REPORT TO CITY COUNCIL
To:Honorable Mayor and Members of the City Council
From:Grant Yates, City Manager
Prepared by:Jason Simpson, Assistant City Manager
Date:February 27,2018
Subject:Change Order No. 2 –Second Amendment to Public Works Construction
Agreement with Maples and Associates for the Installation of
Sewage/Wastewater Lift Station at the RV Resort Rehabilitation Project (CIP
PROJECT #Z40007).
Recommendations
1.Approve and authorize the City Manager to execute Change Order No. 2 –Second
Amendment in the not to exceed amount of $149,860.00 with Maples and Associates for
installation of the Sewage/Wastewater Lift Station at the RV Resort Rehabilitation
Project (CIP PROJECT #Z40007), in final form as approved by the City Attorney.
2.Authorize the City Manager to execute any additional change orders not to exceed a
10% contingency amount of $14,986.00 for underground uncertainties and adjustments.
Background
On July 11, 2017, following a formal bid process, the City Council awarded a construction
agreement in the amount of $998,428.00 to Maples and Associates for the installation of dry
utilities underground electrical at the Campground Rehabilitation Project. The following general
requirement items are included in the initial scope of work:
General Requirements
Underground Dry Utilities (Conduit & Wire)
Above Ground Dry Utilities
Main Electrical Panels & Breakers/Circuits\
Electrical Power Pedestals (236 RV Sights)
Security Lighting Exterior(Street Light Caissons, Light Poles and Lamps)
Underground Data/Communication Conduits
The installation of dry utilities at the project site necessitated a change order which was
previously approved by the City Council on February 16, 2018.
Change Order No. 2 -- Installation of Sewer Lift Station at the RV Resort Rehabilitation Project.
February 27, 2018
Page 2
On January 9, 2018, the City Council awarded a Design and Build Service Agreement to Pacific
Southwest Industries (PSI) for the Design and Build of the Sewage/Wastewater Lift Station at
the RV Resort Rehabilitation Project (CIP PROJECT #Z40007). The design and build of the
Sewage/Wastewater Lift Station has been completed and the delivery of all the components to
the RV Resort is anticipated in the next two weeks.
The Sewage/Wastewater Lift Station will be used for pumping wastewater and sewage from a
lower to higher elevation in the RV Resort, specifically, where the elevation of the source is not
sufficient for gravity flow. The lift station unit has been built as a factory assembled package
system. Key elements of the lift station include a sewage/wastewater receiving well (wet-well),
equipped with lift electric pumps and piping with valves, a junction box, and an equipment
control panel with alarm system.
Maples and Associates is currently fully mobilized on the site and ready to immediately proceed
on this critical path item.
Discussion
The essentials of this change order are summarized below as general requirements:
General Requirements
Excavate approx. 30’ Deep x 15’ Sq. w/ Shoring
Undergrounding of the Lift Station Vault
Pour Anti Floatation Collar, Set Electric Pumps
Ready Bypass Piping & Vault
Connection to Newly Installed Sewage/Wastewater Line
Connection to Existing Sewage/Wastewater Main
Provided Electrical Supply Connection to Main Panel
Installation of Backup Power Pad for Emergency Generator
Staff has confirmed with Maples and Associates that the scope of the change order is complete
for the installation. As a separate matter but related item, sewage/wastewater connection
approval has been obtained from Elsinore Valley Water District.
Following the approval of this agenda item, the installation of Sewage/Wastewater Lift Station
work will be scheduled in conjunction with the underground electrical and wet utilities site
improvements being completed by Maples.
Fiscal Impact
The installation of the Sewage/Wastewater Lift Station at the RV Resort Rehabilitation Project
(CIP PROJECT #Z40007) is included in the Fiscal Year 17/18 – 21/22 Capital Improvement
Plan (CIP) budget.
Exhibits
A: Second Amendment
B: Plans (Plan Set Civil, Electrical and PSI)
Change Order No. 2 -- Installation of Sewer Lift Station at the RV Resort Rehabilitation Project.
