HomeMy WebLinkAboutItem No. SA7CITY OF LAKE ELSINORE
REPORT TO THE REDEVELOPMENT AGENCY
TO: Redevelopment Agency
FROM: Ron Molendyk, Executive Director
DATE: October 24, 1993
SUBJECT: Lakeshore Drive Bridge
The City of Lake Elsinore is constructing the Lakeshore Drive
bridge and the San Jacinto River Channel. Cost of both projects is
anticipated at $4,845,000. Eighty percent of the cost of the
bridge construction and all associated improvements is being
reimbursed to the City by Caltrans from federal set -aside bridge
construction funds. This is expected to approximate $2,432,000.
Construction of the Lakeshore Drive bridge requires changes and
modifications to all utilities, storm drains, roadway approaches
and other contiguous facilities. The cost of those modifications
which are necessary for bridge construction are also reimbursed by
the federal government at 80 percent.
A set of preliminary construction plans for the bridge was sent to
EVMWD to review because a number of their facilities will be
affected. The sewer lift station on the east side of the bridge
must be relocated. EVMWD requested the project enlarge the site,
construct a block wall around the perimeter, install a sliding gate
and pave the entire site. Additional costs are estimated to
approximate $48,000. We have designed these changes into our plans
because EVMWD's requests meet City standards and would upgrade the
appearance of the site.
A 30 inch water line and a 16 inch sewer line run parallel to the
bridge and are buried in the ground. These must also be relocated.
They will be reconstructed 12 feet deeper to a position 16 feet
below the bottem of the finish grade of the channel. Also, they
will be protected by armor rock on both sides of the channel and a
1 foot thick concrete slab located below the armor rock and above
the pipe. Our design engineers feel strongly that this is
sufficient protection for both pipes.
EVMWD has reviewed the plans. They have responded by requesting
the pipes be installed in steel sleeving the full length of the
channel, and that 2 additional 30 inch butterfly valves be
installed in the water line. Additional cost of these changes is
estimated at $83,000.
The design engineers for the project feel the changes are
unnecessary and have warned us that Caltrans may not approve
reimbursement of these costs. In addition, they have not been
successful in convincing EVMWD to withdraw their requests.
FISCAL IMPACT
Cost of these changes is estimated to approximate $83,000. Without
federal reimbursement of $66,400, the RDA will have to fund the
entire amount.
AGENDA ITEM NO.
PAGE/— OF
Report to the Redevelopment Agency
October 24, 1993
Page 2
Approve a potential extra cost of $83,D00 to encase the water and
sewer lines in steel casing and add two butterfly valves to the
water pipeline crossing the San Jacinto River at the Lakeshore
Drive bridge.