HomeMy WebLinkAboutItem No. SA4CITY OF LAKE ELSINORE
REPORT TO THE REDEVELOPMENT AGENCY
TO: Redevelopment Agency
FROM: Ron Molendyk, Executive Director
DATE: May 11, 1993
SUBJECT: San Jacinto River Channel and
Lakeshore Drive Bridge
BACKGROUND
The Redevelopment Agency (RDA), in conjunction with the Federal
Highway Administration, has funded the replacement of the Lakeshore
Drive Bridge over the San Jacinto River. In order to complete the
bridge, the RDA has also funded the construction of the San Jacinto
River Channel between Lakeshore Drive and the Lake Inlet Channel.
On March 10, 1992, a contract was awarded to Mohle, Grover &
Associates (MGA) in the amount of $58,000 to design the roadway and
cross - sections for Lakeshore Drive bridge.
On November 10, 1992, after discovering that the RDA had to. design
and construct the San Jacinto River Channel, a change order in the
amount of $114,618 was awarded to MGA to manage the Bridge Project
and the Channel Project, secure the Right -of -Way for both projects,
and design a new Lakeshore Drive detour roadway. This work is
substantially complete.
DISCUSSION
During January and February of 1993, heavy rains came to Lake
Elsinore and the San Jacinto River watershed which produced enough
water to raise Lake Elsinore from elevation 1228 to elevation 1258.
When the rains and runoff subsided, and the lake level stabilized,
water backed up into the channel all the way through both project
sites to the Interstate 15 bridges. Six feet of water now lies
above the finish elevation of the San Jacinto River channel.
A wet channel, especially with 6 feet of still water, 'forces
numerous design and construction changes in the project:
-The reinforced concrete baffled spillway can be discarded. It is
far too expensive to build down to elevation 1220 in a wet
environment. Instead, steel sheet piles will be driven into the
ground to create a spillway at elevation 1252 and they will be
armored with large rock. The concrete spillway can be
constructed in the future should the lake level fall below 1240.
-An earthen dam must be built just below the spillway to keep the
lake water from flowing into the channel during construction.
- Pumping must be included in the project to remove the existing
water from the channel and to remove the continuous flow that
persists from the Railroad Canyon dam.
All of these changes requires our project engineers to incorporate
changes in the plans and specifications to show a new channel
profile and to provide for construction in a wet channel. These
include:
-Re -survey and create new topographic contours $ 6,800
- Prepare new cross sections for the entire length 4,380
- Design temporary dike and dewatering program 7,620
-Re- design the spillway with sheet piles and rock 12,460
- Recalculate project quantities and cost estimates 5,600
- Revise bidding documents and specifications 5,360
- Prepare bid advertisement, addendum and meetings 81,340
AGENDA IT0., %'C.,:
PAGE C.
Report „to Redevelopment Agency
May 11, 1993
Page 2
While preparing the design for the bridge foundations and the
channel transitions it was discovered the bridge realignment places
the bridge foundation pilings directly over the existing water and
sewer lines in Lakeshore Drive. These must be relocated away from
the bridge footings and below the level of possible channel scour.
Cost for design is $ 9,640.
Finally, EVMWD requires major modifications and upgrade to their
Sewer Lift Station located immediately east of the site. These
include perimeter block walls, site paving, lighting and an
automatic sliding entry gate. Additional design cost is $ 9,640.
FISCAL IMPACT
Fiscal impact of these additional costs amount to $74,360.
Sufficient funds remain in the project to cover these costs.
Despite the design changes caused by high water levels, total costs
for all design services are approximately 7 percent of the
engineer's project estimate.
Approve an amendment to the contract with Mohle, Grover &
Associates to increase their fee by $74,360. Total contract amount
will be $246,978.
PREPARED BY:
APPROVED BY:
APPROVED FOR
AGENDA LISTING
AGENDA ITEM NO. � 4
PAGE OF=
A.
Develop Project Work -a -Round Plan to Mtigate HIGH LAKE LEVEL.
e.g., Temporary Dike, Rock Spillway, Pumping, & River Diversion.
