HomeMy WebLinkAboutItem No. 10 PWCA Musco Sports Lighting Canyon Hills ParkCity Council Agenda Report City of Lake Elsinore 130 South Main Street Lake Elsinore, CA 92530 www.lake-elsinore.org File Number: ID# 19-544 Agenda Date: 4/14/2020 Status: Approval FinalVersion: 1 File Type: Council Consent Calendar In Control: City Council / Successor Agency Agenda Number: 10) Public Works Construction Contract Award to Musco Sports Lighting LLC for Canyon Hills Park LED Field Lighting Retro-Fit (CIP Project # Z40024) 1.Award the Public Works Construction Agreement for the Canyon Hills LED Field Lighting Retro -Fit to Musco Sports Lighting, LLC; 2.Authorize the City Manager to execute the agreement for $473,850.00 to Musco Sports Lighting LLC, in substantially the form attached and in such final form as approved by the City Attorney; 3.Authorize the City Manager to execute change orders not to exceed the 10% contingency amount of $47,385.00; and 4.Authorize the City Clerk to record the notice of completion upon completion. Page 1 City of Lake Elsinore Printed on 7/1/2020 REPORT TO CITY COUNCIL To: Honorable Mayor and Members of the City Council From: Grant Yates, City Manager Prepared by: Jason Simpson, Assistant City Manager Date: April 14, 2020 Subject: Public Works Construction Contract Award to Musco Sports Lighting LLC for Canyon Hills Park LED Field Lighting Retro-Fit (CIP Project # Z40024). Recommendations 1. Award the Public Works Construction Agreement for the Canyon Hills LED Field Lighting Retro-Fit to Musco Sports Lighting LLC; 2. Authorize the City Manager to execute the agreement for $473,850.00 to Musco Sports Lighting LLC, in substantially the form attached and in such final form as approved by the City Attorney; 3. Authorize the City Manager to execute change orders not to exceed the 10% contingency amount of $47,385.00; and 4. Authorize the City Clerk to record the notice of completion upon completion. Background The City is performing various lighting efficiency and lighting improvement projects to Lake Elsinore sports fields City-wide. The Canyon Hills field lighting system requires LED lighting to replace the existing lighting due to the repairs and maintenance of bulb burnouts. The new LED lighting technology will operate more efficiently than the existing metal halide lights. Also, the quality of lighting on the playing fields will be much improved. Discussion The project will include the removal of all field light racks and bulbs from the poles and install new lighting racks with the latest LED bulbs. Lighting control systems will be updated to manage and control the lighting system remotely from a PC or smartphone. The lighting package of 92 LED luminaires will be factory aimed and assembled with ball tracker luminaires. Musco sports cluster control systems and warranty services are considered by many to be the best in field lighting. The product assurance and warranty program will cover materials and labor, eliminating 100% of the City’s maintenance costs for ten years. Musco Sports Lighting LLC (Canyon Hills Park) April 14, 2020 Page 2 Once purchased, the delivery of this system is estimated at 6 to 8 weeks before the City receives the materials. Upon receipt of the materials, the installation of the new lighting system is expected to take 3 to 6 weeks. Musco field lighting systems have been competitively bid and priced on Sourcewell, master project #199030, contract number 071619-MSL, with an expiration date of 8/27/2023. Sourcewell, formerly National Joint Powers Alliance, was created by state law as a service cooperative to provide programs and services to members in education and government. Sourcewell was established with the statutory purpose to assist members in meeting specific needs which are more efficiently delivered cooperatively than by an entity individually. Sourcewell is authorized to establish competitively awarded cooperative purchasing contracts on behalf of itself and its member agencies. Sourcewell follows the competitive contracting law process to solicit, evaluate, and award cooperative purchasing contracts for goods and services. Sourcewell cooperative purchasing contracts are made available through the joint exercise of powers law to member agencies. Member agencies include all eligible government, education, and non-profit agencies nationwide and in Canada. The attached proposal from Musco proposes LED Lighting Retro-Fit with a sports cluster system and total light control technology at $473,850.00 (inclusive of sales tax). Following the approval of this agenda item, the staff will execute a City purchase and installation agreement for the entire system and place the material for an estimated installation in May 2020. Fiscal Impact Canyon Hills Field Lighting Project (CIP Project # Z40024) is included in the Fiscal Year 2019/2020 Capital Improvement Plan (CIP) budget. Exhibits A - Agreement B - Proposal Agreement No. __________ AGREEMENT FOR PUBLIC WORKS CONSTRUCTION CANYON HILLS PARK FIELD LIGHTING IMPROVEMENTS PROJECT CIP PROJECT NO. Z40024 This Agreement for Public Works Construction (“Agreement”) is made