February 27, 2018
Page 3
C: Maples and Associates Proposal
1
CHANGE ORDER NO. 2
SECOND AMENDMENT TO AGREEMENT FOR PUBLIC WORKS
CONSTRUCTION
MAPLES AND ASSOCIATES
FOR RV RESORT REHABILITATION PROJECT
CIP PROJECT NO. Z40007
DRY UTILITIES
THIS CHANGE ORDER NO. 2 – SECOND AMENDMENT (the “Second Amendment”) is made
and entered into as of February 27, 2018 by and between the City of Lake Elsinore, ("City"),
and Maples and Associates Inc. ("Contractor”). In consideration of the mutual covenants and
conditions set forth herein, the parties agree as follows:
1. This Second Amendment is made with respect to the following facts and purposes:
a. On July 11, 2017 the City and Contractor entered into an agreement entitled Agreement
for Public Works Construction with Maples and Associates for the installation of dry
utilities underground electrical at the RV Resort Rehabilitation Project (CIP PROJECT
#Z40007) (the “Original Agreement’).
b. On or about February 13, 2018, the City and Contractor entered into that certain First
Amendment to the Original Agreement. The Original Agreement and the First
Amendment are hereinafter referred to as the Agreement.
c. The parties now desire to increase the agreement amount for an additional One
Hundred Forty-Nine Thousand Eight Hundred Sixty Dollars ($149,860.00) for additional
work and amend the Agreement as set forth in this Second Amendment, such work as
described in “Proposal 02142018” dated February 14, 2018 and attached hereto.
2. Compensation of the Agreement is hereby amended to increase the amount that the City
agrees to pay the Contractor One Hundred Forty-Nine Thousand Eight Hundred Sixty
Dollars ($149,860.00) for a total not-to-exceed amount of One Million Three Hundred
Twenty Five Thousand Six Hundred Seventeen Dollars ($1,325,617.00).
3. Except for the changes specifically set forth herein, all other terms and conditions of the
Agreement shall remain in full force and effect.
2
IN WITNESS WHEREOF, the parties hereto have caused this Second Amendment to be
executed by and through their respective authorized officers, as of the date first above written.
“CITY”
CITY OF LAKE ELSINORE, a municipal
corporation
Grant Yates, City Manager
ATTEST:
_______
City Clerk
APPROVED AS TO FORM:
City Attorney
“CONTRACTOR”
Maples and Associates
Mike Maples, Owner
PROPOSAL DATED FEBRUARY 14, 2018
[ATTACHED]
%+6;1(.#-''.5+014'VICINITY MAPN.T.S.CITY OF LAKE ELSINOREOREER
TASTSIG
T
E
DR
E
PEIACFLOFCIVLIARNI
ERONSOFEISLEGINNAJ
O
H
NM.BRUDIN3550 E. Florida Avenue, Suite BHemet, California 92544(951) 765-6622 Fax (951) 765-6621
%105647%6+10016'5
(LIFT STATION PLAN)
.+(656#6+10#0&(14%'/#+02.#0
SCALE: 1" = 10'
CITY OF LAKE ELSINORE
O
R
EERT
AS
TSIGTEDRE P
EIACFL OF
CI V LI ARNI ERON
SOFE IS
L
EGI
NNA
JOH N M .BR
U
D
I
N3550 E. Florida Avenue, Suite B
Hemet, California 92544
(951) 765-6622 Fax (951) 765-6621
Feet
1:10
201005
37#06+6+'5
(LIFT STATION PLAN)
DESCRIPTION
FIRST ISSUE
REV BY
A SR
A
DRAWING NO. PROJECTDRAWN BY
DT
DATE REV
NTS
SCALE
INFORMATION AND IS THE EXCLUSIVE
PROPERTY OF PSI. IT MAY NOT BE
COPIED OR REPRODUCED IN ANY FORM
WITHOUT THE EXPRESS WRITTEN PERMISSION
OF PSI.
THIS DRAWING CONTAINS CONFIDENTIALPSI pacific southwest industries
ENGINEERED- PUMPS/FLUID HANDLING & DISPOSAL SYSTEMS
DUPLEX SEWAGE
2
D
1
A
12
D
345
4
A
5 3
C
B
C
B
No. DateDescriptionRevisions: SEWAGE PUMP SYSTEM PSI pacific southwest industriesENGINEERED- PUMPS/FLUID HANDLING & DISPOSAL SYSTEMS30520 COPLASA ST. , LAKE ELSINORE, CA 92530 PH: 800 358-9095LIFT STATION DETAILSLA LAGUNA RV & RESORTRIVERSIDE DR LAKE ELSINORE, CA LSD-1Date: 08/17/17Drawn by: DTScale: NTSChecked by: SRSheet no: 1 of 2 78”
ERS8171708/17/17 LA LAGUNA
RV RESORT
CONTROL
PANEL
8” INLET
DESCRIPTION
FIRST ISSUE
REV BY
A SR
A
DRAWING NO.
