Loading...
HomeMy WebLinkAbout0005_2_RMF Change Order - Exhibit A1 DATE: QUANTITY UNIT Lump Sum 1.00 TOTAL 1 Review by:Initials Date Date THIS CHANGE ORDER IS APPLICABLE TO: City Manager: $74,443.00 Approved by: Contractor Change Order No. Assistant City Manager: THE AMOUNT OF THE CONTRACT WILL BE (INCREASED) BY THE SUM OF $74,443.00 None $74,443.00Electrical Work - Parking Lot; FIOS connection; CITY OF LAKE ELSINORE 130 S. MAIN STREET LAKE ELSINORE, CA 92530 (951) 674-3124 November 15, 2016 PROJECT CHANGE ORDER CHANGE ORDER # UNIT PRICE EXTENSION Phase II ELECTRICAL (FIELD LIGHTING AND EXTERIOR LIGHTING Bid Set "D" ITEM Authorized by: Jason Simpson TOTAL AMOUNT OF CONTRACT CITY PROJECT # March 8, 2016DATE AWARDED: PROJECT TITLE: Rosetta Canyon Sports Park CONTRACT AWARDED TO: RMF CONTRACTING, INC. Z40004 UNIT PRICE EXTENSIONQUANTITYITEM QUANTITIES DECREASED $74,443.00 security cameras; one additional main electrical power line. $1,249,572.00 QUANTITIES INCREASED PRIOR TO THIS CHANGE ORDER CONTRACTOR IS AUTHORIZED TO MAKE THE FOLLOWING CHANGES: Assistant City Manager