HomeMy WebLinkAbout0014_2_SB 821 Chaney Street CCO - Exhibit APUBLIC WORKS CONSTRUCTION CONTRACT
CONTRACT CHANGE ORDER
Date 10/22/2019 C.C.O No. 1
951-674-3124
130 S. MAIN STREET
LAKE ELSINORE, CA 92530
WWW.LAKE-ELSINORE.ORG
PROJECT NAME
SB 821 CHANEY STREET SIDEWALKPROJECT
CONTRACTOR:
I.E. GENERAL ENGINEERING
In conformance with and as part of the existing Agreementfor this projectthe City of Lake Elsinore
authorizes and directs changes to the Agreement as described below.
1)EXTRA WORK ORDER (EWO) (Unknown or Unforeseen Worknot covered by Contract)
a)Extra Work Item A: Additional project square footage–Grind/overlay
Lump Sum Additional Project LimitWork = $20,443.60
2)CHANGED WORKORDER (CWO)(Significant increasesin quantity of Unit-Price items;greater than 25%):
a) Changed Work Item A:
i)Time for completion will be increased/decreased by (+-) Zero (0)Working Days
3)CLOSING SUMMARYORDER (CSO) (Final adjustment of original estimated contract quantities based on final
measured quantities):
a)Closing Summary Order:
i)Additionof Work: Based on the change of additional scope of workconstructedthe final
amount owed to the contractor isgreater than the original agreement amount.
ii)Payment for this work is paid as follows: The various items that went over quantities were all
bid items in the original contract and will be paid at the unit prices bid,with the total being $
Total = $20,443.60
AGREEMENT AMOUNT:Compensation as set
forth in the Agreement and as amended by
this and prior Contract Change Order(s) is:
$359,191.20
Original Contract Amount: $307,952.60
Amount All Previous CCOs(+-): $30,795.00
Amount This CCO(+-): $20,443.60
TotalContract Amount: $359,191.20
PUBLIC WORKS CONSTRUCTION CONTRACT
CONTRACT CHANGE ORDER (cont’d)
C.C.O No. 1
2of 2
CITY’S ACCEPTANCE:The above described
work is hereby approved and directed to be
completed in accordance with the Contract
Documents.
City of Lake Elsinore
Rec.:______________________________
City Engineer Date
App.:_____________________________
City Manager Date
CONTRACTOR’S ACCEPTANCE:Contractor agrees to perform
the above work as directed,in accordance with the
Contract Documents,and acceptpayment describedabove
as full compensation for work described subject to
additions and reductions of the quantities of various items.
Contractor: I.E. General Engineering_____________
By _________________________________________
Title: _______________________________________
Date: _______________________________________