HomeMy WebLinkAbout0004_1_Traffic Engineer Update - SRREPORT TO PUBLIC SAFETY ADVISORY COMMISSION
TO:Honorable Chairman and Members of the Public Safety Advisory
Commission
FROM:Farid Dost, Senior Civil Engineer
DATE:June 20, 2017
SUBJECT: Traffic Engineer Update
Recommendation
Receive and file.
Discussion
Cultural Center Parking Lot – Construction commenced May 11 and will be completed in
Mid-September 2018.
Lakeshore Drive Sidewalk –Project is out to bid; construction completion is expected in
Mid-November 2018.
Graham Avenue Grind and Overlay –Project will go out to bid in late June; construction
completion is expected in late August 2018.
Summerly Signal Construction –A new signal at Diamond Drive and Summerly Place as
part of the Summerly development was initiated in early June and completion is expected
by October 2018.
Railroad Canyon Road and Summerhill sign – Additional signage will be installed at
Railroad Canyon Road/ Summerhill/ and Grape Street Traffic Signal to further alert drivers
of the new lane configuration for the southbound Summerhill approach.
Lake Street/I-15 Off-ramp –Widening and signalization is currently under construction.