HomeMy WebLinkAbout0014_2_SB 821 Chaney Street CCO - Exhibit APUBLIC WORKS CONSTRUCTION CONTRACT CONTRACT CHANGE ORDER Date 10/22/2019 C.C.O No. 1 951-674-3124 130 S. MAIN STREET LAKE ELSINORE, CA 92530 WWW.LAKE-ELSINORE.ORG PROJECT NAME SB 821 CHANEY STREET SIDEWALKPROJECT CONTRACTOR: I.E. GENERAL ENGINEERING In conformance with and as part of the existing Agreementfor this projectthe City of Lake Elsinore authorizes and directs changes to the Agreement as described below. 1)EXTRA WORK ORDER (EWO) (Unknown or Unforeseen Worknot covered by Contract) a)Extra Work Item A: Additional project square footage–Grind/overlay Lump Sum Additional Project LimitWork = $20,443.60 2)CHANGED WORKORDER (CWO)(Significant increasesin quantity of Unit-Price items;greater than 25%): a) Changed Work Item A: i)Time for completion will be increased/decreased by (+-) Zero (0)Working Days 3)CLOSING SUMMARYORDER (CSO) (Final adjustment of original estimated contract quantities based on final measured quantities): a)Closing Summary Order: i)Additionof Work: Based on the change of additional scope of workconstructedthe final amount owed to the contractor isgreater than the original agreement amount. ii)Payment for this work is paid as follows: The various items that went over quantities were all bid items in the original contract and will be paid at the unit prices bid,with the total being $ Total = $20,443.60 AGREEMENT AMOUNT:Compensation as set forth in the Agreement and as amended by this and prior Contract Change Order(s) is: $359,191.20 Original Contract Amount: $307,952.60 Amount All Previous CCOs(+-): $30,795.00 Amount This CCO(+-): $20,443.60 TotalContract Amount: $359,191.20 PUBLIC WORKS CONSTRUCTION CONTRACT CONTRACT CHANGE ORDER (cont’d) C.C.O No. 1 2of 2 CITY’S ACCEPTANCE:The above described work is hereby approved and directed to be completed in accordance with the Contract Documents. City of Lake Elsinore Rec.:______________________________ City Engineer Date App.:_____________________________ City Manager Date CONTRACTOR’S ACCEPTANCE:Contractor agrees to perform the above work as directed,in accordance with the Contract Documents,and acceptpayment describedabove as full compensation for work described subject to additions and reductions of the quantities of various items. Contractor: I.E. General Engineering_____________ By _________________________________________ Title: _______________________________________ Date: _______________________________________