City of Lake Elsinore 130 South Main Street
Lake Elsinore, CA 92530
www.lake-elsinore.org
File Number: ID# 19-329
Agenda Date: 9/24/2019 Status: Council Consent
Calendar
Version: 1
File Type: Council Consent
Agreement
In Control: City Council / Successor Agency
Agenda Number: 13)
Page 1 City of Lake Elsinore Printed on 9/19/2019
Lincoln Street Pavement Rehab CCO
Page 1 of 1
REPORT TO CITY COUNCIL
To:Honorable Mayor and Members of the City Council
From:Grant Yates, City Manager
Prepared By: Nicole McCalmont
Date:September 24, 2019
Subject:SB1 - Lincoln Street Pavement Rehabilitation & Striping Contract Change
Order
Recommendation
Approve the contract change order to All American Asphalt for the additional scope of work on
Grand Avenue in the amount of $220,087.39.
Background
Lincoln Street Pavement Rehabilitation was submitted to CA League of Cities for Approval in
order to utilize SB1 Grant allocation of $354,123 allocated to the City of Lake Elsinore for Fiscal
Year 18/19. City Council awarded the contract to All American Asphalt on June 25, 2019 in the
amount of $833,360.25.
Discussion
Grand Avenue Pavement rehabilitation was added to the Lincoln Street Pavement
Rehabilitation Project scope due to the close proximity to the original project location as well as
the deteriorated condition/uneven pavement of Grand Ave roadway surface. Over the years
multiple utility trenching operations caused the Grand Ave roadway surface to become uneven
and accelerated its deterioration. In an effort to improve the condition of pavement on Grand
Ave, staff requested All American Asphalt to extend their scope of work adding these
improvements which is a cost savings to the City since the contractor was already mobilized at
the location.
Fiscal Impact
Funding for this project has been allocated within the approved CIP Budget.
Exhibits
A – Change Order
PUBLIC WORKS CONSTRUCTION CONTRACT
CONTRACT CHANGE ORDER
Date 09/03/2019 C.C.O No. 1
951-674-3124
130 S. MAIN STREET
LAKE ELSINORE, CA 92530
WWW.LAKE-ELSINORE.ORG
PROJECT NAME
SB1 Lincoln Street Pavement Rehabilitation & Striping
CONTRACTOR:
All American Asphalt
In conformance with and as part of the existing Agreement for this project the City of Lake Elsinore
authorizes and directs changes to the Agreement as described below.
1) EXTRA WORK ORDER (EWO) (Unknown or Unforeseen Work not covered by Contract)
a) Extra Work Item A: Addition of Grand Avenue Rehabilitation
Lump Sum Grand Avenue = $220,087.39
2) CHANGED WORK ORDER (CWO)(Significant increases in quantity of Unit-Price items; greater than 25%):
a) Changed Work Item A:
i)Time for completion will be increased/decreased by (+-) Zero (0) Working Days
3) CLOSING SUMMARY ORDER (CSO) (Final adjustment of original estimated contract quantities based on final
measured quantities):
a) Closing Summary Order:
i)Addition of Work: Based on the change of additional scope of work constructed the final
amount owed to the contractor is greater than the original agreement amount.
Total = $220,087.39
AGREEMENT AMOUNT:Compensation as set
forth in the Agreement and as amended by
this and prior Contract Change Order(s) is:
$1,053,447.64
Original Contract Amount: $ 833,360.25
Amount All Previous CCOs (+-): $0.00
Amount This CCO (+-): $ 220,087.39
Total Contract Amount: $1,053,447.64
CITY’S ACCEPTANCE:The above described
work is hereby approved and directed to be
completed in accordance with the Contract
Documents.
City of Lake Elsinore
Rec.: _____________________ 09/03/2019
City Engineer Date
App.: _____________________________
City Manager Date
CONTRACTOR’S ACCEPTANCE:Contractor agrees to perform
the above work as directed,in accordance with the
Contract Documents, and acceptpayment describedabove
as full compensation for work described subject to
additions and reductions of the quantities of various items.
Contractor: All American Asphalt
By _________________________________________
Title: _______________________________________
Date: _______________________________________