Loading...
HomeMy WebLinkAboutItem No. 33CITY OF LAKE ELSINORE REPORT TO THE CITY COUNCIL TO: Mayor and City Council FROM: Ron Molendyk, City Manager DATE: March 23, 1993 SUBJECT: 'CHANGE ORDER NO. 6 FOR THE ROBB ROAD BOOSTER PUMP STATION IMPROVEMENT ON ORANGE GROVE WAYr CFD 88 -3. BACKGROUND The West End Community Facilities District 88 -3 was formed to finance construction of public improvements in support of area developments. Some of the improvements include storm drains, water and sewer lines, street improvements, fire station, parks; water reservoirs and sewer and water pump stations. Funds for the CFD are provided by the sale of bonds based upon the value of the property to be improved. These bonds are paid off over a number of years by the property owners within the boundary of this CFD 88 -3. The contract for the Robb Road Booster Pump Station Improvements being constructed by the CFD was awarded to S.C. Engineering, Inc., on September 24, 1991 by the City Council. Construction of the improvements began in October, 1991. Change Orders Nos. 1, 2, 3, 4, and 5 were approved by the City Council for $57,996.32. ANALYSIS This Change Order•No. 6 provides for additional facilities, upgrade of facilities, and time delay reimbursements for the Robb Road Booster Pump Station that were made after the bids had been received by the City of Lake Elsinore. Item IPA$#: Sun Shade Roof Panels. The documents specifying the roof panels were not correct. At a meeting with the Contractor and the Civil Engineer, it was agreed that a heavier panel would be required. The increase in contract amount for this item is $4,490.00. Item INS": Electrical Re- Wiring and Troubleshooting. After removing the old existing pumps, portions of• the existing electrical system.that operate the pump were found inadequate for the two new, more powerful pumps. This item is to troubleshoot and re -wire the existing system for the new pumps. This type of work is always completed on a time and materials basis, as the full extent of the work is not known until all electrical components. have been inspected and tested during the actual construction phase of the project. The increase in the contract amount for this item is $2,275.00. Item 11c": Painting. This item..is for additional painting of the pump area and the electrical panels that was not included on the original plans, yet had to be done. The increase in the contract amount for this item is $1,848.00. Item I'DIR: Replace Conduit. During construction, some of the existing underground conduit had to be replaced with new conduit to service the updated pump station. This was done by a different contractor. The increase in the contract amount for this item is $475.00. AGENDA ITEM NO. J� PAGE .1 OF Mayor and City Council March 23, 1993 Page two Item „E": Time Extension Reimbursement. This item is to cover "extended overhead" costs to the Contractor due to the many delays in the project time schedule that were not the contractor's responsibility. This cost was calculated in accordance with the Eichleay Formula• and was agreed to by the Contractor, the CFD Consortium and Paul A. Moote & Associates, Inc. This project experienced three major delays that were not the responsibility of the Contractor. The first delay was in the installation of a 12" water line in Lincoln Street.. The second delay was caused by excess pressure by the'new pumps to the homes in the area. - This caused -a delay while pressure reducing valves were installed in 320 existing homes. The. third delay was caused by replacement of the existing pump cans. This work was not anticipated. The original contract was for 125 days. This project has been extended an additional 352 days by events and circumstances beyond the Contractor's control The increase in the contract amount for this item is $18,750.00. FISCAL IMPACT This Change order will increase the contract amount by $27,838.00 Below is a breakdown of the. current project costs for this contract'. Contract Amount (9/24/91) $157,000.00 Sum of previous Change Orders 1,2,3,4,5 57,996.32 Amount this Change Order No. 6 27,838.00 Revised Contract Amount 242,834.32.: RECOMMENDATION 1. Authorize the amendments to the contract for $27,838.00 for the additional facilities on the Robb Road Booster, Pump Station Improvements for CFD 88 -3. 2. Authorize the City Engineer to process and execute the appropriate change order documents. PREPARED BY: k 1'141 "C � David Kircher, Associate Civil Enq neer APPROVED BY: APPROVED FOR AGENDA LISTING AGENDA ITEM N0. 33 PAGE Z. OF WEST LAKE ELSINORE CFD 88.3 Distribution to: CITY OF LwE ELSINORE CITY OF LAKE ELSPIORE X CONSTRUCTON CHANGE ORDER PAM A.MOOTEaASSOC. X S.C. ENGINEERING, INC. z CHANGE ORDER A 6 MICKEY CAPUANO X PROJECT: Robb Road Pump Station Improvements CONTRACTOR: S.C. ENGINEERING, M. P.O. Box 10194 Torrance, CA 90505 You are directed to make the following changes in this Contract: item 09, Sunshade Roof Panels hem 'B', Electrical Re-wring hem 'C', Painting INITIATION DATE: January 1, 1993 CONSTRUCTION MANAGERS PROJECT NO: 100.392.16 CONTRACT DATE: September 24, 1991 Increase: $4,490.00 Increase: Increase: $2.275.00 $1.848.00 hem 'D', Replace Conduit Increase: $475.00 hem -E-. Time Extension Increase: $18,750.00 Add all of the above hems to contract as hem No. 20, Change Order No. 6, Total item Amount: $27.838.00 Not valid until signed by the Gty of Lake Elsinore. the Construction Manager and the Contractor. Signature of the Contractor Indicates agreemerd herewith including any adjustment In the Contract Sum or the Contract Time The original Contract Sum was $ 157,000.00 Net Change by previously authorized Change Orders (No. 1.43.4 b 5) ..... »___ »..»