ERS81717
PROJECTDRAWN BY
DT 08/17/17
DATE REV
NTS
SCALE
INFORMATION AND IS THE EXCLUSIVE
PROPERTY OF PSI. IT MAY NOT BE
COPIED OR REPRODUCED IN ANY FORM
WITHOUT THE EXPRESS WRITTEN PERMISSION
OF PSI.
THIS DRAWING CONTAINS CONFIDENTIALPSI pacific southwest industries
ENGINEERED- PUMPS/FLUID HANDLING & DISPOSAL SYSTEMS
PACKAGED LIFT STATION
2
D
1
A
12
D
345
4
A
5 3
C
B
C
B
EMERGENCY BYPASS
WITH CAMLOCK
FITTING AND PLUG
ALL PIPING IS 4”
SCH 80 PVC STEEL
ANTI-FLOTATION
FLANGE
2” SCH 10
316 SS GUIDE
RAILS
PROBE LEVEL
SENSOR BAR
ANTI-FLOTATION
FLANGE
LA LAGUNA
RV & RESORT
~68.5”
8”
Inlet330”78”
78”
4”
VENT
(2) 2”
ELECTRICAL
CONDUITS
2” DRAIN
DUPLEX
CONTROL
PANEL
NOTICE TO THE CONTRACTOR
This lift station and controls will be owner specified, contractor furnished, and delivered to the
site. The successful bidder will furnish all other materials and labor to install the lift station and
its controls and ensure its proper operation. It is the contractor ’s responsibility to install the lift
station per this plan as indicated and make all connections, plumbing and electrical, in an
approved manner as required by this drawing and local codes. The contractor ’s responsibilities
are as follows: receiving the lift station and off loading, excavation and setting, all plumbing
connections (inlet, vent, wet well to valve box, force main run thereafter to the point of city
connection of receiving manhole or force main), all electrical conduit from the wet well to control
panel, provide proper backfill and compaction procedures. The contractor will be required to
lower the pumps into place and perform the system start up . A startup procedure form will be
provided and it must be filled out and returned to the lift station supplier prior to the owners
possession date via fax or email. Fax #951-678-7163 email- info@psipumps.com
Receiving / offloading instructions and preparation before setting
Receiving the lift station
Inspect the entire shipment for damage before the lift station is taken off the truck. If there is damage, note as
specifically as possible including clear photos of damage on the bill of lading as to any damage, then offload.
Contact the shipper at once and have the bill of lading with you. Call 800-358-9095 for further instructions.
Preparing the lift station
The lift station has been made ready to travel several hundred miles. The main wet well will contain bracing that
needs to be removed before it is set in place. The lift station is to remain horizontal and on the pallet until the day
it is to be set in place. On that day open the main hatch and remove the control panel, basin fittings, transducer
housing and float tree. Remove all lumber bracing, wire ties and duct tape. Check all flange bolts and tighten as
necessary. Check all flange bolts in the valve box as well, tighten as necessary.
Setting the lift station
The best way to set the wet well is to use two cinch straps of equal length. Place the straps right under the rim so
they will tighten as the wet well is lifted. If the straps are properly positioned the wet will hang level and secure. If
you have experience in this area use your own discretion.
BASIN INSTALLATION INSTRUCTIONS
1. Excavation Dimensions: Excavation shall be 6" deeper than the depth of the basin, below finish grade
and done in such a manner as to preserve the undisturbed state of bearing soils at the bottom. Diameter
of excavation shall be sufficient to allow for necessary external pipe connections with a minimum 12"
greater than the basin diameter.
