Capital Cost Breakdown Capital Cost FY2026 Administration $200,000 Design $325,000 Engineering $325,000 Construction/Maintenance $18,500,000 Furniture, Fixtures and Equipment $650,000 Total $20,000,000 Capital Cost Total Budget $20M Capital Cost by Year Administration Design Engineering Construction/Mai… Furniture, Fixture… 2026 $20,000,000.00 $0 $5M $10M$15M$… Capital Cost for Budgeted Years TOTAL $20,000,000.00 Administration (1%)$200,000.0 Design (2%) $325,000.00 Engineering (2%) $325,000.00 Construction/Maintenance (93 Furniture, Fixtures and Equipm 204 Funding Sources Breakdown Funding Sources FY2026 Other $20,000,000 Total $20,000,000 Funding Sources Total Budget $20M Funding Sources by Year Other 2026 $20,000,000.00 $0 $5M $10M$15M$… Funding Sources for Budgeted Years TOTAL $20,000,000.00 Other (100%) $20,000,000.00 205 Operational Costs Breakdown Operational Costs FY2026 FY2027 General Maintenance $300,000 $300,000 Utilities $300,000 $300,000 Total $600,000 $600,000 Operational Costs Total Budget $1.2M Operational Costs by Year General Maintena…Utilities 2026 2027 $600,000.00 $600,000.00 $0 $150K$300$450$… Operational Costs for Budgeted Years TOTAL $1,200,000.00 General Maintenance (50%)$60 Utilities (50%) $600,000.00 206 COMMUNITY CENTER Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Department Community Services Type Capital Improvement Description Design and construction of a park, community center (approx 15-20k square feet), and library centrally located in the city or apply funds for construction of to up to three smaller neighborhood centers (around 5-10k square feet) dispersed throughout the City (potentially Summerly, Canyon Hills, and Alberhill).   Details If funding source is other, please explain.None Type of Project New Construction 207 Capital Cost Breakdown Capital Cost FY2024 FY2025 Administration $600,000 $600,000 Design $1,800,000 $1,200,000 Engineering $1,500,000 $1,650,000 Construction/Maintenance $7,500,000 Furniture, Fixtures and Equipment $900,000 $750,000 Land Acquisition $1,200,000 $300,000 Total $6,000,000 $12,000,000 Capital Cost Total Budget $18M Capital Cost by Year Administration Design Engineering Construction/Mai… Furniture, Fixture…Land Acquisition 2024 2025 $6,000,000.00 $12,000,000.00 $0 $3M $6M $9M$… Capital Cost for Budgeted Years TOTAL $18,000,000.00 Administration (7%)$1,200,000 Design (17%) $3,000,000.00 Engineering (18%)$3,150,000.0 Construction/Maintenance (42 Furniture, Fixtures and Equipm Land Acquisition (8%)$1,500,00 208 Funding Sources Breakdown Funding Sources FY2024 FY2025 Other $6,000,000 $12,000,000 Total $6,000,000 $12,000,000 Funding Sources Total Budget $18M Funding Sources by Year Other 2024 2025 $6,000,000.00 $12,000,000.00 $0 $3M $6M $9M$… Funding Sources for Budgeted Years TOTAL $18,000,000.00 Other (100%) $18,000,000.00 209 Operational Costs Breakdown Operational Costs FY2025 FY2026 FY2027 General Maintenance $25,000 $50,000 $50,000 Other $250,000 $500,000 $500,000 Utilities $15,000 $30,000 $30,000 Total $290,000 $580,000 $580,000 Operational Costs Total Budget $1.45M Operational Costs by Year General Maintena…Other Utilities 2025 2026 2027 $290,000.00 $580,000.00 $580,000.00 $0 $150K$300K$450K Operational Costs for Budgeted Years TOTAL $1,450,000.00 General Maintenance (9%)$125, Other (86%) $1,250,000.00 Utilities (5%) $75,000.00 210 MAIN STREET ARCHWAY Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Est. Start Date 09/01/2022 Est. Completion Date 02/01/2023 Department Community Services Type Capital Improvement Description This project provides for the design and construction of two Main Street archways that host horizontal landscape style steel (street banner size, i.e. 10' x 3'), hanging LED screens to promote upcoming events, information, waynding, etc. near Library Steet and Heald Avenue. Details If funding source is other, please explain. None New Facility or Replacement New Location Benet to Community This project supports the City's efforts to improve marketing to the community for upcoming community events and programs.  