..- »».... »- .»..__ »..... $ 57,996.32 The Contract Sum prior to this Change Order was »— .------- _-- -_^ — -- ^ -•^- °- $ 214,996.32 The Contract Sum win be increased by this Change Order (No. 6) $ 27.838.00 The new Gorman Sum including this Change Order will be »...__..._._.. -_-..» - »......... $ 242,834.32 The Date of Substantial Completion as of the date of this Change Order Is - »» - -•- --- -••• July 15, 1992 Recommended: PAULA. MOOTS 8 ASSOCIATES, INC. �Zmq' w Drive, Any,, CA 92705 f,414 % elA 3 Peter a*I o . - DATE Project Manager Agreed To: S.C. ENGINEERING. INC. P.O. Box 10194 - Torrance, CA 90505 DATE Authorized: CRY OF LAKE ELSINORE. CFD 88.3 130 South Main Street Lake Elsinore, CA 92530 2,TE AGENDA ITEM NO. PAGE C OF • ST:ARFiELD 8 PAYNE ATMIL14ZY3 AT LAU' r. o. doff sec 3UrM X00 1213' 3/2.7070 11CMAZL M ►AYNIF , ?.:0 COMMERCE ORAT NNff v 3TAR7IILD 7%f141 AMACKINZAACfff. IR. FORT 1PtSMiy0%1. P.4� 1>+034 TLUeonLl. 5&- -W-`113 SMJTI IT A 31*UNAN � � "%%Y A. IVLLACK =1t7� C000MAN gNCTNT O. MwNutIZ LIDECCA O ?TURCNIO )AVID M. CRZtN AM13 v. CANFIELD* OF COVN3LL ETCHTrAY FORMULA The decision of the Armed Services Board of Contract Appeals in rich le Coroor on, ASBCA No. 5183, 60 -2 BCA 2688 (1960), $rr•d on recon., affirmed on reconsideration, 61 -1 SCA 26940 established a formula for the calculation of unabsorbed home office overhead, often referred to as "extended overhead." The formula provided the following: I, contract Billings Total °Overhead overhead Total Billings For X for PContr et ° Allocable contraeo Contract Period ZI. Allocable Overhead Days of Performance III. Daily Contract X overhead Daily Contract overhead Number of Amount Days Of Delay Claimed The "Ziehleay formula" was subsequently applied by the boards of contract appeals as a reliable method of calculating the delay damages resulting from extended performance. Unfortunataly, the decision of the Armed Services Board of Contract Appeals in I=v Construe';^^• C= any- Tne., ASBCA Nos. 21218 at al., 80 -1 BCA 14,392 (1980), and the decision of ie General Services Soard'of Contract Appeals in r�ia - S,rMoanv. GSBCA Nos. 5316 at al., 83 -2 BCA 16,548 (1983), threw .the.applieability o! the formula into question- Although the Savoy and ectrie decisions were subsequently reversed by the United States court of Appeals for the Federal Circuit, the law has continued to evolva as new rulings are isssied. The Government has - argued that a delay in parformanca ordinarily does not increase the total amount of home office overhead a contractor incurs in connection with a particular of time 'Mahe overhead, theretora, overhead over a r a period extended period of time, is absorbed by other contract work. 33 �o�g to the Government, the Only situation. )AGE which NO. r. A. O PAGE 3 contractor can recover for such extended overhead is where the delay in performance (1) requires the contractor to hire additional home office personnel or incur additional overhead expenses, or (2) prevents the contractor from taking on other work it would have been able to assume had there not been a delay. The united States Court of Appeals for the Federal circuit rejected this argument in capital Electr *_c, and stated, in the concurring opinion, that: Although superficially plausible, the government's argument does not withstand more penetrating analysis based upon the theory on, which extended overhead is allowed as an element of delay damages. By definition, this type of overhead cannot be directly attributed to the performance of a particular contract, yet it is an essential part of the contractor's total cost of doing business. Some basis, therefore, must.be found for allocating this total overhead among the various contracts in connection with which it is incurred. Although there has been .considerable .inconsistency among various federal agencies as to the applicability of Eichleav, it appears that the boards will continue to apply the formula to delays compansable under one of the operative clauses in the . :.contract (i.e. Differing Site Conditions, Changes, Suspension of 'Work). The contractor must prove, however, that there has been a delay caused by the Government, that he has suffered some damages as a result of the delay. and that there is not a more precise method of calculating the extended home office overhead .costs. Subsequent to the reversal of capital Electric and-Savoy by the united States Court of Appeals for the Federal Circuit,. it appeared that the agencies which accepted the Eichleay formula ware applying a two- part'test to determine whether the contractor was entitled to recover under the formula. The test required that the contractor show: (i) That the bonding capacity Of the.company, bad been limited and toally y absorbed by contract work; or (2) That there had been obtain other work which extended overhead. -2- an inability to could absorb the AGENDA ITEM NO_� F •, PAGE % OF Ot (i) That the bonding capacity Of the.company, bad been limited and toally y absorbed by contract work; or (2) That there