The RDA /City owns the building at 183 North Main Street known as
the "Methodist Church". Staff has reviewed and determined what
improvements are needed to facilitate utilization of the first
floor of the building only. Staff has checked state and local laws
concerning unreinforced masonry and at,this time no up- grading is
required.
DISCUSSION
Listed below are cost estimates to clean -up and repair the
building. These costs are based on the RDA /City acting as the
owner /builder contractor. The RDA /City will obtain a significant
number of bids on each area of the work.
The following are estimated costs and work to be performed:
• Plan and Specs /Design Fee
$
10,000.00
• Sound System
$
5,000.00
• Sandblast & Stucco Exterior
$
11,000.00
• Solid Block Windows
($65.00 each x 14)
$
1,000.00
• Stucco Trim Side & Rear Windows
($100.00 x 14)
$
1,400.00
• Remove Existing Roof & Reroof
$
9,000.00
• Three Heat Pumps /Air Conditioning
$
16,000.00
• Plumbing for Restroom
$
12,000.00
• Temporary Fence
$
3,500.00
• Paint Exterior Wood Windows & Doors
$
3,000.00
• Concrete Block Doors & Windows
$
3,000.00
• Electric
$
25,000.00
• Paint and Patch Interior
$
8,000.00
• New Handicap Ramp
$
2,000.00
• Resurface Entry Stairs
$
2,000.00
• Interior Framing and Drywall
$
5,000.00
• New Doors & Bath Partitions
$
9,000.00
• Glazing Cover over Windows
$
6,000.00
• Chime System
$
12,000.00
• Landscaping
S 5.000.00
$148,900.00
The following is work that needs to be completed, however, cost
estimates are unavailable at this time.
• Repair the Stain Glass Windows
• Sound Deadening Material for the Walls
• Refinishing the Floors and Repairing
• Carpet Meeting Rooms
• Security System
• Refinishing Pews
• Rebuilding Stage
The above list is the Scope of Work which needs to be accomplished
and what staff is proposing.
A :{t DA ITEM N0.
REPORT TO REDEVELOPMENT AGENCY
OCTOBER 26, 1993
Page 2
SUBJECT: 183 NORTH MAIN STREET
FISCAL IMPACT
Administrative Services Director has indicated that the
rehabilitation of the building is a funded Redevelopment Agency
project and $200,000 is the budgeted amount.
• y! �!_ s •
It is recommended that the Redevelopment Agency approve the Scope
of Work and direct staff to solicit bids, approve and execute all
contracts for the rehabilitation to a maximum amount of $200,000.00
for fiscal year 1993 -94.