HomeMy WebLinkAbout0009_1_NOC Elevator - SRREPORT TO CITY COUNCIL
To:Honorable Mayor and Members of the City Council
From:Grant Yates, City Manager
Prepared by: Jason Simpson, Assistant City Manager
Date:January 24, 2017
Subject:Notice of Completion on Public Works Construction Work for Rosetta
Canyon Sports Park Phase II Z40004
Recommendation
1. Accept the improvements into the City Maintained System for the project; and,
2. Authorize staff to file the Notice of Completion with the County Recorder for the project; and,
3. Authorize final costs and staff to release all retention monies 35 days after the filing of the
Notice of Completion for Schindler Elevator Corp $65,600
Background
The City Council awarded a contract to Schindler Elevator Corp for the work specified in the
above table. All of this work has been completed per the plans this project. Final billing and
invoicing has been received by the City and contractor paid in full less the retention amount.
Discussion
This contractor has completed the corresponding scope of work for the subject project and the
State of California has completed the elevator inspection and issued the certification.
Fiscal Impact
Funding for these projects were allocated under the City’s CIP adopted budget for the Fiscal
Year 2016/2017.
Exhibits
A - Notice of Completion - Rosetta Canyon Sports Park Phase II (Schindler Elevator Corp)