2. Backfill Materials:
a. The backfill materials shall be in inert, free flowing granular soil such as clean sand or gravel (1/4"
mesh or finer).
b. Acceptable backfill includes “stone dust” from rock crushing operation provided it possesses all
the characteristics of free flowing sand and contains less than 20% by weight passing the No. 200
mesh sieve. Soil fines must be non-plastic.
c. Silts, clays, organic soil, granulated cinder, slag and similar corrosive material shall not be used.
Backfill shall be free of organic material, loam, trash, snow, ice, stones, rubble, etc.
3. Pipe Connections: Make necessary pipe connection in approved manner. Note: connection may be
threaded, caulked lead joints or other specified approved method,
NOTE: BACKFILL SHOULD BE DONE AS SOON AS THE WET WELL IS SET AND LEVEL.
4. Backfill as follows:
a. If the hole is flooded, the water level shall be pumped down to a maximum depth of 3 inches before
preparing the bed and placing the basin. Water level shall be maintained below bottom of the
basin until the excavation is backfilled and until there is adequate safety against uplift.
b. The first layer of backfill is the base for the basin and shall be at least 6" thick.
c. Place the basin on the bed and after aligning and leveling, push additional fill under and around
the basin and compact by tamping to a uniform depth of 12" around the basin. This insures that
the established grade and level of the basin will be maintained during remainder of the backfilling
operation.
d. Backfill shall be continued in one foot layers with specified sand backfill uniformly distributed
around the basin and compacted around the basin.
e. Concrete encasement may be used in lieu of backfill as described above, if the whole excavation
does not exceed 12" in diameter larger than the basin to be installed.
5. Cover: The cover shall be bolted in place with an approved gasket material to effect a gas-tight seal.
Instructions to remove a reinforcing rib to install the inlet
This procedure is required only if the gravity inlet lands on a rib!
Measure the length of the rib to be removed. Using a sawzall cut the rib lengthwise on the top and bottom of the
rib. Keep in mind that the rib is hollow. Make the end cut between the top and bottom of the rib. Note: take care
not to damage the underlying wall of the wet well. Remove the cut rib and the foam underneath. Use a circular
sander to reduce the ridges left by the removal of the rib. What should remain is the uniform wall thickness of the
wet well where the inlet is to be installed. Note: it is ok to remove a little more rib than to just fit the inlet fitting.
Six inches on each side of the inlet is fine.
INSTALLATION OF THE FLOAT TREE AND THE SUBMERSIBLE TRANSDUCER HOUSING
Installing the submersible transducer housing and transducer
(The transducer is very sensitive to shock - be very careful with it!)
The housing has been cut to fit prior to leaving the factory. Slip the bottom of the housing over
the pre-installed strainer at the bottom of the wet well. At the top under the small hatch there will
be a clamp holding a short 2” pipe. Discard the short pipe and use the clamp to secure the top of
the housing. Make sure the housing is plumb.
The transducer will be located behind the outer door of the control panel. Remove all packing
material and slowly lower the transducer into the housing until it reaches the bottom, then pull
back 2” of cable, loop the cable over the housing and secure with the wire ties provided, use two.
The cable is color coded and will correspond with the connection locations in the control panel.
The clear tube will connect to the aneroid bellows in the control panel.
Installing the float tree
The floats have been preset - no adjustment is necessary. Lower the float tree through the small
hatch on the main wetwell cover. Insert the bottom end of the tree into the floor flange installed
at the bottom of the wetwell. The short 1” pipe in the clamp will be discarded. The clamp will be
used to secure the top of the float tree. Once installed, rotate the float tree to ensure free
movement of the floats. The floats need to float up and down without touching anything. The
tags on the floats will correspond with the connection locations in the control panel - do not
remove the tags.
TOP ELEV. 1266.00
S INV. ELEV. 1243.33
BOTTOM
ELEV. 1238.50
SUBMERSIBLE PROBE LEVEL SETTINGS
ALL PUMPS OFF @ 1239.33
LEAD PUMP OFF @1239.83
LEAD PUMP ON @ 1242.33
LAG PUMP ON @ 1242.83
ALARM ON @ 1243.33
Job no:ERS817174” VENT
TBD
CONTRACTOR IS TO COMBINE THE
TWO 4” DISCHARGE LINES INTO ONE
4” FM PVC SCH 80 FORCE MAIN
DETACHED VALVE BOX
(WITH PIPING)
78”
CONTRACTOR IS TO COMBINE THE
TWO 4” DISCHARGE LINES INTO ONE
4” PVC SCH 80 FORCE MAIN.