and entered into as of April 14, 2020, by and between the City of Lake Elsinore, a municipal corporation (‘‘City”), and Musco Sports Lighting LLC. (“Contractor”). The City and Contractor, in consideration of the mutual promises and covenants set forth herein, agree as follows: 1. The Project and Project Documents. Contractor agrees to construct the following public improvements (“work”) identified as: CANYON HILLS PARK FIELD LIGHTING IMPROVEMENTS The Project Documents include this Agreement and all of the following: (1) Proposal Documents including Bidder’s Proposal as submitted by the Contractor, Contract Documents, General Specifications, Special Provisions, and all attachments and appendices; (2) everything referenced in such documents, such as specifications, details, standard plans or drawings and appendices, including all applicable State and Federal requirements; (3) all required bonds, insurance certificates, permits, notices, and affidavits; and (4) any and all addenda or supplemental agreements clarifying, amending or extending the work contemplated as may be required to ensure completion in an acceptable manner. All of the provisions of the above-listed documents are made a part of this Agreement as though fully set forth herein. 2. Compensation. a. For and in consideration of the payments and agreements to be made and performed by City, Contractor agrees to construct the Project, including furnishing all materials and performing all work required for the Project and to fulfill all other obligations as set forth in the Bidder’s Proposal, such initial contract price of four hundred seventy-three thousand eight hundred fifty dollars and no cents ($473,850.00). b. City hereby promises and agrees to employ, and does hereby employ, Contractor to provide the materials, do the work, and fulfill the obligations according to the terms and conditions herein contained and referred to, for the prices set forth, and hereby contracts to pay the same at the time, in the manner, and upon the conditions set forth in the Project Documents. c. The Contractor agrees to receive and accept the prices set forth in the Bidder’s Proposal as full compensation for furnishing all materials, performing all work, and fulfilling all obligations hereunder. Such compensation shall cover all expenses, losses, damages, and consequences arising out of the nature of work during its progress or prior to its acceptance including those for well and faithfully completing the work and the whole thereof in the manner and time specified in the Project Documents; and also including those arising from actions of the elements, unforeseen difficulties or obstructions encountered in the prosecution of the work, suspension or discontinuance of the work, and all other unknowns or risks of any description connected with the work. 3. Completion of Work. a. Contractor shall perform and complete all work within Forty-Five (45) working days from the date of commencement specified in the Notice to Proceed and shall provide, furnish and pay for all the labor, materials, necessary tools, expendable equipment, and all taxes, utility, and transportation services required for construction of the Project. b. All work shall be performed and completed in a good, skillful manner in strict accordance with the drawings, specifications, and all provisions of this Agreement as hereinabove defined and in accordance with applicable laws, codes, regulations, ordinances, and any other legal requirements governing the Project. c. Contractor shall not be excused with respect to the failure to so comply by any act or omission of the City, the Director of Public Works, the City Engineer, a City inspector, or a representative of any of them unless such act or omission actually prevents the Contractor from fully complying with the requirements of the Project Documents, and unless the Contractor protests at the time of such alleged prevention that the act or omission is preventing the Contractor from fully complying with the Project Documents. Such protest shall not be effective unless reduced to writing and filed with the City within three (3) working days of the date of occurrence of the act or omission preventing the Contractor from fully complying with the Project Documents. d. City and Contractor recognize that time is of the essence in the performance of this Agreement and further agree that if the work called for under the Agreement is not completed within the time hereinabove specified, damages will be sustained by the City and that, it is and will be impracticable or extremely difficult to ascertain and determine the actual amount of damages the City will sustain in the event of, and because of, such delay. It is, therefore, agreed that such damages shall be presumed to be in the amount of One Thousand dollars ($1,000) per calendar day, and that the Contractor will pay to the City, or City may retain from amounts otherwise payable to Contractor, such amount for each calendar day by which the Contractor f ails to complete the work, including corrective items of work, under this Agreement within the time hereinabove