HomeMy WebLinkAbout2009-7-14 Report to RDA Item no. 4 CITY OF �..
LAI(E o LSINOR
REDEVELOPMENT
1" AGENCY
REPORT TO REDEVELOPMENT AGENCY
TO: HONORABLE CHAIRMAN AND MEMBERS OF THE
REDEVELOPMENT AGENCY
FROM: ROBERT A. BRADY
EXECUTIVE DIRECTOR
DATE: JULY 14, 2009
SUBJECT: DOWNTOWN MASTER PLAN
Background
Based on public input received in association with both the Civic Center
Competition and the General Plan Update process, it became evident that a
comprehensive study and plan were needed for the overall Downtown Lake
Elsinore area. The City's Redevelopment Agency subsequently authorized City
Planning Division staff to team with a qualified private consulting firm to prepare
a land use plan and associated development standards for a defined downtown
study area. The area is generally located south of Interstate 15 and north of the
lakefront between Riley Street and Chestnut Street.
The national architecture and planning firm Cooper Carry was selected along
with their various sub - consultants and commenced working on the Downtown
Master Plan project in November 2008. The consultant's initial task was to
become familiar with the myriad of issues associated with the downtown area
and tour the area in order to experience the existing conditions and identify the
various types of constraints and opportunities. The team then obtained input from
City residents and downtown merchants and property owners.
Thursday December 4 and Friday December 5, 2008 — Representatives from the
economic sub - consultant firm of Economic & Planning Systems conducted a
series of interviews at the City Cultural Center with various downtown
stakeholder groups including merchants, local developers and realtors to
ascertain existing economic conditions within the downtown area and the City as
a whole.
Saturday Morning December 6, 2008 — The first interactive public workshop was
conducted at the City Cultural Center. The purpose of the workshop was to
identify the various needs and perceptions associated with the downtown master
plan study area. Moreover, clear goals needed to be formulated.
RDA July 14, 2009 Item No. 4
Page 1 of 6
Downtown Master Plan
July 14, 2009
Page 2 of 6
Some of the main points garnered from the workshop participant's responses
included the following:
• Need for large public area at the lake front.
• Need for a strong downtown connection to the lake.
• Need to improve actual or perceived safety issues
downtown.
• Need to create a civic center in the downtown area.
• Need to "reuse" old buildings downtown.
Workshop participants were also asked to identify the top five investments which
should be made in the downtown area which included the following:
• Pier
• Downtown Street Improvements
• City to Publicly Purchase Land
• Lake Boardwalk
• City Hall
The design team then compiled all the information gathered from their document
review and field research along with the various interviews and workshop input
and commenced drafting a conceptual land use plan for the downtown study
area. Once the land use plan began to take shape, the team's economic sub -
consultants commenced drafting a market study for the downtown area so as to
ensure that the envisioned land use plan was economically viable based on
future anticipated market conditions.
Thursday Evening January 29, 2009 — The second interactive public workshop
was conducted at the City Cultural Center. The main purpose of the workshop
was to unveil the conceptual land use plan to the workshop participants and to
receive additional input on topics that needed further clarification after the first
workshop.
Conceptual Land Use Plan
The main concept of the conceptual land use plan is to reconnect the existing
downtown area with the lakefront to the south. The concept would be achieved
by realigning and extending Main Street directly to the water. Moreover,
Lakeshore Drive would be extended west across the existing drainage channel.
Given the length of Main Street between the 1 -15 freeway and the lake, and the
public's propensity to walk a limited distance, the design team has created five
distinct districts that can be walked in five minutes time. The districts include the
following:
RDA July 14, 2009 Item No. 4
Page 2 of 6
Downtown Master Plan
July 14, 2009
Page 3 of 6
Gateway District — This area is composed of the block between Flint Street and I-
15. The district would consist primarily of office buildings up to six stories tall.
Limited retail space would also be provided to serve the offices.
Garden District — Just south of the Gateway District, the Garden District
envisions primarily residential uses allowing residents to live and shop
downtown. The Main Street frontage is planned to consist of multi - family housing
which appear to be large historic single - family residences with gardens abutting
the roadway. Small retail or office uses could be established on the ground floor
of the residential buildings.
Cultural District — Just north of the Historic District, the conceptual land use plan
recommends diverting Main Street around a circle containing a new public library
and museum, and the historic Armory building creating a unique environment.
The Cultural District also anticipates a performing arts center, which would be
supplemented by mixed -use retail and residential uses.
Historic District — The heart of downtown Lake Elsinore comprises the three block
stretch of Main Street spanning from Heald Avenue to Prospect Street. The
primary intent of the Historic District is to preserve the architectural facades of
the buildings while allowing for the upgrading of the buildings with a mixture of
uses enabling the area to serve as the City's downtown commercial core long
into the future.
Waterfront District — The conceptual land use plan saves the best for last with
significant new investment by the waterfront. Improvements include a City Hall
and Civic Center, other governmental offices, a town square, retail space,
restaurants, and mixed use development with residential above retail. In addition,
the plan envisions an upscale resort hotel adjacent to a new pier on the lake side
of Lakeshore Drive. A large waterfront park is also anticipated which will feature
a variety of active uses and programmed space. Main Street would terminate on
a new pier which would feature a large ferris wheel ride, shops and a restaurant,
as well as stands for temporary uses such as a farmers market and other
ongoing events.
Each of the five proposed districts would have its own specific theme and feel
regarding architectural styles, signage and streetscapes. A series of public open
spaces with public art would be established throughout the various districts. In
addition, several shared public parking structures would be constructed
throughout the downtown area so as to serve the parking needs of the general
public.