LA LAGUNA RV RESORT
LAKE ELSINORE, CA
SE-1&2: PACKAGE SEWAGE LIFT STATION
SCOPE OF SUPPLY:
Furnish and install complete pre-packaged sewage pump lift station model # PSI-ERS81717 as manufactured by Pacific Southwest Ind. No
exceptions to this specification may be taken without engineers approval.
The lift station shall incorporate a quick removal system that does not require the use of o-rings or gaskets to make a seal between the vortex pump
and the pre-mounted quick removal discharge base. The vortex pumps shall be guided to the discharge base by the use of two stainless steel guide
rails for each pump. The diameter of the guide rails shall be no less than 2"and shall extend from the discharge base to the upper guide bracket
mounted on the cover. Lifting chain or cable shall be attached to the top of the pump and to the cover adjacent to the upper guide bracket for easy
access and pump removal. The internal discharge plumbing shall be pre-plumbed in schedule 80 PVC and extend , in parallel, 12" beyond the wet
well side wall for contractor connection to the valve box and then combine into one 4” force main. Each pump discharge line shall include one non-
slamming check valve and one true union ball valve in a detached valve box. The valve vault will be pre-plumbed with flanged check and plug valves
The lift station shall include a submersible transducer for primary level control and 2 float back up system, pre-set and ready to be installed the wet
well. The duplex control panel shall be surface mountable adjacent to the lift station. The pumps, quick removal system, and level sensors shall
be housed in a fiberglass wet well 60" in diameter and 330”in length and shall incorporate an oversized steel anti-flotation flange.
PUMPS: Each pump model number 100UZ45.5 shall deliver 270 GPM each at 35.17 FT TDH.
The pump(s) shall be a recessed vortex designed to pump wastewater, sewage or effluent containing solids(3.94” spherical without damage during
operation. The pump(s) shall be designed so that the shaft power required (BHP)/(KW) shall not exceed the motor rated output throughout the entire
operating range of the pump performance curve.
MATERIALS OF CONSTRUCTION
All major parts of the pumping unit(s) including casing, Impeller, discharge elbow, and motor frame shall be manufactured from gray cast iron, ASTM A48
CLASS 35. Internal and external surfaces coming into contact with the pumpage shall be protected by a fused polymer coating. All exposed fasteners
shall be stainless steel. All units shall be furnished with a discharge elbow with 150 lb. (10 Kg./Cm2) flat face flange and 4" ANSI flange. Impellers shall be
of the multi-vane vortex design, equipped with back pump out vanes, tungsten carbide vane tip and shall be slip fit to the shaft and key driven.
MECHANICAL SEAL
All units shall be furnished with a dual inside mechanical shaft seal located completely out of the pumpage, running in a separate oil filled chamber and
further protected by an exclusionary oil seal located between the bottom seal faces and the fluid being pumped. The oil chamber shall be fitted with a
device that shall provide positive lubrication of the top mechanical seal, (down to one third of the standard oil level). The device shall not consume any
additional electrical power. Mechanical seals shall be rated to preclude the incursion of water up to 42.6 PSI (98.4 Ft.). Units shall have silicon carbide
versus silicon carbide upper and lower mechanical seal faces. Mechanical seal hardware shall be stainless steel. Units designed to exceed 42.6 PSI at
shut off head shall incorporate seal pressure relief ports.
MOTOR
The pump motor(s) shall be 7.5 HP, 5.5 kW., 230/460 V. 3 Phase 60 Hz and shall be NEMA MG-1, Design Type B equivalent. Motor(s) shall be rated at
20.5/10.2 full load amps. Motor(s) shall have a 1.15 service factor and shall be rated for 20 starts per hour. Motor(s) shall be air filled, copper wound,
class F insulated with built in thermal and over current protection for each winding. Motor shaft shall be 420 stainless steel and shall be supported by
two permanently lubricated, high temperature ball bearings, with a B-10 life rating at best efficiency point of 60,000 hours. The bottom bearing on units
7.5 HP (5.5 KW) and below shall be a single row, double shielded, C3, deep groove type ball bearing. Units 10 Hp. (7.5 KW) and larger shall have a
double row, double shielded, C3, angular contact type bottom bearing. The top bearing on all units shall be a single row, double shielded, C3, deep
groove type ball bearing.