specified and as adjusted by any changes to the work. 4. Changes to Work. City and Contractor agree that the City may make changes to the work, or suspend the work, and no matter how many changes, such changes or suspensions are within the contemplation of the Contractor and City and will not be a basis for a compensable delay claim against the City nor be the basis for a liquidated damages claims against the Contractor. Any change to the work shall be by way of a written instrument (“change order”) signed by the City and the Contractor, stating their Agreement to the following: a. The scope of the change in the work; b. The amount of the adjustment to the contract price; and c. The extent of the adjustment to the Schedule of Performance. The Executive Director is authorized to sign any change order provided that sufficient contingency funds are available in the City’s approved budget for the Project. All change in the work authorized by the change order shall be performed under the applicable conditions of the Project Documents. City and Contractor shall negotiate in good faith and as expeditiously as possible the appropriate adjustments for such changes. 5. Bonds. Contractor shall provide, before commencing work, a Faithful Performance Bond and a Labor and Material Bond, each for one-hundred percent (100%) of the contract price in the form that complies with the Project Documents and is satisfactory to the City Attorney. 6. Non-Assignability. Neither this Agreement nor any rights, title, interest, duties, or obligations under this Agreement may be assigned, transferred, conveyed, or otherwise disposed of by Contractor without the prior written consent of City. 7. Licenses. Contractor represents and warrants to City that it holds the Contractor’s license or licenses set forth in the Project Documents, is registered with the Department of Industrial Relations pursuant to Labor Code Section 1725.5 as of March 1, 2015, and holds such other licenses, permits, qualifications, insurance and approvals of whatsoever nature which are legally required of Contractor. Contractor represents and warrants to City that Contractor shall, at its sole cost and expense, keep in effect or obtain at all times during the term of this Agreement, any licenses, permits, insurance and approvals which are legally required of Contractor to practice its profession. Contractor shall maintain a City of Lake Elsinore business license. 8. Indemnity. Contractor shall indemnify, defend, and hold harmless the City and its officials, officers, employees, agents, and volunteers from and against any and all losses, liability, claims, suits, actions, damages, and causes of action arising out of any personal injury, bodily injury, loss of life, or damage to property, or any violation of any federal, state, or mun icipal law or ordinance, to the extent caused, in whole or in part, by the willful misconduct or negligent acts or omissions of Contractor or its employees, subcontractors, or agents, by acts for which they could be held strictly liable, or by the quality or character of their work. The foregoing obligation of Contractor shall not apply when (1) the injury, loss of life, damage to property, or violation of law arises from the sole negligence or willful misconduct of the City or its officers, employees, age nts, or volunteers and (2) the actions of Contractor or its employees, subcontractor, or agents have contributed in no part to the injury, loss of life, damage to property, or violation of law. It is understood that the duty of Contractor to indemnify and hold harmless includes the duty to defend as set forth in Section 2778 of the California Civil Code. Acceptance by City of insurance certificates and endorsements required under this Agreement does not relieve Contractor from liability under this indemnification and hold harmless clause. This indemnification and hold harmless clause shall apply to any damages or claims for damages whether or not such insurance policies shall have been determined to apply. By execution of this Agreement, Contractor acknowledges and agrees to the provisions of this Section and that it is a material element of consideration. 9. Insurance Requirements. a. Insurance. Contractor, at Contractor’s own cost and expense, shall procure and maintain, for the duration of the Agreement, unless modified by the City’s Risk Manager, the following insurance policies. i. Workers’ Compensation Coverage. Contractor shall maintain Workers’ Compensation Insurance and Employer’s Liability Insurance for his/her employees in accordance with the laws of the State of California. In addition, Contractor shall require each subcontractor to similarly maintain Workers’ Compensation Insurance and Employer’s Liability Insurance in accordance with the laws of the State of California for all of the subcontractor’s employees. Any notice of cancellation or non-renewal of all Workers’ Compensation policies must be received by the City at least thirty (30) days prior to such change. The insurer shall agree to waive all rights of subrogation against City, its officers, agents, employees, and