City of Lake Elsinore 130 South Main Street
Lake Elsinore, CA 92530
www.lake-elsinore.org
File Number: ID# 19-508
Agenda Date: 3/10/2020 Status: Approval FinalVersion: 1
File Type: Council Consent
Calendar
In Control: City Council / Successor Agency
Agenda Number: 8)
Page 1 City of Lake Elsinore Printed on 3/5/2020
REPORT TO CITY COUNCIL
To: Honorable Mayor and Members of the City Council
From: Grant Yates, City Manager
Prepared by: Jason Simpson, Assistant City Manager
Date: March 10, 2020
Subject: Change Order No. 3 - PlainJoe Studios for Wayfinding Signage
Recommendation
Approve and authorize the City Manager to execute Change Order No. 3 for $79,356.34 for the
Agreement to PlainJoe Studios' for Wayfinding Signage.
Background
PlainJoe Studios' assisted with the development of a branding and marketing concept for the
RV Resort Rehabilitation Project. Additional work by PlainJoe Studios’ included farther-
reaching content-rich, emotionally compelling, and experiential opportunities to tell the Story of
the RV Resort. Key community leaders and staff worked together to develop the needed
branding for the RV Resort Project. The result conceptualizes and constructed important
information about the RV Resort and feeds a dialogue between campers and the campground
where they stay. Much of this leads to a static and digital wayfinding system, signage, unique
graphics, exhibition substance, installation of both art, and play elements, all with a common
branding of the entire RV Resort.
Discussion
The purpose of this change order is to further the approved signage design and build for
branding and wayfinding at Launch Pointe. Working with CalTrans on the Launch Pointe
entrance (Riverside & Lincoln), it has been determined additional signage is needed to improve
traffic movement into Launch Pointe from Lincoln. Also, this change order will provide for
additional Launch Pointe marketing opportunities on the main entrance arch. Specifically, on
both the right and left side of the arch, two large panels will display the Bobber Restaurant and
Lake Boat Launch advertisement banners. Finally, in this change order, additional signage and
pedestrian portal elements will be constructed to improve the beach access and will be installed
to complement the currently under construction marina deck with ADA and staircase access to
the beach from the parking lot.
PlainJoe Studios’ Change Order 3
March 10, 2020
Page 2
Following the approval of this agenda, item coordination will begin on the fabrication and
installation of these elements. The beach access portal will require minimal site development to
support the construction of the arch. All other elements will essentially be mounted in
predetermined locations to facilitate pedestrian and vehicular movement.
Fiscal Impact
The change order is part of the FY19/20 Capital Improvement Plan (CIP) budget funding.
Exhibits
A – Change Order #3
B – Cost Proposal
3
DATE:
QUANTITY UNIT
Lump Sum 1.00
Lump Sum 1.00 $26,645.34
Lump Sum 1.00 $23,806.90
TOTAL
SUM OF
3
Review by: Initials Date Date
PRIOR TO THIS CHANGE ORDER
CONTRACTOR IS AUTHORIZED TO MAKE THE FOLLOWING CHANGES:
Assistant City Manager
$23,806.90
UNIT PRICE EXTENSIONITEM
Item #1 Exterior Wayfinding
ITEM
QUANTITIES DECREASED
$26,645.34
$28,904.10$28,904.10
Item #2 Install
Item #3 Design and PM
UNIT PRICE
CITY PROJECT #
September 26, 2017DATE AWARDED:
PROJECT TITLE: Launch Pointe Signage, Beach Access PlainJoe Studios
Advertizement Posters
Z40007
Authorized by: Jason Simpson TOTAL AMOUNT OF CONTRACT
$618,172.26
QUANTITIES INCREASED
CITY OF LAKE ELSINORE
130 S. MAIN STREET
LAKE ELSINORE, CA 92530
(951) 674-3124
March 10, 2020
PROJECT CHANGE ORDER CHANGE ORDER #
THIS CHANGE ORDER IS APPLICABLE TO:
CONTRACT AWARDED TO:
City Manager:
$79,356.34
Approved by:
Contractor
Change Order No.
Assistant City Manager
EXTENSION
THE AMOUNT OF THE CONTRACT WILL BE (INCREASED) BY THE
$79,356.34
None
QUANTITY
Graphic #Description Quantity Total
Exterior Wayfinding
LPP01 Main Entry Banners Graphic - Boat Launch 1 $864.00
LPP02 Main Entry Banners Graphic - Bobber 1 $864.00
LPP Main Entry Banners Graphic Frames 2 $1,265.66
SM01a.01 La Laguna Monument Sign 1 - White Arrow 1 $56.43
SM01a.02 La Laguna Monument Sign 1 - Blue Circle 1 $156.41
SM01b La Laguna Monument Sign 1 - Wood Panels 1
SM01c La Laguna Monument Sign 1 - Cut Lettering 1
SM02a.01 La Laguna Monument Sign 2 - White Arrow 1 $56.43
SM02a.02 La Laguna Monument Sign 2 - Blue Circle 1 $156.41
SM02b La Laguna Monument Sign 2 - Wood Panels 1
SM02c La Laguna Monument Sign 2 - Cut Lettering 1
WX01a Beach Access Single Post Sign 1 $59.06
Wx01b Beach Access Single Post Sign - Directional 1 $20.39
WX02a.01 Beach Access Portals - I Beam 2
WX02a.02 Beach Access Portals - Post 1
WX02a.03 Beach Access Portals - Post 1
WX02.04 Beach Access Portals - Blue Graphic Side A 1 $157.50
WX02a.05 Beach Access Portals - Blue Stripes Side A 1 $34.33
WX02a.06 Beach Access Portals - Gray Graphic Side A 1 $48.44
WX02b.04 Beach Access Portals - Blue Graphic Side B 1 $157.50
Plain Joe Studios
Launche Pointe: Phase 3
$1,952.84
$1,952.84
$21,019.10
WX02b.05 Beach Access Portals - Blue Stripes Side B 1 $34.33
WX02b.06 Beach Access Portals - Gray Graphic Side B 1 $48.44
$0.00
Install
Install Labor -$26,645.34
-$0.00
-
Design & Project Management
Design & PM -$23,806.90
-
Total $79,356.34
* Does not include Sales Tax