HomeMy WebLinkAboutItem # 8 Maples Senior Center - Exhibit B Change Order No. 22
DATE:
QUANTITY UNIT
Lump Sum 1.00
TOTAL
SUM OF
2
Review by: Initials Date DateApproved by:
Director Public Works:
Contractor
City Manager:
$88,878.00
THE AMOUNT OF THE CONTRACT WILL BE (INCREASED) BY THE
$88,878.00
Change Order No.
ITEM QUANTITY UNIT PRICE EXTENSION
None
QUANTITIES DECREASED
QUANTITIES INCREASED
ITEM UNIT PRICE EXTENSION
WATER AND ELECTRICAL DAMAGE - ROOF
AND WALLS
$88,878.00 $88,878.00
Assistant City Manager PRIOR TO THIS CHANGE ORDER
$206,984.92
CONTRACTOR IS AUTHORIZED TO MAKE THE FOLLOWING CHANGES:
DATE AWARDED: September 13, 2016
Authorized by: Jason Simpson TOTAL AMOUNT OF CONTRACT
December 1, 2016
THIS CHANGE ORDER IS APPLICABLE TO:
CITY PROJECT # z40016 CONTRACT AWARDED TO:
PROJECT TITLE: SENIOR ACTIVITY CENTER - EMERGENCY
REPAIRS
MAPLES AND ASSOCIATES
CITY OF LAKE ELSINORE
130 S. MAIN STREET
LAKE ELSINORE, CA 92530
(951) 674-3124
PROJECT CHANGE ORDER CHANGE ORDER #