REPORT TO CITY COUNCIL
TO: HONORABLE MAYOR
AND MEMBERS OF THE CITY COUNCIL
FROM: GRANT M. YATES
CITY MANAGER
DATE: DECEMBER 11, 2012
SUBJECT: NOTICE OF COMPLETION
BOAT LAUNCH FACILITY IMPROVEMENT
PROJECT NO. 4237
Recommendations
1. Approve Contract Change Order No. 1 to Fiber Docks in the amount of
$27,973.88
2. Approve final contract change order to Reyes Construction for $49,771.00
3. Authorize the use of available unallocated revenue funds in the amount of
$26,752.76
4. File the Notice of Completion with the County Recorder
5. Release all retention monies 35 days after the filing of the Notice of
Completion
Background
The California Department of Boating & Waterways (DBAW) awarded the City a
$3,000,000 grant to construct the La Laguna Resort & Boat Launch Facility Project. On
March 8, 2011 the City Council approved the purchase of the precast concrete
components, boat dock components and the purchase of rip -rap (rock slope protection)
in the amount of $513,968.70. On March 22, 2011 City Council approved the Haul
Route Application for the transport of 170,000 cubic yards of imported fill from a 40 acre
borrow site located at the east end of Lake Elsinore at the terminus of Malaga Road.
On May 24, 2011 the City Council approved the Environmental Services Agreement
with HDR Engineering, Inc. to perform the required biological pre- disturbance activities,
biological resources monitoring during construction activities and the Pechanga Band of
Luiseno Indians performed archaeological monitoring during any ground disturbance
AGENDA ITEM NO. 7
Page 1 of 6
Page 2
Notice of Completion
December 11, 2012
activities. On June 28, 2011 the City Council approved the award of the construction
contract to Reyes Construction, Inc.
Discussion
All construction for the boat launch has been completed and the City has beneficial use
of the project. There were two change orders processed to the docks themselves, the
first was a change order issued to Fiber Docks to add High Density Poly Ethylene
(HDPE) and cleats to the outside of the docks. This improvement added flexibility to
utilize the outside of the docks for mooring and provides protection from boat impacts.
In addition, change order number one also added security gates to the end of one set of
docks to secure an area for the police patrol boats. In early June, the City requested
change order number two, overtime compensation for the manufacturer to insure the
installation of the docks before the boat launch grand opening scheduled for July, 4,
2012. These change orders was in the amount of $27,973.88
On January 24, 2012 the City Council awarded Reyes Construction, Inc., a contract
change order to perform earthwork for the wetlands enhancement project to promote an
ecological approach to restoring the beneficial uses of the Lake which is part of the
environmental mitigation requirements of the boat launch. A subsequent change order
in the amount of $49,771.00 was issued due to the soft and saturated bottom conditions
which altered the contractor's methods to perform the required work.
On June 29, 2012 Reyes Construction, Inc. completed the boat launch improvements
according to the approved plans and specifications.
Fiscal Impact
The project budget is $8,607,455.00 and the funding sources are shown below:
General Fund $ 315,120.00
Fund 221 -Park CIP $ 313,882.00
RDA Tax Increment $ 450,000.00
RDA Bond Issue for Construction $4,528,453.00
Grant -CA Department of Boating &Waterways $3,000,000.00
$8,607,455.00
The following are total expenditures:
Design and Planning and Consulting Services $ 1,016,161.00
Environmental Study & Monitoring, Soils Reports and
Other Professional Services and Consulting $ 368,314.00
Legal Fees $ 13,731.00
Construction Administration $ 80,533.00
Construction Services & Material $6,959,846.88
City Labor /Inspection & Other Administrative Costs $ 160,496.88
Page 2 of 6
Page 3
Notice of Completion
December 11, 2012
Other
Total Construction Short Fall
$ 35,125.00
$8,634,207.76
$ 26,752.76
The construction shortfall of $26,752.76 was a result of changes to the project scope to
include the environmental mitigation, extension of the wading barrier and changes to the
fiber docks.
Prepared by: Peter Ramey 6?4,,,,
Project Engineer
Approved by: Ken Seumalo Ki ks
Director of Public Works
Approved by: James Riley
Director of Adnpistrative Services
Approved by: Grant Yates
City Manager
Attachments: Vicinity Map
Notice of completion
Page 3 of 6
RECORDING REQUESTED BY
AND WHEN RECORDED MAIL TO:
Name City of Lake Elsinore
Street 130 S. Main Street
Address
city a stale Lake Elsinore CA 92530
NOTICE OF COMPLETION
Notice is hereby given that:
1. The undersigned is owner or corporate officer of the owner of the interest or estate stated below in the property hereinafter described:
2. The full name of the owner is City of Lake Elsinore
3. The full address of the owner is1 S Main Street
4. The nature of the interest or estate of the owner is in fee.
(If Other han fee, strike 'In Fee' and insets for example,'purcpaser under cor of purch"I" or'lear"")
5. The full names and full addresses of all persons, if any, who hold title with the undersigned as joint tenants or as tenants in common are:
NAMES ADDRESSES
6. A work of improvement on the property hereinafter described was completed on June 29 2012 . The work done was:
Construction of new boat launch facility, with ancillary improvements.
7. The name of the contractor, if any, for such work of improvement was Revac CTtinn, Inn , 1483 Snf )th Signal Driv
Pomona CA 91766 -3844
(If no contractor for work of improvement as a whole, insen'nom') (Date of Conbrcl)
8. The property on which said work of improvement was completed is in the city of Lake Elsinore
County of Riverside State of California, and is described as follows: Construction of a New Boat Launch Facility
and ancillary Improvements'
9. The street address of said property is 32040 Riverside Drive
(if no turner address has been officially assigned, Insert 'hood')
Dated: December 11, 2012
signature of owner of rumored officer of owner
City Clerk City l5ftbi rf't1sIii8Ple
VERIFICATION
1, the undersigned, say: I am the Director of Public Works / City Engineer the declarantof the foregoing
(TresideN O("Manager of' A farmer or'0wnerur etc.)
notice of completion; I have read said notice of completion and know the contents thereof; the same is true of my own knowledge. I
declare under penalty of perjury that the foregoing is true and correct.
Executed on Derpmher 3 .20 12 , at I aka Elsinore , California.
goat. of smother //� (city wherefig/uurrreee))r-
V` p�
(personal signature at the individual who is swearing that the cautious of the notice of
completion are true)
Page 4 of 6
Page 5 of 6
Regional Vicinity
FIGURE 1
ONE CO MPANY Afa, So(nrianS - Lake Elsinore Boat laouh Nehahildaaon I Cay of lake Elsinore I atrial Study /AND
250 500 1,000 Feet City of Lake Elsinore
' ' I ' ' ' I Campground Launch Facility
Page 6 of 6