Loading...
HomeMy WebLinkAboutItem No.6CITY OF LAKE ELSINORE REPORT TO TEE CITY COUNCIL TO: Mayor and Counciimembers FROM: Ron Molendyk, City Manager DATE: September 28, 1993 SUBJECT: NOTICE OF COMPLETION FOR LARESHORE DRIVE / ROBB ROAD INTERSECTION IMPROVEMENTS As part of the 1991 -92 Capital Improvement Program, the intersection of Lakeshore Dr. and Robb Rd. was reconstructed to form a "T" intersection with the'new' extension of Grand Avenue. The project included the removal of an underground storage tank, the construction of storm drain inlets and pipe, and the construction of street improvements. The contract for this work was awarded to R.A Ruiz Construction on October 8, 1991. Construction began in December of 1991. DISCUSSION During the course of construction, several change orders were issued to cover unexpected work. The change orders are summarized below. C. 0. No. Description 1. 1 After the underground storage tanks were-removed, - Riverside- County Health Department required unexpected testing and borings. Also, extra costs were incurred to increase the safety of the traffic control and detour through the construction area. The contractor was asked to decrease the time required to complete the first phase of the project by working overtime. Total cost: $32,289.13. 2 Extra conduit was installed for street lights. Extra striping was installed for the second phase traffic control. Two manholes had to be reconstructed. Changes had to be made to the storm drain due to conflicts with the waterline. Total cost: $17,449.44. 3 In order to complete the project, the contractor first had to repair damage to his work site caused by G.T.E. trenching operations. Another manhole had to be reconstructed. Some failed areas in the road had to be removed and replaced. The school entrance was also redesigned to provide a safer and more convenient pedestrian access. However, some, items were deleted from the contract and some quantities were lower than shown in the bid schedule. This resulted in a decrease of $32,881.74 from the original contract bid. Total decrease in cost: $9,086.52. The project is now complete and has been accepted by the City. C : \rp51 \dots \tim \agenda \lakerob4.rpt AGENDA ITEM NO. PAGE-1—OF—ii- Mayor and Councilmembers • September 28, 1993 Page Two FISCAL IMPACT Below is a summary of the project costs for the Lakeshore Drive / Robb Road Intersection Project: Improvement Proj P Contract Amount $305,187.70 ' Sum of Change Orders 44,310.51 Final Contract Amount $349,498.21 RECOMMENDATION 1. Accept the project as complete.. . 2. Request that the Mayor sign the Notice of Completion. 3. Authorize the City Clerk`to record the Notice of Completion within ten days. APPROVED BY: APPROVED FOR AGENDA LISTING: r C : \wp51 \docs \tim \agenda \lakerob4.rpt AGENDA ITEM N0. ..Yc PAGE-A--OF-1—