HomeMy WebLinkAboutPC Reso No 2017-45 (C&C Housing, MSHCP)RESOLUTION NO. 2017-45
A RESOLUTION OF THE PLANNING COMMISSION OF THE CITY OF LAKE
ELSINORE, CALIFORNIA, RECOMMENDING THAT THE CITY COUNCIL OF THE
CITY OF LAKE ELSINORE, CALIFORNIA, AOOPT FINDINGS THAT PLANNING
APPLICATION 2016-103 IS CONSISTENT WITH THE WESTERN RIVERSIDE COUNTY
MULTTPLE SPECTES HABTTAT CONSERVATTON pLAN (MSHCp)
Whereas, C&C Housing submitted an application for a residential design review, proposing to
build an affordable multifamily development with 81 apartments units and associated features and
facilities including resident/visitor parking, a leasing/management office, a community center,
onsite laundry facility, active and passive open spaces, and a maintenance garage. The Project
is generally located on vacant land west of Mission Trail, approximately 500 feet south of Hidden
Trail and Elberta Road and is more specifically referred to as Assessor Parcel Number (APN.
365-030-001); and,
Whereas, Section 6.0 of the Western Riverside County Multiple Species Habitat Conservation
Plan (MSHCP) requires that all projects which are proposed on land covered by an MSHCP
criteria cell and which require discretionary approval by the legislative body undergo the Lake
Elsrnore Acquisition Process (LEAP) and a Joint Project Review (JPR) between the City and the
Regional Conservation Authority (RCA) prior to public review of the project applications; and,
Whereas, Sectron 6.0 further requires that discretionary development projects be analyzed
pursuant to the MSHCP "Plan Wide Requirements" even if not within an MSHCP criteria cell; and,
Whereas, the Project is discretionary in nature and requires review and approval by the Planning
Commission (Commission) and City Council (Council); and,
Whereas, a portion of the Project is within MSHCP Criteria Cell 4743 and the entire Project is
within the Elsinore Plan Area of the MSHCP, and therefore, the Project was reviewed pursuant to
the MSHCP "Plan Wide Requirements"; and,
Whereas, Section 6.0 of the MSHCP requires that the City adopt consistency findings prior to
approving any discretionary project entitlements for development of property that is subject to the
MSHCP; and,
Whereas, on June 6, 2017, at a duly noticed Public Hearing the Commission has considered
evidence presented by the Community Development Department and other interested parties with
respect to this item.
NOW, THEREFORE, THE PLANNING COMMISSION OF THE CITY OF LAKE ELSINORE,
CALIFORNIA, DOES HEREBY RESOLVE, DETERMINE AND ORDER AS FOLLOWS:
Section 1. The Commission has reviewed and analyzed the proposed applications and their
consistency with the MSHCP prior to making a decision to recommend that the Council adopt
Findings of Consistency with the MSHCP for the Project.
Section 2. That in accordance with the Lake Elsinore Municipal Code (LEMC), and the MSHCP,
Findings for adoption have been made as follows.
PC Reso No. 2017-45
Page 2 of 5
1. The proposed Project is a project under the City's MSHCP Resolution, and the City
must make an MSHCP Consistency Finding before approval.
Pursuant to the City's MSHCP lmplementing Resolution, prior to approving any
discretionary entitlement, the City is required to review the Project to ensure
consistency with the MSHCP criteria and other "Plan Wide Requirements." The
Project, as proposed, was found to be consistent with the MSHCP criteria. ln
addition, the Project was reviewed and found conslstenf with the following "Plan
Wide Requirements". Protection of Specles Associated with Riparian/Riverine Areas
and Vernal Pool Guidelines (MSHCP $ 6.2), l.Protection of Narrow Endemic
Specles MSHCP S 6.3), l.Urban/Wildlands lnteiace Guidelines (MSHCP S 6.4),
l.Vegetation Mapping (MSHCP $ 6.1), 3.Additional Survey Needs and Procedures
(MSHCP S 6.2), 3. Fuels Management (MSHCP S 6.4), and payment of the MSHCP
Local Development Mitigation Fee (MSHCP Ordinance $ 4.0).
2. The proposed Project is subject to the City's LEAP and the County's JPR.
The Project site, borrow site, and temporary haul road is located within Subunit 3
(Elsinore) of Elsinore Area Plan of the Western Riverside County MSHCP. The
Project site, borrow site, and temporary haul road is located within MSHCP Criteria
Cells, proposed extension of the existing Core 3, and in the vicinity of proposed
Linkage 8. The Project site, borrow site, and temporary haul road are located within
the MSHCP Project site, borrow site, and temporary haul road for the western
burrowing owl (Athene cunicularia hypugaea) pursuant lo Secllon 6.3.2 of the
MSHCP. The borrow site and temporary haul road are also located within the
MSHCP Project site, borrow site, and temporary haul road for Narrow Endemic plant
species pursuant to Sectlon 6.1.3 of the MSHCP and Criteria Area plant species
pursuant to Secflon 6.3.2 of the MSHCP. The Project would be required to comply
with the MSHCP through obtaining a consistency determination and any other
additional approvals required by the MSHCP, including processes such asthe City's
implementation of the HANS (Habitat Evaluation and Acquisition Negotiation
Strategy) process, the Lake Elsinore Acquisition Process (LEAP), and/or a
Determination of Biologically Equivalent or Superior Preservation (DBESP), if
appropriate. lt is anticipated that a DBESP will be required for this Project, subject
to MSHCP approval, and the Project will be required to demonstrate consistency
with the MSHCP through the preseNation of equivalent or superior resources in
comparison to project impacts.