POWER CABLE AND CABLE ENTRANCE
The pump power cable shall be suitable for submersible pump applications and shall be field replaceable utilizing standard submersible pump cable. The
cable entrance shall incorporate built-in strain relief and a combination three-way mechanical compression sealing with a fatigue reducing/thermal
expansion boot. The cable entrance assembly shall contain an anti-wicking block to eliminate water incursion into the motor due to capillary wicking
should the power cable be accidentally damaged.
DUPLEX ALTERNATING CONTROL PANEL
( MAIN LEVEL CONTROL BY SUBMERSIBLE PROBE LEVEL SENSORS)
The control panel shall have a NEMA 4X door -in -door dead front locale fiberglass enclosure suitable for wall mounting. A integral motor starter
with short circuit protection and over load protection shall be provided for each pump . An alternating relay shall be provided to alternate pumps on
each successive cycle of operation. The starter shall have auxiliary contacts to operate both pumps in an override condition. The control circuit
shall not be affected in the event that either pump trips the pump circuit breaker. H.O.A. switches, run lights for each pump, motor overload light for
each pump, elapsed time meter for each pump, thermal cut out terminals with over temperature lights, control circuit breaker or fuse, 15 amp
convenience outlet breaker, 2KVA control circuit transformer with fused primary, 15 amp 120 volt convenience outlet (GFI) grounded and bonded
and mounted on inner door, lighting arrester, surge capacitor, phase monitor, time delay for no simultaneous pump starting and alarm test switch for
light and buzzer operation only (no contact closure)shall be provide as a minimum. A terminal strip shall be provided to terminate all incoming
power, pump, transducer, level sensors and remote alarm wiring. The control panel shall offer a high water alarm light, top mounted for 360 degree
visibility. An external push button shall be provided to silence the audible alarm. The control panel shall be optioned with a generator hook up
receptacle, 60 amp manual transfer switch and matching plug. Provide single pole double throw auxiliary contacts for power loss to the lift station or
high water alarm condition. One set of contacts will provide for both events.
The control panel will be equipped with a 4 channel Auto Dialer (OR RTU’S for city telemetry system) to be used for monitoring the
following conditions: High Water Alarm, Power Loss, Pump 1 Failure, Pump 2 Failure.
FIBERGLASS WET WELL AND VALVE BOX:
The fiberglass wet well shall be suitable for high water table installations and shall have a steel anti-flotation flange bottom shall be provided by the
wet well manufacturer. The wet well shall be no less than 60" inside diameter and be 330" in length. The fiberglass tank will be fitted with an
oversized anti flotation collar 78” outside diameter The capacity of the wet well below the lowest inlet is to be ~735 gallons (operating capacity).
The laminate shall have a barcol hardness of a least 90% of the resin manufactures minimum specified hardness for cured resin on both the interior
and exterior surfaces. The minimum wall thickness of the wet well shall not be less than 3/8". The wet well manufacturer shall encapsulate in the
bottom of the wet well stainless steel studs for the mounting of the quick removal system. . The top rim flange must be no less than 3" wider than the
ID of the wet well (66" O.D.) The wet well must be provided with 2- 8" inlet fitting for field installation by the contractor at the elevation and location
as indicated on the plans. All other penetrations shall be sealed by using “Uniseal” fitting or “Flex boot” fittings. The valve box shall be
manufactured with the same process as the wet well. The valve box shall have an inside diameter of 60" with a depth of 78" and be fitted with and
oversized anti floatation flange 78” outside diameter The valve box shall include two non-slamming check valves(Model# Valmatic 504MIK), 2- 4”
cast iron plug valves (Model# Valmatic5804) and a 3” emergency bypass piping with shut off valve and appropriate cam-lock fittings.
ALUMINUM DIAMOND COVERS WITH HATCH ACCESS:
The covers of the wet well and valve box shall be no less than 1/4" thick aluminum diamond tread suitable for load up to 300 psf. The covers must
have a clear access opening for pump removal and valve access as recommended by the pump manufacturer. The access covers shall be hinged
with a hold open arm at 90 degrees. The covers will be equipped with a slam lock feature.