volunteers for losses arising from work performed by Contractor for City. In the event that Contractor is exempt from Worker’s Compensation Insurance and Employer’s Liability Insurance for his/her employees in accordance with the laws of the State of California, Contractor shall submit to the City a Certificate of Exemption from Workers Compensation Insurance in a form approved by the City Attorney. ii. General Liability Coverage. Contractor shall maintain commercial general liability insurance in an amount not less than one million dollars ($1,000,000) per occurrence for bodily injury, personal injury and property damage. If a commercial general liability insurance form or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to the work to be performed under this Agreement or the general aggregate limit shall be at least twice the required occurrence limit. Required commercial general liability coverage shall be at least as broad as Insurance Services Office Commercial General Liability occurrence form CG 0001 (ed. 11/88) or Insurance Services Office form number GL 0002 (ed. 1/73) covering comprehensive General Liability and Insurance Services Office form number GL 0404 covering Broad Form Comprehensive General Liability. No endorsement may be attached limiting the coverage. iii. Automobile Liability Coverage. Contractor shall maintain automobile liability insurance covering bodily injury and property damage for all activities of the Contractor arising out of or in connection with the work to be performed under this Agreement, including coverage for owned, hired and non-owned vehicles, in an amount of not less than one million dollars ($1,000,000) combined single limit for each occurrence. Automobile liability coverage must be at least as broad as Insurance Services Office Automobile Liability form CA 0001 (ed. 12/90) Code 1 (“any auto”). No endorsement may be attached limiting the coverage. iv. Professional Liability Coverage [if applicable]. Contractor shall maintain professional errors and omissions liability insurance appropriate for Contractor’s profession for protection against claims alleging negligent acts, errors or omissions which may arise from Contractor’s services under this Agreement, whether such services are provided by the Contractor or by its employees, subcontractors, or sub consultants. The amount of this insurance shall not be less than one million dollars ($1,000,000) on a claims- made annual aggregate basis, or a combined single limit per occurrence basis. b. Endorsements. Each general liability and automobile liability insurance policy shall be with insurers possessing a Best’s rating of no less than A: VII and shall be endorsed with the following specific language: i. The City, its elected or appointed officers, officials, employees, agents and volunteers are to be covered as additional insured with respect to liability arising out of work performed by or on behalf of the Contractor, including materials, parts or equipment furnished in connection with such work or operations. ii. This policy shall be considered primary insurance as respects the City, its elected or appointed officers, officials, employees, agents and volunteers. Any insurance maintained by the City, including any self-insured retention the City may have, shall be considered excess insurance only and shall not contribute with it. iii. This insurance shall act for each insured and additional insured as though a separate policy had been written for each, except with respect to the limits of liability of the insuring company. iv. The insurer waives all rights of subrogation against the City, its elected or appointed officers, officials, employees or agents. v. Any failure to comply with reporting provisions of the policies shall not affect coverage provided to the City, its elected or appointed officers, officials, employees, agents or volunteers. vi. The insurance provided by this Policy shall not be suspended, voided, canceled, or reduced in coverage or in limits except after thirty (30) days written notice has been received by the City. c. Deductibles and Self-Insured Retentions. Any deductibles or self-insured retentions must be declared to and approved by the City. At the City’s option, Contractor shall demonstrate financial capability for payment of such deductibles or self-insured retentions. d. Certificates of Insurance. Contractor shall provide certificates of insurance with original endorsements to City as evidence of the insurance coverage required herein. Certificates of such insurance shall be filed with the City on or before commencement of performance of this Agreement. Current certification of insurance shall be kept on file with the City at all times during the term of this Agreement. 