HomeMy WebLinkAboutItem No.36TO: ` FROM: DATE: CITY OF LAKE ELSINORE REPORT TO CITY COUNCIL Mayor and City Council Ron Molendyk, City Manager July 13, 1993 SUBJECT_: CHANGE ORDER NO. 3 FOR STREET IMPROVEMENT TRAFFIC SIGNALS, AT GRAND AVENUE AND LINCOLN STREET, AND GRAND AVENUE, ROBB,ROAD AND LAKESHORE DRIVE, WEST LAKE ELSINORE, CFD 88 -3 BACKGROUND The West End Community Facilities District 88 -3 was formed to finance construction of public improvements in support of area developments. Some of the improvements include storm drains, water and sewer lines, street improvements, traffic signals, fire station, parks, water reservoirs and sewer and water pump stations. Funds for the CFD are provided by the sale of bonds based upon the value of the property to be improved. These bonds are paid off over a number of years by the property owners within the boundary of this CFD 88 -3. The contract for the Street Improvement Traffic Signals being constructed by the CFD was awarded to Sierra Pacific Electrical Contracting on November 12, 1991, by the City Council. Construction of the improvements began in January, 1992, and were completed in April, 1993. Change Orders Nos. 1 and 2 were approved by the City Council for $5,033.09. ANALYSIS This Change Order No. 3 provides for repairs to the existing facilities that were damaged by persons unknown, and changes in the Scope of Work that were made after the Bids had been received by the City of Lake Elsinore. Item nAll (Replace Damaged Traffic Loops.) This work is for the replacement of the traffic detector loops on Grand Avenue at Lincoln Street that were damaged during the winter storms. Increase Contract Amount By $1,060.00 Item uBu (Replace Damaged Pedestrian Signal.) the replacement of a Pedestrian intersection of Robb Road and Lakesho damaged by persons unknown. Increase Contract Amount By FISCAL IMPACT This Change Order will increase the contract by is a breakdown of the current project costs for This work is for Signal at the re Drive, that was $742.48 $1,802.48. Below this contract. Contract Amount (11/12/91) $184,241.00 Sum of Previous Change Orders 1 & 2 5,033.09 Amount this Change Order No. 3 1,802.48 Revised Contract Amount 191,076.57 3� PAGE L OF Mayor and City Council July 13, 1993 Page two RECOMMENDATION 1. Authorize the amendments to the contract for $1,802.48 for the additional facilities /repairs on the Street Improvement Traffic Signals for CFD 88 -3. 2. Authorize the City Engineer to process and execute the appropriate change order documents. PREPARED BY: David Kircher, Associate Civil Engineer APPROVED BY: 1 Services APPROVED FOR LISTING BY: Ron Molendtk, City Manager AGENDA ITEM NO. ^� PAGE OF 3 i SENT BY: WEST LAKE ELSINORE CFO 88.3 CRY OF LAKE ELSINORE CCN9TR1JC7ON CHANGE ORDER CHANGE ORDER a 3 6 -16-93 ;11 :51AM ; PAUL A MOOTE-4 Distribution to: CRY OF LAKE ELSINORE. 81ERRAPACIFIC x PAUL A MOCITE 8 ASSOC. X MICKEYCAPUANO x 19096742392E 2 PROJECT: PHASE 0, STREET IMPROVEMENTS INITIATION DATE: February, 1893 TRAFFIC SIGNALRATION, GRAND AVENUE CONSTRUCTION MANAGER'S CONTRACTOR: Storrs Peelfle PRQECTNO: 100992.11.1 2542 Avalon Stroat CONTRACT DANE: December 10, 1091 Riverside, CA 92500 CFDACOOUNTNO: 255. 4064.420 Tel: (714) 784.1410 You are directed to make the following changes In this Contreet: Add the following to contract as Change Order No. 3: A. Replace damaged loops aid pedestrian, signal at Lump Sum Coat Itereess: 1,802.48 Total 1,802.48 Not va8d until Signed by the City of Lake Elainwo, the Construction Manager and the Contractor. Slonaturo of :he Contractor IndIcawo agroement he- ewl:h, including anv adluatrnant in the Contract Sum or the Contract Time. The original Contract Sum was ........ .... _ ... _ ........................ ............................... ...... I ....... . S 184,241.00 Net Change by previously authorized Change Orden No. t 8 2 .......... .. ........ _ .,.„ ..,.........._.__._ »....... $ 5,033.09 The Contract Sum prior to this Cfargs Order was .......... ......_........... 8 189,274.09 The Contract Sum will be ino eased by INS Change Order No. 3 ............ _. ............. ... ........................ __... $ 1,802.48 The new Contract Sum Ind-u- 1ng this Change Order will be ............... _... ........................ _.._.._..................... $ 191,078,67 The Date of :tubstantia! Completion as of the oats of this Change Order .._._.............................................. Project Complete Recommended: PAUL A. MOOTE 8 ASSOCIATES, INC. 57 Brookhoi ow Drive, Santa Ana, CA 02705 8/9/03 By Polar M. 900110 DATE Project Manager Agreed To: SIERRA PACIFiC 2542 Avalon Street, Riverside, CA 92509 BY DATE Authorized: CRY OF LAKE ELSINORE, CFD 88.3 130 South Main Street, take Elsinore, CA 92630 _ AGENDA ITEM NO. 3_ . TE PA OF 3 I