The land use plan and the various issues associated with its implementation
have been integrated into a comprehensive Downtown Master Plan document
(See Attachment No. 1). The document serves as a bold methodology for the
long term renewal and revitalization of the City's historic downtown area. An
RDA July 14, 2009 Item No. 4
Page 3of6
Downtown Master Plan
July 14, 2009
Page 4 of 6
integrated process has been utilized to plan and design the land use, urban form,
circulation and infrastructure (both grey and green) to create both a high- density
pedestrian oriented downtown and a robust world class waterfront park and pier.
The plan has the potential to transform the downtown area into a regional
destination with landmarks, land uses and amenities that will create a viable,
livable and memorable place that the citizens of Lake Elsinore will be proud of for
generations to come.
Downtown Master Plan Market Study
Subsequent to the drafting of the Conceptual Land Use Plan, the economic sub -
consultants completed the "Revised Draft Lake Elsinore Downtown Market
Study" (See Attachment No. 3). The study examined the market potential for
residential, retail, office and hotel development within the downtown study area.
The study estimates the following potential real estate absorption rates:
Land Use Demand Through 2013 Demand Through 2035
Residential 120 -200 Units 790 -1,470 Units
Retail 9,000- 13,000 Square Feet 63,000- 95,000 Square Feet
Office 12,000 Square Feet 80,000 Square Feet
Hotel 40 -80 Rooms 150 -300 Rooms
Downtown Code
Upon completion of the Conceptual Land Use Plan, the planning sub - consultant
firm Downtown Solutions also commenced drafting a Downtown Code (See
Attachment No. 2). The code is a hybrid type of regulatory control which blends
conventional zoning, form -based zoning, and municipal (non- zoning) ordinances
to create the customized development standards needed to implement the
Downtown Master Plan. The code serves to address new development on private
property, describes how it will relate to the public realm, regulates permitted
uses, and will include standards for ensuring compatibility of the differing uses in
what is planned to be an urban environment.
Upon adoption, the code will be the single regulatory document for development
within the master plan area. The code will supersede the existing zoning code,
and other development standards and guidelines currently applicable to the
downtown area, although it will make reference to the zoning code wherever
appropriate. Topics addressed in the code include, but are not limited to the
following:
• Provision for appropriate building forms and frontages based on the
specific building typology.
• Provision for reduced parking requirements.
RDA July 14, 2009 Item No. 4
Page 4 of 6
Downtown Master Plan
July 14, 2009
Page 5 of 6
• Provision for specific storefront design parameters dealing with solid to
void ratios, design basics and sign locations.
• Specification of maximum allowable square footages for some ground
floor retail uses.
• Regulation of outdoor dining and how it impacts the pedestrian
environment.
The Downtown Code will also include special provisions designed to ensure that
the goals of the master plan are implemented. The provisions will include the
following:
1. Protection for Non - Conforming Uses and Structures — The code will
provide that existing uses within the master plan boundary may continue
indefinitely and owners will be allowed to make limited additions, remodel
and fully maintain their property during the interim. It will only be when an
owner proposes to put a new development on their property that the code
requirements will apply.
2. Minimum Development Site — In order to ensure that new development
occurs at a scale that will produce the urban environment envisioned in
the master plan, the code will require a minimum of one half acre in order
to provide for development of sufficient scale to support the intensity of
use specified by the FAR's or residential densities of the plan. This
requirement will not be a minimum lot size; it only affects the size of a
single development project, which will usually be achieved by combining
several smaller lots into a building site. This may occur when a single
entity purchases adjacent lots or when adjacent neighboring owners enter
into a partnering agreement.
Improvement Projects and Potential Funding Mechanisms
The Downtown Master Plan serves as a long -term vision document for the
downtown area which could take twenty to thirty years to fully develop based on
future local and national economic conditions. However, there are a few
development projects in the downtown area which are either planned or being
considered that can serve as catalysts to ensure that the momentum of the
master plan does not wane within a short period of time. These projects include
the Pottery Court affordable housing complex to be developed at the southeast
corner of Langstaff and Pottery Streets, and the Business Incubator facility to be
sited across from the existing Cultural Center. In addition, staff continues to
receive inquires about potential private developments on an ongoing basis.
In order to achieve the vision outlined in the master plan document, a variety of
public improvement projects will be required over time including several street
RDA July 14, 2009 Item No. 4
Page 5 of 6
Downtown Master Plan
July 14, 2009
Page 6 of 6
and infrastructure improvement projects which should be considered for future
inclusion in the City's Capital Improvement Program. These projects vary in
complexity and cost. The project consultants have drafted an Improvement
Projects & Potential Funding Mechanism List (See Attachment 4) which outlines
the necessary projects along with potential funding mechanisms. It should be
noted that this list of funding mechanisms is not exhaustive. As each specific
project moves forward, staff will seek additional applicable funding sources
available at that time.
Next Steps in the Process
Staff requests that the Redevelopment Agency identify necessary modifications
to the attached documents or, if comfortable with the approach and documents,
direct staff to incorporate them into the General Plan EIR. Staff will then bring the
entire Downtown Master Plan package before the Planning Commission,
Redevelopment Agency and City Council for final consideration and adoption at
the end of the year along with the General Plan Update, and Housing Element
which will all be integrated into a single Environmental Impact Report.
G
Prepared By: Matthew C. Harris, 14`
Senior Planner
Reviewed By: Tom Weiner,
Acting Director of Com ► nity Development
Approved By: Robert A. Brady, t '
Executive Directo �
1
Attachments
1. Lake Elsinore Downtown Master Plan Document
2. Downtown Code Document
3. Lake Elsinore Downtown Master Plan Revised Draft Market Study
Document
4. Improvement Projects & Potential Funding Mechanisms List
RDA July 14, 2009 Item No. 4
Page 6 of 6