10. Notices. Any notice required to be given under this Agreement shall be in writing and either served personally or sent prepaid, first class mail. Any such notice shall be addressed to the other party at the address set forth below. Notice shall be deemed communicated within 48 hours from the time of mailing if mailed as provided in this section. If to City: City of Lake Elsinore Attn: City Manger 130 South Main Street Lake Elsinore, CA 92530 With a copy to: City of Lake Elsinore Attn: City Clerk 130 South Main Street Lake Elsinore, CA 92530 If to Contractor: Musco Sports Lighting LLC Attn: Karen Anderson 100 1st Avenue W P.O. Box 808 Oskaloosa, IA 52577 11. Entire Agreement. This Agreement constitutes the complete and exclusive statement of Agreement between the City and Contractor. All prior written and oral communications, including correspondence, drafts, memoranda, and representations, are superseded in total by this Agreement. 12. Amendments. This Agreement may be modified or amended only by a written document executed by both Contractor and City and approved as to form by the City Attorney 13. Assignment and Subcontracting. Contractor shall be fully responsible to City for all acts or omissions of any subcontractors. Assignments of any or all rights, duties , or obligations of the Contractor under this Agreement will be permitted only with the express consent of the City. Nothing in this Agreement shall create any contractual relationship between City and any subcontractor, nor shall it create any obligation on the part of the City to pay or to see to the payment of any monies due to any such subcontractor other than as otherwise is required by law. 14. Waiver. Waiver of a breach or default under this Agreement shall not constitute a continuing waiver of a subsequent breach of the same or any other provision under this Agreement. 15. Severability. If any term or portion of this Agreement is held to be invalid, illegal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions of this Agreement shall continue in full force and effect. 16. Controlling Law Venue. This Agreement and all matters relating to it shall be governed by the laws of the State of California, and any action brought relating to this Agreement shall be held exclusively in a state court in the County of Riverside. 17. Litigation Expenses and Attorneys’ Fees. If either party to this Agreement commences any legal action against the other party arising out of this Agreement, the prevailing party shall be entitled to recover its reasonable litigation expenses, including court costs, expert witness fees, discovery expenses, and attorneys’ fees. 18. Mediation. The parties agree to make a good faith attempt to resolve any disputes arising out of this Agreement through mediation prior to commencing litigation. The parties shall mutually agree upon the mediator and share the costs of mediation equally. If the parties are unable to agree upon a mediator, the dispute shall be submitted to JAMS or its successor in interest. JAMS shall provide the parties with the names of five qualified mediators. Each party shall have the option to strike two of the five mediators selected by JAMS, and thereafter, the mediator remaining shall hear the dispute. If the dispute remains unresolved after mediation, either party may commence litigation. 19. Authority to Enter Agreement and Administration. Contractor has all requisite power and authority to conduct its business and to execute, deliver, and perform the Agreement. Each party warrants that the individuals who have signed this Agreement have the legal power, right, and authority to make this Agreement and to bind each respective party. The Executive Director is authorized to enter into an amendment or otherwise take action on behalf of the City to make the following modifications to the Agreement: (a) a name change; (b) grant extensions of time; (c) non- monetary changes in the scope of services; and/or (d) suspend or terminate the Agreement. The Director of Public Works shall act as the Project administrator on behalf of the City. 20. Prohibited Interests. Contractor maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Contractor, to solicit or secure this Agreement. Further, Contractor warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working solely for Contractor, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Agreement. For breach or violation of this warranty, City shall have the right to rescind this Agreement without liability. For the term of this Agreement, no member, officer, or employee of City, during the term of his or her service with City, shall have any direct interest in this Agreement, or obtain any present or anticipated material benefit arising therefrom. 21. Equal Opportunity Employment. Contractor represents that it is an equal opportunity employer, and it shall not discriminate against any subcontractor, employee, or applicant for employment because of race, religion, color, national origin, handicap, ancestry, sex or age. Such non-discrimination shall include, but not be limited to, all activities related to initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination. 