HomeMy WebLinkAboutItem No. 37CITY OF LAKE ELSINORE REPORT TO THE CITY COUNCIL TO: Mayor and Councilmembers FROM: Ron Molendytt City Manager DATE: May li, 1993 SUBJECT: CHANGE ORDER NO. 1 FOR GRAEAM AVENUE LANDSCAPE BACRGROIIND The contract for the Graham Avenue Landscape project was awarded to Gali Landscape and Maintenance Company on March 23, 1993 by the City Council for $51,352:00. Construction of the improvements began in April of 1993. The project was designed such that the City would install the improvements and the individual property owners would provide irrigation and maintenance. Only those properties that were occupied at the time that the plans were prepared were included in the scope of the project. In order to construct the improvements and connect to private water services, staff obtained signed Right of Entry forms from all property owners. After construction started, staff was.directed to include all parcels in the scope of the project in order to have the landscaping and irrigation be continuous from Langstaff Street to Mohr Street. This requires the addition of ten vacant parcels that were originally excluded. ANALYSIS Staff was successful in obtaining permission to connect to adjacent private water meters for five parcels. There are four parcels that the adjacent property owners refused to provide water for their neighbor's frontage. Two parcels at the northeast and southeast corners of Graham Avenue and Scrivener Street are vacant and do not have existing water meters. They are owned by separate parties. In order to include these two parcels in the project, the City will have to purchase new water meters from Elsinore Valley Municipal Water District. The cost of 3/4" meters is approximately $5,600.00 each. Two more vacant parcels located at the northeast corner of Graham Avenue and Lindsay Street are owned by the same party. There was an existing water meter at this site with number 124266 stamped on the cover. The property owner gave the City permission to use this meter for irrigation of the parkways in front of both lots. When City staff contacted Elsinore Valley Municipal Water District to unlock the meter and restore service, Water District personnel arbitrarily removed the meter. They claim that there is no record of that meter so someone will have to purchase a new meter. The cost of this meter is approximately $5,600.00. The extra landscaping and irrigation to be constructed by the contractor will be added at the contract unit prices. This work includes irrigation for 27 tree wells in front of Elsinore Middle School, and 5,280 square feet of additional irrigation and groundcover in the parkways. c: \wp57 \docs \tim \agenda \gramacap.rpt AGE D- _.. ..... _._.3 PAGE OF 1 - Mayor and Councilmembers May 11, 1993 Page Two FISCAL IMPACT Below is a summary of the Landscape Project: CIP Project Budget Contract Amount Sum of Previous Change Amount of Change Order Revised Contract Amount Water Meters (EVMWD) project costs for the Graham Avenue $90,000.00 51,352.00 Orders 0.00 No. 1 11,951.00 $63,303.00 $16,800.00 Since the water meters are a facility that will directly benefit the property owners, the City can put a condition on future development that the owner reimburse the City for the cost of the water meter and that the owner take over the cost of watering and maintaining the landscaping in the parkway. 1. Authorize the amendment to the contract with Gali Landscaping and Maintenance Co. for $11,951.00 for the extra irrigation and landscaping. 2 Authorize the purchase of three water meters from Elsinore Valley Municipal Water District at a cost of $16,800.00. 3. Authorize the Mayor to process the appropriate Change Order documents. PREPARED BY: Timothy M..Shell, Contract Administrator APPROVED BY: APPROVED FOR AGENDA LISTIN c: \wp57 \dots \tim \agenda \9rawcap.rpt A CITY OF LAKE ELSINORE 130 SOUTH MAIN STREET LAKE ELSINORE9 CALIF. 92330 PHONE (714) 674 -3124 CNAMPE ORDER Na: Ona (11 PRO ✓ECT CHANor ORDER OA7F• -lay 5. 1993 oRne(NArW eY:_City of Lake Elsinore ►MIS C010q 0004► d /A't.VAIK M CITY PRO ✓ECT NQ: 910 Q000463-40 20 9037 PRO ✓ECT TITLE: -GRAHAM AVFNUF 1 ANf1SCAP� FROM f AKFSHORF nRT VF TO LANGSTAFF STREET AVAYORIZE0 BY: CONTRACT AWARDED r0: GALI LANSCAPING AND MAINTENANCE 17807 Bullock Street Encino, CA 91316 Ab4?r AWARDED. —March 23. 1993 SCHEDULED CONPLE7/ON OATFY_ i6 i aS3 7=1. AMOUNT OF CONTRACT CONTRACTOR /S AUTHOR17E0 r0 MAKE THE M1.40W /N6 CAMMSr Revise bid items 2, 3 and 8 from Lump Sum to Square Foot by dividing the Lump Sum price by the Square Footage shown soil preparation and also for hydroseed. Unit price will be $0.13 per square foot for clearing and grubbing (Item #2), $1.02 per square foot for irrigation system (Item #3) and $0.14 per square foot for 90 -day Maintenance (Item #8). B. Item Z- 3 5 8 C Increase bid quantities to cover an extra 5,280 ri square feet as shown: Clearning - t � Unit Price Amount a g 0980 SF TOM $-T,-727.40 Irrigation Sytem Soil Preparation /Fine Grade 20,980 SF 20,980 SF $1.02 $0.25 21,399.60 Hydroseed Turf 20,980 SF $0.20 - 5,245.00 4,196.00 90 -day Maintenance 20,980 SF $0.14 2,937.20 Add irrigation for tree wells for 4 automatic valves and install in front of Elsinore Middle School, 4 exchange 4 manual valves New Bid Item No. 9, Additional station automatic controller Irrigation,Lump Sum,$2,881.80. ::�:,at 800 W. Graham, 4M $11,951.00 RACrWILL RE (INOREASEOI (OECOPASA-nI ev rui FPS C%2VM0rPD4I00 07LL BE (INCREASEOJ REVIEWED Or. PROJECT ENGINEER Clrr ENGINEER O/R.OEVELOP. SERVICES 0/RECTOR OF FINANCE /ow♦ 0Y- 3 1�5 Mrs AAfcL. rH /S CHANCE ORDEOI —$63, 303.00 /N/77ALS DATE AfPROVEO BY: OAT6 �►. d. s s a3 - G s--6 _y CONTRACTOR CITY CLERK ITEM PACES OF