Principal
8
HRS
Senior Engineer
32
HRS
Design Engineer
16
HRS
CARD Operator
32
HRS
Clerical
4
HRS
@
$ 140
$
1,120
@
$ 110
$
3,520
@
$ 85
$
1,360
@
$ 45
$
1,440
@
$ 45 $ 180
SUBTOTAL
$
70620
B. Re -Survey River Channel Topography: Survey Date: February 13, 1993.
Establish East Channel Right -of -Way Line and Cross - Section River Bed from
Lakeshore Drive South.
Field Survey Crew: (3 days) $ 3,600
(By Robert Wada & Assoc.)
Office: Data Point Conversion to Contours. $ 3.200
SUBTOTAL $ 6,800
C. Prepare Cross - Section Plan Sheets
The Eight (8) Cross - Section Plan Sheets Prepared By Black & Veatch were
Revised to Account for a Changed Existing Ground Line and Revised Top of
Channel Elevations.
Principal 3 HRS
Senior Engineer 4 HRS
Design Engineer 16 HRS
CADD Operator 32 HRS
Clerical 48 HRS
@
$ 140
$
420
@
$ 110
$
440
@
$ 85
$
1,360
@
$ 45
$
1,440
@
$ 45 $ 2.160
SUBTOTAL
4,380
D. Recalculate Project Quantities for Rock Slope Protection, Rock Spillway, Access
Ramp, and Earthwork.
Senior Engineer 4 HRS @ $ 110 $ 440
Design Engineer 24 HRS @ $ 185 $ 4,440
CADD Operator 16 HRS @ $ 45 $ 720
SUBTOTAL $ 5,600
2 AGENDA ITEM NO 4
.doc
PAGE OF elscontr
0
E.
F4
G.
L
Prepare Plans for Rock Spillway and Channel Access Ramp.
Principal
8 HRS
@
$ 140
$ 1,120
Senior Engineer
24 HRS
@
$ 110
$ 2,640
Design Engineer
60 HRS
@
$ 85
$ 5,100
CADD Operator
80 HRS
@
$ 45 $ 3 .600
100
HRS
SUBTOTAL
$12,460
Prepare Bidding Documents and Specifications for Revised Project.
Principal 3 HRS @ $ 140 $ 420
Senior Engineer 40 HRS @ $ 110 $ 4,400
Clerical 12 HRS @ $ 45 $ 540
SUBTOTAL $ 5,360
Pre -Bid Engineering Services for "San Jacinto River Channel Improvements"
Project.
• PRE BID MEETING $ 420
• PREPARE ADDENDUMS NO. 1,2,3 $ 5,280
• BID OPENING $ 440
• SUNDAARY OF BID RESULTS $ 22.200
REFERENCE CHECK AND $ 8,340
RECOMMENDATION.
Relocation of 30" Water Line and 16" Sewer Line for EVMWD.
Principal
8
HRS
@
$
140 $ 1,120
Senior Engineer
24
HRS
@
$
110 $ 2,640
Design Engineer
56
HRS
@
$
85 $ 4,760
CADD Operator
100
HRS
@
$
45 $ 4,500
Clerical
12
HRS
@
$
45 $ 540
Survey
4
MS
@
$ 150 $ 600
SUBTOTAL $14,160
3
AGENDA ITEM NO
(,j ft: el ' .da
'1
PAGE — OF
J. Modifications to Sewer Lift Station Including Fencing, Site Paving, Lighting, and
Entry Gate.
Principal
Senior Engineer
Design Engineer
CARD Operator
Clerical
4 HRS
@
$ 140
$
560
16 HRS
@
$ 110
$
1,760
48 HRS
@
$ 85
$
4,080
60 HRS
@
$ 45
$
2,700
12 HRS
@
$ 45 $ 540
SUBTOTAL
$
9,640
TOTAL CONTRACT CHANGE ORDERNO.2 REQUEST:
TOTAL: $74,360
Please give me a call if you have any questions regarding this change order.
Respectfully submitted,
MOHLE, GROVER & ASSOCIATES
R Henry Mohle, P.E.
President
tf±W�
4 AGENDA ITEM NO.
t.da
PAGE --5— OF