22. Prevailing Wages. a. Contractor and all subcontractors shall adhere to the general prevailing rate of per diem wages as determined and as published by the State Director of the Department of Industrial Relations pursuant to Labor Code Sections 1770, 1773, and 1773.2. Copies of these rates and the latest revisions thereto are on file in the office of the City Clerk of the City of Lake Elsinore and are available for review upon request. b. Contractor’s attention is directed to the provisions of Labor Code Sections 1774, 1775, 1776, 1777.5 and 1777.6. Contractor shall comply with the provisions of these Sections. The statutory provisions for penalties for failure to comply with the State’s wage and the hour’s laws will be enforced. c. Labor Code Sections 1774 and 1775 require the Contractor and all subcontractors to pay not less than the prevailing wage rates to all workmen employed in the execution of the contract and specify forfeitures and penalties for failure to do so. The minimum wages to be paid are those determined by the State Director of the Department of Industrial Relations. Labor Code Section 1776 requires the Contractor and all subcontractors to keep accurate payroll records, specifies the contents thereof, their inspection and duplication procedures, and certain notices required of the Contractor pertaining to their location. The statutory penalties for failure to pay prevailing wages will be enforced. If the Project has been awarded to Contractor on or after April 1, 2015, Contractor and its subcontractors must furnish electronic certified payroll records to the Labor Commissioner. Beginning January 1, 2016, Contractor and its subcontractors must provide electronic certified payroll records to the Labor Commissioner without regard to when the Project was awarded to the Contractor. d. Labor Code Section 1777.5 requires a Contractor or subcontractor employing tradesmen in any apprentice able occupation to apply to the Joint Apprenticeship Committee nearest the site of the public works project, which administers the apprenticeship program in that trade for a certificate of approval. The certificate will also fix the ratio of apprentices to journeymen to be used in the performance of the Agreement. The Contractor is required to make contributions to funds established for the administration of apprenticeship programs if the Contractor employs registered apprentices or journeymen in any apprentice able trade and if other contractors on the public works site are making such contributions. Information relative to apprenticeship standards, contributions, wage schedules and other requirements may be obtained from the State Director of Industrial Relations or from the Division of Apprenticeship Standards. Labor Code Section 1777.6 provides that it shall be unlawful to refuse to accept otherwise qualified employees as registered apprentices solely on the grounds of race, religious creed, color, national origin, ancestry, sex, or age. e. Eight hours’ labor constitutes a legal day’s work, as set forth in Labor Code Section 1810. 23. Execution. This Agreement may be executed in several counterparts, each of which shall constitute one and the same instrument and shall become binding upon the parties when at least one copy hereof shall have been signed by both parties hereto. In approving this Agreement, it shall not be necessary to produce or account for more than one such counterpart. [Signatures on next page] IN WITNESS WHEREOF, the parties have caused this Agreement to be executed on the date first written above. “CITY” City of Lake Elsinore, a municipal corporation Grant Yates, City Manager ATTEST: City Clerk APPROVED AS TO FORM: City Attorney “CONTRACTOR” Musco Sports Lighting LLC . ©2016, 2018 Musco Sports Lighting, LLC - 1 - M-2038-enUS-6 Quote Quote Canyon Hills Community Park LED Retrofit March 18, 2020 Sourcewell Master Project: 199030, Contract Number: 071619-MSL, Expiration: 08/27/2023 Category: Sports lighting with related supplies and services All purchase orders should note the following: Sourcewell purchase – contract number: 071619-MSL Quotation Price – Materials and Installation Musco Equipment and Installation as described below: Musco Materials and Installation: $445,000. Estimated Sales Tax on Materials, Based on 7.75%: $ 28,850. Project Total: $473,850.00 Pricing furnished is effective for 90 days unless otherwise noted and is considered confidential. SportsCluster System with Total Light Control – TLC for LED™ Technology Retrofit System Description • Factory wired and tested remote electrical component enclosures • Pole length, factory assembled wire harnesses • (12) Factory wired poletop luminaire assemblies • (92) Factory aimed and assembled luminaries, including BallTracker™ luminaires • UL Listed as a complete system Warranty Services • 10 Year Warranty program that covers materials and onsite labor, eliminating 100% of your maintenance costs for 10 years. • Equipment on cell poles will have a 10-year materials warranty, with lamps and onsite labor included for 2 years. Installation Services Provided See attached scope of work. Payment Terms Payment terms to be coordinated with Musco’s Credit Department. Please email a copy of the Purchase Order to Musco Sports Lighting, LLC: Karin Anderson Field Sales Representative Musco Sports Lighting, LLC Phone: 760-798-3162 E-mail: Karin.anderson@musco.com Ref: 197725 All purchase orders