3. The proposed Project is consistent with the Riparian/Riverine Areas and Vernal
Pools Guidelines.
Section 6.21 .of the MSHCP focuses on protection of riparian/riverine areas and
vernal pool habitat types based upon their value in the conseNation of a number of
MSHCP covered species. All potential impacts to riparian/riverine areas will be
mitigated as identified in the Determination of Biological Equivalent or Superior
PreseNation DBESP) to be completed and approved prior to the issuance of a
building permit. There are no vernal pools or fairy shrimp habitat on the Project Site,
and therefore, the Project is conslstenl with Section 6.21.of the MSHCP.
I
PC Reso No. 2017-45
Page 3 of 5
4. The proposed Project is consistent with the Protection of Narrow Endemic Plant
Species (NEPS) Guidelines.
There is potential for direct and indirect impacts to spec/a/ status plants within the
Survey Area. Ihe specles with the highest likelihood of occurrence within the Survey
Area are little mousetail and smooth tarplant; focused surveys pursuant to the
MSHCP Narrow Endemic and Criteria Area Species Survey requirements will be
conducted in spring 2017. The impacts to sens/rve plants are not currently known,
however it is expected that compliance with the MSHCP (including required
mitigation, if applicable) will reduce potential direct impacts to a below significance.
Additionally, potential indirect impacts to special status species within.
5. The proposed Project is consistent with the Additional Survey Needs and
Procedures.
The Project is located within the Criteria Area Specles Survey Area (CASSA) tor
several criteria area plants and the Burrowing Owl survey area as identified in
Section 6.23. Additional Survey Needs and Procedures of the MSHCP. Surveys
were conducted on the entire Project Site, and the results indicated that two plant
specles, the smooth tarplant and little mousetail are present on the Project Site. The
smooth tarplant and little mousetail will be relocated to on and off-site mitigation
areas which will provide adequate long-term protection of these specles. No
Burrowing Owls occupied the Project Srte. As such, the Prqect is consistent with
Section 6.23.of the MSHCP.
6. The proposed Project is consistent with the Urban/Wildlands lnterface Guidelines.
Section 6.41 .of the MSHCP sets forth guidelines which are intended fo address
indirect effects assoclafed with locating development in proximity to the MSHCP
Conservation Area, where applicable. Future Development in proximity to the
MSHCP Conservation Area may result in Edge Effects that will adversely affect
biological resources within the MSHCP Conservation Area. To minimize such Edge
Effects, guidelines sha// be implemented in conjunction with review of individual
public and private Development projects in proximity to the MSHCP ConseNation
Area. Through implementation of mitigation measures the Project will minimize the
identified potential indirect impacts with potential future open space. As such, the
Project is conslstent with Section 6.41 .of the MSHCP.
7. The proposed Project is consistent with the Vegetation Mapping requirements.
Vegetation mapping was conducted as paft of the biological surveys conducted on
the entire Project Site and ls conslslent with the MSHCP Section 6.13.Vegetation
Mapping requirements.
8. The proposed Project is consistent with the Fuels Management Guidelines.
The Fuels Management Guidelines presented in Section 6.4 of the MSHCP are
intended to address brush management activities around new development within
or adjacent to the MSHCP Conservation Area and shall be implemented as part of
PC Reso No. 2017-45
Page 4 of 5
the Project. As such, the Proiect is conslslent with the Fuels Management
Guidelines.
9. The proposed Project is conditioned to pay the City's MSHCP Local Development
Mitigation Fee.
As a Condition of Approval, the Proiect will be required to pay the City's MSHCP
Local Development Mitigation Fee at the time of issuance of building permits.
10. The Project is consistent with the reserve assembly requirements of the MSHCP.
The Project Site is located in the Back Basin area and is subiect to the 770 Acre
Back Basin Agreement with the Wildlife Agencies related to reserve assembly. Since
the Project has conserved an area along the outlet channel, which contributes to the
extension of existing Core 3 and shall meet the reserve assembly requirements of
the Back Basin Agreement, the Project does not conflict with the reserve assembly
requirements of the MSHCP.
11 . The proposed Project overall is consistent with the MSHCP
The Project ls consistenf with all applicable provisions of the MSHCP No fufther
actions related to the MSHCP are required.
section 3. Based upon the evidence presented and the above findings, the Planning
Commission hereby recommends that the City Council of the City of Lake Elsinore adopt findings
that the Project rs consistent with the MSHCP.
Section 4. This Resolution shall take effect from and after the date of its passage and adoption.
Passed and Adopted on this 6th day of June. 2017
z/,/ -''- -.')'Za /-_-- -.- l------'
Adam Armit. Chairman
PC Reso No. 2017-45
Page 5 of 5
STATE OF CALIFORNIA
COUNTY OF RIVERSIDE
CITY OF LAKE ELSINORE
l, Justin Kirk, Principal Planner of the City of Lake Elsinore, California, hereby certify that
Resolution No. 2017-45 as adopted by the Planning Commission of the City of Lake Elsinore at
a Regular meeting held on June 6,2017, and that the same was adopted by the following vote:
AYES. Commissioner's Ross, Carroll and Klaarenbeek; Vice-Chair Gray and Chairman Armit
NOES. None
ABSTAIN: None
ABSENT: None
)"