HomeMy WebLinkAbout09-10-2002 City Council/RDA Study SessionCITY COUNCIL/REDEVELOPMENT AGENCY
STUDY SESSION
CITY OF LAKE ELSINORE
183 NORTH MAIN STREET
LAKE ELSINORE, CALIFORNIA
TUESDAY, SEPTEMBER 10, 2002
CALL TO ORDER
Mayor Kelley called the Study zSession to order at 4:05 p.m.
ROLL CALL _
PRESENT: COUNCILMEMBERS: BUCKLEY, HICKMAN,
SCHIFFNER, KELLEY
ABSENT: COUNCILMEMBERS: BRINLEY
Also present were: City Manager Watenpaugh, Assistant City Manager
Best, City Attorney Leibold, Administrative Services Director Boone,
Community Development Director Brady, Community Services
Director Sapp, Information /Communications Manager Dennis, Public
Works Manager Payne and Deputy City Clerk Paredes.
DISSCUSSION
1. Agenda, view:
ti
Councilman Buckley addressed Item No. 2, regarding the Warrant
List for August 30, 2002. He questioned Check No. 70617.
Administrative Services Director Boone stated that it was for debt
service. Councilman Hickman questioned the purpose of Check No.'s
70643, 70665 and 70755. Administrative Services Director Boone
stated that No. 70643 was for a refund deposit; No. 70665 was the
payment for dental insurance for the employees; and No: 70755 was
for Contract Building Inspectors
PAGE TWO — STUDY SESSION- SEPTEMBER 10, 2002
Councilman Hickman addressed Item No. 5, regarding C.D.B. G.
Sponsor's Agreement— Senior Citizen's Center 2002 -2003. He
commented that more than half of the people utilizing the Senior
Center were not residents from within City Limits. He questioned
why the County was contributing $10,000 and the City was picking up
the rest of the cost. He stated that he felt that the County should be
contributing at least half of the support for the Senior Center, City
Manager Watenpaugh explained that the County and contributed
more, however when they opened their Senior Center in.Wildomar the
amount allocated to the City was reduced. Councilman Hickman
asked if it was possible to contact Supervisor Buster regarding the
funding of the Senior Center in Lake Elsinore. City Manager
Watenpaugh stated that he would attempt to do so.
Councilman Buckley addressed Item No. 6, regarding the Patrol Boat
Grant Contract. He questioned if the $45,000 was the maximum
amount that would be spent. City Manager Watenpaugh stated that it
was, and presented an overview of the Agreement. He noted that this
would be the second boat that the City had acquired in this manner.
Community Services Director Sapp explained that the contract would
have to be approved prior to the purchase. Councilman Hickman
inquired if the boat would be used to render aid. Community Services
Director Sapp indicated that the boat would be used for patrol and first
response for first aid.
Councilman Buckley addressed Item No. 21, regarding the Public
Hearing on 2002 Local Law Enforcement Block Grant Program
Award. He noted a typo in one of the recommendations. City
Manager Watenpaugh indicated that he would have it corrected.
Councilman Hickman addressed Item No. 31, regarding the award of
contract for Railroad Canyon Road — Lane Addition Design. He
asked if the City had gone to bid on the Agreement. City Manager
Watenpaugh stated that the City did not go to bid since Harris and
Associates had performed similar projects for the City. Councilman
PAGE THREE — STUDY SESSION — SEPTEMBER 10 2002
Buckley questioned the amount that would be paid to Harris and
Associates for the design and engineering of the project; noting that it
would cost approximately 12% of the cost of the project to do the
design and engineering. City Manager confnmed. Councilman
Buckley suggested that in the future he would like to see the City go
to bid for new projects, since he had a trust problem with Harris and
Associates. Mayor Kelley asked where the City stood with Cal Trans
regarding the interchange. Community Development Director Brady
advised that various designs were submitted to Cal Trans and the only
responded by asking for further soils and seismic information. He
noted that no further information had been received from Cal Trans.
Councilman Buckley asked if sketches of the different interchange
designs could be provided to Council. Community Development
Director Brady stated that he would provide them. There was general
discussion regarding the interchange, as well as the Collier and
Central intersection.
Councilman Hickman addressed Item No. 32, regarding the Main
Street tree light replacement. He asked if Public Works had personnel
to take care of this job. City Manager Watenpaugh indicated that the
City had a contractor who did the tree trimming and an electrician
who the City contracts with. Councilman Hickman suggested that the
City use a chemical to stunt the growth of the trees to reduce the
problem with lights and trimming. City Manager Watenpaugh noted
that there was a chemical to stunt the growth of shrubs and trees,
however that would not address vandalism problems which had
occurred over the last few years. Councilman Hickman suggested that
the DBA should address the trees. There was general discussion
regarding right -of -way issues. Councilman Buckley asked why this
item was not included in the budget. City Manager Watenpaugh
explained that it was mentioned at budget time, however Council was
considering other priorities. He indicated that he was bringing this
item before Council for consideration because the downtown
businesses wished to have Council give the item consideration.
Councilman Hickman asked if the trimming and light repair would be
PAGE FOUR- STUDY SESSION— SEPTEMBER 10, 2002
done after the leaves fell. Community Services Director Sapp
indicated that it would be done after the leaves fell, and noted that
they only had to be.trimmed once every four or five years.
Councilman Buckley stated that he could' under�tand trimming the
trees and replacing and fixing lights, however he asked why staff
wished to increase the number of lights. City Manager Watenpaugh
noted that there were approximately 200 lights per tree and there
should be 400 lights, however over the years there had been repairs
and the number of lights had decreased, so the request was to bring
the number of lights back to the original number. Mayor Kelley noted
that the City has done a "band -aid" job for the last several years and
she felt that if the City was going to address this, it should be done
correctly. Mayor Pro Tem Schiffner stated that it would cost $40,000
up front, however in the long range he felt it would be a good
investment.
Redevelopment Agency
No comments were made.
ADJOURNMENT
THE CITY COUNCILIREDEVELOPMENT AGENCY STUDY
SESSION ADJOURNED AT 4:25 P.M.
9ENIE KELLEY, M"OR
CITY OF LAKE ELSINORE
PAGE FIVE — STUDY SESSION — SEPTEMBER 10, 2002
Respectfully submitted,
N I )�a�
A ria L. Paredes, Deputy City Clerk
ATTEST:
VICKI KASAD, C.M.C., CITY CLERK
HUMAN RESOURCES DIRECTOR
CITY OF LAKE ELSINORE