These improvements will also increase City revenues by drawing in more participants to the events and stimulating further economic returns in the downtown area. 211 Capital Cost Breakdown Capital Cost FY2025 Administration $30,000 Design $45,000 Engineering $20,000 Construction $585,000 Total $680,000 Capital Cost Total Budget $680K Capital Cost by Year Administration Design Engineering Construction 2025 $680,000.00 $0 $200K$400K$600K Capital Cost for Budgeted Years TOTAL $680,000.00 Administration (4%)$30,000.00 Design (7%) $45,000.00 Engineering (3%) $20,000.00 Construction (86%)$585,000.0 212 Funding Sources Breakdown Funding Sources FY2025 NPDES $680,000 Total $680,000 Funding Sources Total Budget $680K Funding Sources by Year NPDES 2025 $680,000.00 $0 $200K$400K$600K Funding Sources for Budgeted Years TOTAL $680,000.00 NPDES (100%) $680,000.00 213 SENIOR CENTER IMPROVEMENTS Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Department Community Services Type Capital Improvement Description With the expansion of senior programming at the Lake Elsinore Senior Activity Center, additional indoor space is needed to meet the need. This project will expand the Annex building of the Senior Center to the existing patio cover. This will also provide for an expanded area for programs and rentals for private events.  This enclosure will provide additional climate-controlled  space to allow the City to better serve the senior and active adults in the community. Images Senior Center Annex Interior Location of proposed expansion. Senior Center Annex Patio Location of proposed expansion. Details If funding source is other, please explain. None Type of Project New Construction Location 214 Capital Cost Breakdown Capital Cost FY2024 Construction/Maintenance $300,000 Total $300,000 Capital Cost Total Budget $300K Capital Cost by Year Construction/Mai… 2024 $300,000.00 $0 $80K$160K$240K Capital Cost for Budgeted Years TOTAL $300,000.00 Construction/Maintenance (10 215 Funding Sources Breakdown Funding Sources FY2024 Measure Z $300,000 Total $300,000 Funding Sources Total Budget $300K Funding Sources by Year Measure Z 2024 $300,000.00 $0 $80K$160K$240K Funding Sources for Budgeted Years TOTAL $300,000.00 Measure Z (100%)$300,000.00 216 THIRD STREET DRAINAGE IMPROVEMENTS PHASE III Overview Submitted By Nicole McCalmont, CIP Specialist Request Owner Nicole McCalmont, CIP Specialist Est. Start Date 07/01/2023 Est. Completion Date 06/30/2025 Department Infrastructure Type Capital Improvement Description This project includes the complete design, hydrology/hydraulic analysis and construction of missing storm drain improvements along Third Street, Conard Avenue and Welch Drive starting at Cambern Avenue. Improvements include the construction of new storm drains, catch basins, laterals, and modications to existing ood control channel downstream. Images Third Street Drainage Phase III Details If funding source is other, please explain. Unspecied New Facility or Replacement New Location Benet to Community The project will improve emergency access, safety, and circulation in the area by maintaining the integrity of the roadway during inclement weather. This project also supports the removal of certain properties currently identi ed in the ood plain area west of Interstate 15. 