had been obtain other work which extended overhead. -2- an inability to could absorb the AGENDA ITEM NO_� F •, PAGE % OF $ •:IP. K While a showing that the contractor meets either one of these two tests will still be helpful, it is not yet clear that these are mandatory requirements to entitlement under the Eichleay formula. In fact, the Armed Services Board of Contract Appeals in George E Jensen Contractor. inc., ASBCA No. 297720 85 -1 BCA 179833 (1984), recently stated that: Home office expenses are indirect costs usually allocated to all of the contractor's contracts based upon each contract's incurred direct costs. When a goverment caused delay causes a contractor's direct costs to decline greatly, that contract does not receive its fair share of the fixed hose office expenses. The Eichleay formula is one method approved by boards and courts over a long period of time which corrects this distortion in the allocation of these indirect expenses. In a decision involving the remard:of the Savoy case, the Armed Services Board awarded the contractor $151,135.20 in extended overhead costs. The Board rejected the Government's argument that the application of the formula was unfair in that it did not give proper credit for amounts already paid through the application of overhead percentage rates to direct costs. The Board concluded that a contractor's receipt of a percentage markup on direct costs did not mean that it had been adequately compensated for all of the extended overhead costs incurred. The Board also found that because the delays had occurred sporadically throughout contract performance, the contractor was unable to shift his efforts to other projects. r In recent cases, the various boards have held that before the Eichleay Formula will be applied, the contractor must show only that he suffered damages as a result of .the delay. These damages include loss of bonding capacity with the concurrent inability to obtain new work, a drop in revenues due to delays, or stand -by costs incurred during the delay. Ricway. ire., ASBCA No. 29983, 86 -2 BCA 18,841 (1986); P3t2+.i+an Construction GSBCA NO. 7343, 85 -2 BCA 18,897 (1985): Stenhenson Associates, GSBCA NO. 6573, 6815, 86 -3 BCA 19,071 (1986); R.G. ;%er Co o-a" on, Xng BCA No. 4885, 85 -3 SCA 19,012 (1985). In view of the decisions outlined above, the government cannot successfully argue that the Eichleay formula has been rejected and does not apply to delay situations. Although the application of the formula.may have been narrowed somewhat by recent decisions, the Eichleay formula should continua to be 71 '.. -3- AGENDA ITEM fd0. 3 PAGE, OF i considered a reliable method of calculating extended home office overhead delay damages. We have attached copies of the most important decisions regarding the Eichleay formula, together with several articles of interest. This information is arranged chronologically and will provide the reader with a history, of the arguments and the most recent interpretations of the law. The applicability of the after a n uevaluation delay can case. In applying the formula, it is important to be consistent in your figures and the time periods used. You must use the contract billings► total billings, and overhead for the same time period, generally the originally specified contract period. If you use an extended contract period (extended by contract modification, not delays) you must use the billings for that period. In the formula, the "days of performance" element must be the same as the time period used for contract /total, billings. By applying the formula properly, you will increase your chances,of avoiding rejection df your claim by a government auditor or negotiator. Please feel free to contact us if you should have any questions? ecisions which affect the p f current statusofrthe Important law. W /cmc August 11 1987 Rssp�ect��f��ul��ly �/ subm4-c- iitted* , �/y" t"r� �V • Michael R. Payne 90 .jam, 3 �;— AGENDA ITEM NO. .lF41 PAGE-2—'OF �.:'..•SFRM �yry - -M . x W considered a reliable method of calculating extended home office overhead delay damages. We have attached copies of the most important decisions regarding the Eichleay formula, together with several articles of interest. This information is arranged chronologically and will provide the reader with a history, of the arguments and the most recent interpretations of the law. The applicability of the after a n uevaluation delay can case. In applying the formula, it is important to be consistent in your figures and the time periods used. You must use the contract billings► total billings, and overhead for the same time period, generally the originally specified contract period. If you use an extended contract period (extended by contract modification, not delays) you must use the billings for that period. In the formula, the "days of performance" element must be the same as the time period used for contract /total, billings. By applying the formula properly, you will increase your chances,of avoiding rejection df your claim by a government auditor or negotiator. Please feel free to contact us if you should have any questions? ecisions which affect the p f current statusofrthe Important law. W /cmc August 11 1987 Rssp�ect��f��ul��ly �/ subm4-c- iitted* , �/y" t"r� �V • Michael R. Payne 90 .jam, 3 �;— AGENDA ITEM NO. .lF41 PAGE-2—'OF �.:'..•SFRM �yry - -M . x