HomeMy WebLinkAboutCC Reso No 2019-030 SB1 Road repair and accountability act of 2017RESOLUTION NO 2019 -030
RESOLUTION ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2019 -20 FUNDED BY
SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the;Road Repair and Accountability Act of 2017
(Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the
Governor in April 2017 in order to address the significant multi -modal transportation funding
shortfalls statewide; and,
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure
the residents of our City of Lake Elsinore are aware of the projects proposed for funding in our
community and which projects have been completed each fiscal year; and,
WHEREAS, the City of Lake Elsinore must adopt a list of all projects proposed to
receive funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB
1 by resolution, which must include a description and the location of each proposed project, a
proposed schedule for the project's completion, and the estimated useful life of the
improvement; and,
WHEREAS, the City of Lake Elsinore, will receive and estimated $1,031,103 in RMRA
funding in Fiscal Year 2019 -20 from SB 1; and,
WHEREAS, this is the third year in which the City of Lake Elsinore is receiving SB 1
funding and will enable the City of Lake Elsinore to continue essential road maintenance and
rehabilitation projects, safety improvements, repairing and replacing aging bridges, and
increasing access and mobility options for the traveling public that would not have otherwise
been possible without SB 1 ; and,
WHEREAS, the City of Lake Elsinore has undergone a robust public process to ensure
public input into our community's transportation priorities /the project list; and,
WHEREAS, the City of Lake Elsinore used a Pavement Management System to develop
the SB 1 project list to ensure revenues are being used on the most high - priority and cost -
effective projects that also meet the communities priorities for transportation investment; and,
WHEREAS, the funding from SB 1 will help the City of Lake Elsinore maintain and
rehabilitate 18 streets /roads, and add active transportation infrastructure throughout the City of
Lake Elsinore this year and hundreds of similar projects into the future; and,
WHEREAS, the SB 1 project list and overall investment in our local streets and roads
infrastructure with a focus on basic maintenance and safety, investing in complete streets
infrastructure, and using cutting -edge technology, materials and practices, will have significant
positive co- benefits statewide.
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the City Council
of the City of Lake Elsinore, State of California, as follows:
1. The foregoing recitals are true and correct.
CC Resolution No. 2019 -030
Page 2 of 3
2. The fiscal year 2019 -20 list of projects planned to be funded with Road Maintenance and
Rehabilitation Account revenues include:
Street
Name
From
Graham
To
Treatment
Slurry Seal II
1
Lewis
Pottery
Sumner
2
3
Scrivener
Lowell
Graham
2" AC Overlay
Graham
Pottery
3" AC Overlay
4
Kellogg
Graham
1
Pottery
Heald
Pottery
Heald
Scrivener
Davis
Pottery
Slurry Seal II
5
Lindsay
Graham
Sumner
3" AC Overlay
2" AC Overlay
2" AC Overlay
6
Poe
7
Poe
Graham
8
Pottery
Poe
2" AC Overlay
3" AC Overlay
3" AC Overlay
9
Pottery
Langstaff
Scrivener
10
Graham
11
Riley
Heald
Sumner
3" AC Overlay
3" AC Overlay
3" AC Overlay
Slurry Seal II
Slurry Seal II
Slurry Seal II
12
Davis
Pottery
Lakeshore
Lakeshore
Flint
13
Davis
Pottery
14
Townsend
Pottery
Collier
15
Chaney
Treleven
16
Pottery
Langstaff
Poe
Heald
17
Matich
Lakeshore
3" AC Overlay
18
Flint
Cheney
Silver
2" AC Overlay
19
Silver
Heald
Sumner
2" AC Overlay
20
Lewis
Pottery
End
Slurry Seal II
21
Matich
Heald
Sumner
End
End
Slurry Seal II
i
22
Scrivener
Pottery
Pottery
Slurry Seal II
2" AC Overlay 1
23
Lowell
CC Resolution No. 2019 -030
Page 3 of 3
24
Kellogg
25
Lindsay
26
Minthorn
27
Minthorn
28
Minthorn
Pottery
Pottery
Collier
875' w/o Collier
1645' w/o Collier
PASSED AND ADOPTED by the City Co
California this 23rd day of April 2019, by the folly
Attest:
Mark Mahan
Deputy City Clerk
End 2" AC Overlay
End 2" AC Overlay
875' w/o Collier Slurry Seal II
1645' w/o Collier 2" AC Overlay
Chaney 2" AC Overlay
:it of the City of Lake Elsinore, State of
STATE OF CALIFORNIA )
COUNTY OF RIVERSIDE ) ss.
CITY OF LAKE ELSINORE )
I, Mark Mahan, City Clerk of the City of Lake Elsinore, California, do hereby certify that Resolution
No. 2019 -030 was adopted by the City Council of the City of Lake Elsinore, California, at the
Regular meeting of April 23, 2019, and that the same was adopted by the following vote:
AYES: Council Members Sheridan, Johnson and Magee; Mayor Pro -Tem Tisdale and Mayor Manos
NOES: None
ABSENT: None
ABSTAIN: None -
Mark Mahan
Deputy City Clerk