217 Capital Cost Breakdown Capital Cost FY2024 FY2025 Administration $200,000 Engineering $300,000 Construction $567,024 $567,024 Total $1,067,024 $567,024 Capital Cost Total Budget $1.634M Capital Cost by Year Administration Engineering Construction 2024 2025 $1,067,024.00 $567,024.00 $0 $300K$600K$900K Capital Cost for Budgeted Years TOTAL $1,634,048.00 Administration (12%)$200,000. Engineering (18%)$300,000.00 Construction (69%)$1,134,048.0 218 Funding Sources Breakdown Funding Sources FY2024 FY2025 Other $1,067,024 $567,024 Total $1,067,024 $567,024 Funding Sources Total Budget $1.634M Funding Sources by Year Other 2024 2025 $1,067,024.00 $567,024.00 $0 $300K$600K$900K Funding Sources for Budgeted Years TOTAL $1,634,048.00 Other (100%) $1,634,048.00 219 ALBERHILL VILLAGE SPORTS PARK Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 07/01/2026 Est. Completion Date 06/30/2027 Department Parks Type Capital Improvement Description This project is a new 46-acre park facility. The improvements will consist of constructing new soccer and baseball elds, volleyball and basketball courts, restroooms, picnic areas, concession stand, and play areas for children. Details If funding source is other, please explain.None Type of Project New Construction Benet to Community The Alberhill Villages Sports Park is necessary to meet the needs of the community in the Alberhill Villages Specic Plan (AVSP), encourage residents to utilize the City's parks, and continue in the tradition of the Action Sports Capital of the World. 220 Capital Cost Breakdown Capital Cost FY2027 Design $1,000,000 Engineering $1,000,000 Construction/Maintenance $42,000,000 Equipment/Vehicle/Furnishings $1,000,000 Total $45,000,000 Capital Cost Total Budget $45M Capital Cost by Year Design Engineering Construction/Mai…Equipment/Vehic… 2027 $45,000,000.00 $0 $12M$24M$36M Capital Cost for Budgeted Years TOTAL $45,000,000.00 Design (2%) $1,000,000.00 Engineering (2%)$1,000,000.00 Construction/Maintenance (93 Equipment/Vehicle/Furnishing 221 Funding Sources Breakdown Funding Sources FY2027 Other $45,000,000 Total $45,000,000 Funding Sources Total Budget $45M Funding Sources by Year Other 2027 $45,000,000.00 $0 $12M$24M$36M Funding Sources for Budgeted Years TOTAL $45,000,000.00 Other (100%) $45,000,000.00 222 LAKE REVITALIZATION PLAN Overview Submitted By Brendan Rafferty, Fiscal Ofcer Request Owner Brendan Rafferty, Fiscal Ofcer Est. Start Date 07/01/2023 Est. Completion Date 06/30/2024 Department Parks Type Capital Improvement Description The Lake Revitalization Plan will create a pathway to perform critical infrastructure renovations aimed at improving sustainability of Lake Elsinore, enhancing public access and utilization of the Lake, and supporting new public and private investment around the Lake, including infrastructure upgrades and land development. Details If funding source is other, please explain. None Type of Project Other improvement Location Benet to Community Renovating the Lake is critical to the City's vision of becoming the ultimate lake destination where all can live, work and play, build futures and fulll dreams. 223 Capital Cost Breakdown Capital Cost FY2024 Design $1,000,000 Total $1,000,000 Capital Cost Total Budget $1M Capital Cost by Year Design 2024 $1,000,000.00 $0 $250 $500$750$… Capital Cost for Budgeted Years TOTAL $1,000,000.00 Design (100%) $1,000,000.00 224 Funding Sources Breakdown Funding Sources FY2024 Other $1,000,000 Total $1,000,000 Funding Sources Total Budget $1M Funding Sources by Year Other 2024 $1,000,000.00 $0 $250 $500$750$… Funding Sources for Budgeted Years TOTAL $1,000,000.00 Other (100%) $1,000,000.00 225 226 LAUNCH POINTE - THE RESERVE Overview Submitted By Beau Davis, Assistant Community Services Director Request Owner Beau Davis, Assistant Community Services Director Est. Start Date 11/01/2023 Est. Completion Date 05/01/2024 Department Launch Pointe Resort Type Capital Improvement Description Launch Pointe's world-class amenities have proven to be the recreation destination in Southern