SEWAGE LIFT STATION PROFILE & CALCULATIONS
LA LAGUNA RV & RESORT
LAKE ELSINORE, CA
FIXED CONDITIONS:
STATIC HEAD 21.27 FEET
LENGTH OF RUN 171.0 FEET
TYPE OF PIPE PLASTIC
SIZE OF FORCE MAIN 4 INCH
TYPE OF FLUID RAW UNSCREENED SEWAGE
VOLTAGE 230/460
PHASE 3
GRAVITY INLET SIZE 2- 8 INCH
INLET ELEVATION S 272.04 INCHES , NW 95.64 INCHES
CALCULATIONS:
STATIC HEAD 21.27 FEET
TOTAL FRICTION HEAD 13.90 FEET
CALCULATED TOTAL DYNAMIC HEAD 35.17 FEET
MAINTAINED VELOCITY OF 7.33FEET PER SECOND @ 270 GPM PER PUMP
PUMP CYCLE TIME IS 5.65 MINUTES
INFLOW OF 130 GPM. 10 STARTS PER HOUR
TOTAL 5 STARTS PER PUMP
16”
DISCHARGE
ELEV. 1260.28
66” ALUMINUM DIAMOND TREAD
HATCH COVER 66” ALUMINUM DIAMOND TREAD
HATCH COVER
TOLL FREE 800-358-9095
PACKAGED LIFT STATION
NW INV. ELEV. 1258.03
8”
Inlet
TOP ELEV. 1266.00
FILLET 45 DEG.
BOTTOM
8” INLET
78”
12” BED MIN.
3/4” MINUS
AFC-5
SEE LSD-2
DETAIL
ALARM
LAG PUMP
LEAD PUMP
OFF PUMP
ALL OFF
No. DateDescriptionRevisions: SEWAGE PUMP SYSTEM PSI pacific southwest industriesENGINEERED- PUMPS/FLUID HANDLING & DISPOSAL SYSTEMS30520 COPLASA ST. , LAKE ELSINORE, CA 92530 PH: 800 358-9095LIFT STATION DETAILSLA LAGUNA RV & RESORTRIVERSIDE DR LAKE ELSINORE, CA LSD-2Date: 08/17/17Drawn by: DTScale: NTSChecked by: SRSheet no: 2 of 2 Job no:ERS8171712453
23
D
1
A
D
A
C
B
C
B
45
AFC-1
RECOMMENDED FOR REVIEW BY ENGINEER
ANTI-FLOTATION COLLAR DETAIL
NOTICE TO CONTRACTOR
CONTRACTOR TO PROVIDE ANTI-FLOTATION COLLAR PER DETAIL AFC-1
IF WATERTABLE EXISTS AT THE LIFT STATION LOCATION 7.5 FEET OR LESS FROM
#6 CONTINUOUS
AROUND CONC.
RING (TYP)
#3 TIES
12” O.C.
FIBERGLASS
WET WELL
24”36”CONCRETE
ANTI-FLOTATION
COLLAR 5 CY REQ.
FIBERGLASS
WET WELL
CONCRETE
ANTI-FLOTATION
COLLAR 5 CY REQ.
MINIMUM
60” DIA.
24”24”
60” DIA.
8’
Proposal# 02142018
Install Owner Supplied Pump Station
City of Lake Elsinore
130 South Main Street
Lake Elsinore, California 92530
Attn: Mr. Gus Papagolos
Maples and Associates.
24977 Washington Street J
Murrieta, CA 92562
Phone: 951 491-9562
Lic.# 701704
Date P.O. No. Proposal
02/14/2018 02142018
Scope of Work: Excavate approx. 30’ Deep x 15’ square, Shoring, place ¾ inch rock,
Set lift station, pour anti floatation collar, set pumps & piping.
Set bypass piping and vault, backfill lift station and bypass vault
Startup Lift Station.
Connect to existing Manhole/ approx. 171 of forced main pipeline.
Connect to existing pipe approx. 100L.F.
Run Conduit to Main Switch panel for Pump Station
Pour a concrete pad for Pump Station and Emergency Generator
Backfill with native soil.
Exclusion:
Ground Water Pumping,
Pump Station to be delivered to Jobsite
Total: $149,860.00