should note the following: Sourcewell purchase – contract number: 071619-MSL Delivery Timing 6 - 8 weeks for delivery of materials to the job site from the time of order, submittal approval, and confirmation of order details including voltage, phase, and pole locations. ©2016, 2018 Musco Sports Lighting, LLC - 2 - M-2038-enUS-6 Quote Quote Due to the built-in custom light control per luminaire, pole locations need to be confirmed prior to production. Changes to pole locations after the product is sent to production could result in additional charges. Notes Quote is based on: • Shipment of entire project together to one location. Freight Is Included. • Voltage and phasing to be confirmed. • Structural code and wind speed = 2016 CBC, 110 mi/h, Risk Category II. • Owner is responsible for getting electrical power to the site, coordination with the utility, and any power company fees. • Confirmation of pole locations prior to production. • Warranty is contingent upon site review and compatibility with Musco’s lighting system. • Re-use of existing Musco Control-Link Controller on-site Thank you for considering Musco for your lighting needs. Please contact me with any questions or if you need additional details. Karin Anderson Field Sales Representative Musco Sports Lighting, LLC Phone: 760-798-3162 E-mail: Karin.anderson@musco.com ©2016, 2018 Musco Sports Lighting, LLC - 3 - M-2038-enUS-6 Quote Quote TLC for LED Retrofit Scope of Work Canyon Hills Community Park Lake Elsinore, CA Owner Responsibilities: 1) Total access to the site and pole locations for construction. Must be able to move from location to location on standard rubber tires. 2) Provide reference points for sighting in lighting cross-arms. This would be home plate for the Baseball fields and either corners or the center of the field for Soccer. 3) Removal, replacement, and repair of all fencing necessary for construction. 4) Repair and replacement of any field turf, asphalt, curbs, and concrete damage. Potential damages resulting from necessary construction to be discussed prior to work commencing on site. 5) Locate and mark existing irrigation systems necessary for construction. 6) All necessary permitting costs including any environmental issues. 7) Provide existing electrical design, as built drawings and site plan as necessary. 8) Coordinate access to the cell tower pole and shut down during scheduled work on cell tower pole. Musco Responsibilities: 1) Provide Project Management and assistance as needed. 2) Provide layout of pole locations, aiming diagram, and associated designs. 3) Provide pole inspection for Musco warranty as necessary and survey of existing poles for height, size, and location. 4) Provide required Musco TLC for LED™ equipment 5) Provide light test under owner supplied lighting system as required. Musco Responsibilities Via Subcontractor Responsibilities: 1) Provide equipment and materials to off load equipment at jobsite per scheduled delivery. 2) Keep all heavy equipment off of playing fields and surfaces when possible. Subcontractor to use ground protection when necessary and due care in minimizing damages to existing site. 3) Remove and dispose of the existing lighting fixtures, wiring harnesses and electrical enclosures on (16) existing poles. This will include the recycling of lamps, aluminum reflectors, ballast and steel as necessary. 4) Leave the existing grounding conductors and power feed in place for reattachment to the new Musco TLC for LED™ equipment. 5) Provide adequate trash container for cardboard waste and packing debris. 6) Provide storage containers for material as necessary. 7) Obtain required permits if necessary, owner to pay cost of permits. Subcontractor to advise Musco of costs to subcontractor, if any, before proceeding with permitting. 8) Locate existing underground utilities and irrigation system so as to avoid damage from construction equipment. Repair any such items damaged during construction. 9) Ground the new product on poles per NFPA 780 and NEC code. This will include grounding of the electrical enclosures and remote light fixture cross arms. Existing lightning and surge protection to be verified and repaired as necessary to comply with Musco warranty. 10) Install Musco electrical enclosures, wiring harnesses and sport lighting fixtures on existing poles and terminate power feed. Power feed may need reworked to adapt to the new Musco lighting equipment. This will include new pole top fitter assembly with cross-arms at each pole. Cross-arms to be attached via brackets or special build fitter assemblies that will bolt directly on to existing pole flange near top of pole. Subcontract to work with Musco prior to equipment production to determine best method of attachment to existing poles for cross-arms, ball tracker brackets(Baseball and Large Soccer Only) and enclosures. 11) Provide and install covers for any access holes on poles not used after installation is complete. 12) Provide startup and aiming as required to provide complete and operating sports lighting system. 13) Provide payment of prevailing wages and certified payroll as required.