California. One area that performs the poorest is the Yurt Village. The six units on the four acres can gross a max of $2,500 in revenue on a regular weekend ($625 p/a). The LP Square, The Ineld, and Vintage Village consist of approximately 12.5 acres and can gross as much as $20,000 on a regular weekend ($1,600 p/a). This averages to almost three times as much per acre as the Yurt Village. This proposal is to begin forming a plan to convert the Yurt Village to an exclusive area of Launch Pointe informally dubbed "The Reserve". The Reserve will consist of 10-15 park models matching the theme of Launch Pointe and the existing Yurts. The Reserve would also have an exclusive pool/ spa and venue space which could accommodate a minimum 200 persons. With 10 new park model units and the six existing yurts, The Reserve could gross an average of $8,500 per weekend, putting the per-acre revenues at $2,125 which is $525 more per acre than the 12.5 acres of primary LP RV/ Lodging space. Additional revenues would be earned through the bookings of the larger more accessible event space. The existing Community Hall would be used for smaller events and to enhance the amenity offerings for the resort campers and visitors. An example of some uses are to offer a game room, a hall for groups, and activity gathering space when not reserved for a private function. Images RV Pool and Adjoining Facility An example of the possible proximity of a resort pool and facility next to pool Event Space Example of possible event space for exclusive use at The Reserve. Space would be ideal if able to accommodate a minimum 200 persons. Park Model Row An example of park models and their uniformity 227 Yurt View View from the Lodge Yurt Looking East Details If funding source is other, please explain. Launch Pointe Revenue Generation Type of Project New Construction Location Address: 32040 Riverside Drive 228 Capital Cost Breakdown Capital Cost FY2024 Administration $100,000 Design $100,000 Engineering $100,000 Construction/Maintenance $2,500,000 Furniture, Fixtures and Equipment $200,000 Total $3,000,000 Capital Cost Total Budget $3M Capital Cost by Year Administration Design Engineering Construction/Mai… Furniture, Fixture… 2024 $3,000,000.00 $0 $800K$1.6M$2.4M Capital Cost for Budgeted Years TOTAL $3,000,000.00 Administration (3%)$100,000.0 Design (3%) $100,000.00 Engineering (3%) $100,000.00 Construction/Maintenance (83 Furniture, Fixtures and Equipm 229 Funding Sources Breakdown Funding Sources FY2024 Other $3,000,000 Total $3,000,000 Funding Sources Total Budget $3M Funding Sources by Year Other 2024 $3,000,000.00 $0 $800K$1.6M$2.4M Funding Sources for Budgeted Years TOTAL $3,000,000.00 Other (100%) $3,000,000.00 230 Operational Costs Breakdown Operational Costs FY2024 FY2025 FY2026 FY2027 General Maintenance $70,000 $140,000 $140,000 $140,000 Utilities $25,000 $50,000 $50,000 $50,000 Total $95,000 $190,000 $190,000 $190,000 Operational Costs Total Budget $665K Operational Costs by Year General Maintena…Utilities 2024 2025 2026 2027 $95,000.00 $190,000.00 $190,000.00 $190,000.00 $0 $50K$100K$150K Operational Costs for Budgeted Years TOTAL $665,000.00 General Maintenance (74%)$49 Utilities (26%) $175,000.00 231 SERENITY PARK FITNESS TRAIL Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Est. Start Date 07/01/2023 Est. Completion Date 12/31/2023 Department Community Services Type Capital Improvement Description Install 12 new pieces of tness equipment, including accessible units, install ADA ramp to tness trail, new DG path and ground cover.  