Hi Sonia,
AO Architects recently received a ‘Conditions of Approval’ letter for our Planning Entitlement project below.
The Developer is Saddleback Associates and the project is an industrial business park located on Collier Avenue just West of the 74.
We have one question below (Item 35)
CONDITIONS OF APPROVAL
PROJECT:PA 2021-13/TPM 38124/IDR 2021-01
PROJECT NAME:North Elsinore Business Park
PROJECT LOCATION:APNs: 389-220-003, 004, 005, and 006
APPROVAL DATE:
EFFECTIVE DATE:
EXPIRATION DATE:
Damian Daniel | Associate
T 714.639.9860 M 714.457.7370
DISCLAIMER: Click to view disclaimers that apply to this email and any attachments.
Hi Sonia,
These are conditions of approval for Building Department. Can you review Item 35 and clarify what we are required to do as it relates to 10% voluntary green measures?
Typically, the California Green Standards outline what is required for each project. Just need to understand the 10% voluntary green measures.
Thanks,