Project is part of CA State Parks Per Capita Grant proposal. Images Details If funding source is other, please explain. Unspecied Type of Project Refurbishment Location Supplemental Attachments Excel Landscape Estimate(/resource/cleargov-prod/projects/documents/3c6827a4df1e5ee1bf1b.pdf) Installation of DG, ADA Ramp, mow curb Greenelds Exercise Equipment Quote(/resource/cleargov-prod/projects/documents/a85590c9c6c0d4e53314.pdf) Benet to Community 232 The upgraded trail will provide opportunities for physical tness and outdoor recreation with accessible features for people with disabilities.   Capital Cost Breakdown Capital Cost FY2024 Construction/Maintenance $350,000 Total $350,000 Capital Cost Total Budget $350K Capital Cost by Year Construction/Mai… 2024 $350,000.00 $0 $100K$200K$300K Capital Cost for Budgeted Years TOTAL $350,000.00 Construction/Maintenance (10 233 Funding Sources Breakdown Funding Sources FY2024 Grant(s)$82,775 Other $267,225 Total $350,000 Funding Sources Total Budget $350K Funding Sources by Year Grant(s)Other 2024 $350,000.00 $0 $100K$200K$300K Funding Sources for Budgeted Years TOTAL $350,000.00 Grant(s) (24%) $82,775.00 Other (76%) $267,225.00 234 SNACK BAR IMPROVEMENTS Overview Submitted By Benjamin Foster, Management Analyst Request Owner Benjamin Foster, Management Analyst Department Community Services Type Capital Improvement Description Currently, not all parks are up to Riverside county Health (food and beverage) standards to be able to serve anything but pre-packaged food. With an upgrade, youth leagues and facility rentals can expand the services of hot food through a secured locatn within the parks. Serving windows, air conditioning, Commercial refrigerators, commercial freezers, shelving, 3 bay stainless sinks, expanding Lakepoint and Mcvicker. Details If funding source is other, please explain.None Type of Project None Capital Cost Breakdown Capital Cost FY2025 Construction/Maintenance $400,000 Total $400,000 Capital Cost Total Budget $400K Capital Cost by Year Construction/Mai… 2025 $400,000.00 $0 $100K$200$300$… Capital Cost for Budgeted Years TOTAL $400,000.00 Construction/Maintenance (10 235 Funding Sources Breakdown Funding Sources FY2025 Capital Improvement Fund $400,000 Total $400,000 Funding Sources Total Budget $400K Funding Sources by Year Capital Improve… 2025 $400,000.00 $0 $100K$200$300$… Funding Sources for Budgeted Years TOTAL $400,000.00 Capital Improvement Fund (10 236 SPLASH PAD INSTALLATION Overview Submitted By Francisco Diaz, Public Works Superintendent Request Owner Francisco Diaz, Public Works Superintendent Est. Start Date 07/01/2022 Est. Completion Date 06/30/2023 Department Administration - Public Works Type Capital Improvement Description Installation of new splash pads at Summerlake Park and Rosetta Park. Details If funding source is other, please explain. None Type of Project New Construction Location Benet to Community Splash pads are becoming increasingly popular. Adding splash pads to both Summerlake Park and Rosetta Park will draw more attention to these parks and alleviate public demand to use Launch Pointe. 237 Capital Cost Breakdown Capital Cost FY2025 Other $2,110,000 Total $2,110,000 Capital Cost Total Budget $2.11M Capital Cost by Year Other 2025 $2,110,000.00 $0 $600K$1.2M $1.8M Capital Cost for Budgeted Years TOTAL $2,110,000.00 Other (100%) $2,110,000.00 238 Funding Sources Breakdown Funding Sources FY2025 Other $2,110,000 Total $2,110,000 Funding Sources Total Budget $2.11M Funding Sources by Year Other 2025 $2,110,000.00 $0 $600K$1.2M $1.8M Funding Sources for Budgeted Years TOTAL $2,110,000.00 Other (100%) $2,110,000.00 239 Operational Costs Breakdown Operational Costs FY2026 FY2027 Utilities $10,000 $10,000 General Maintenance $50,000 $50,000 Total $60,000 $60,000 Operational Costs Total Budget $120K Operational Costs by Year Utilities General Maintena… 2026 2027 $60,000.00 $60,000.00 $0 $15K $30K$45K$… Operational Costs for Budgeted Years TOTAL $120,000.00 Utilities (17%) $20,000.00 General Maintenance (83%)$10 240