HomeMy WebLinkAboutCity Council Item No. 6C ITY OF
LADELSI110P\_E
DREAM EXTREME-
REPORT TO CITY COUNCIL
TO: HONORABLE MAYOR
AND MEMBERS OF THE CITY COUNCIL
FROM: ROBERT A. BRADY
CITY MANAGER
DATE: JUNE 9, 2009
SUBJECT: CAMPGROUND AND BOAT LAUNCH FACILITY STATUS REPORT
Background
Two separate, but interrelated projects are in the development process for the City's
Campground. The City plans to rehabilitate the dilapidated boat launch facility at the
Campground by providing a new six lane boat ramp, paved parking lot with 270 spaces,
restroom facilities and elevating the site to function at a wide range of Lake levels.
More importantly, the aquatic safety for shoreline users will be greatly improved. The
second project is the transformation of the Campground into a five star RV resort by a
private developer. The City signed an agreement with the private development firm,
Destination RV Resorts, to invest $17- million of improvements in the Campground in
exchange for the long -term (40 -55 year) concession rights. If both the projects are
brought to fruition, then it's estimated more than $25- million will be invested in
improving the City's Campground.
The City received ownership of the 40 year old Campground from the State of California
in 1992. In December 2001, the City entered into a concessions agreement with
Pyramid Enterprises Inc. to manage the Lake Elsinore Campground. The intent of this
agreement was to turnover daily operations and maintenance of the facility to Pyramid
Enterprises. No significant capital improvements were contemplated under this
agreement. However, until the rehabilitation projects are implemented, the
Campground should be maintained by the Concessionaire in the best condition
possible, despite the poor state of the existing infrastructure.
Discussion
The main hurdles for Destination RV Resorts to complete the development have been
past difficulties in securing financing, as well as technical and financing issues related to
relocating the sewer lift station on Riverside Drive. There hasn't been any significant
change in Destination RV Resorts financial status since the March 24 City Council
meeting.
CC June 9, 2009 Item No. 6
Page 1 of 3
Campground & BLF Project Status Report
June 9, 2009
Page 2
This is an exceedingly difficult project to obtain conventional financing, because the City
must always retain ownership of the property. Typically, lenders require the land to be
owned by developers, so that the lender can hold a collateralized interest in the
property. According to the Managing Member of Destination RV Resorts, the Company
has received commitment letters from private investors and is close to obtaining
commercial financing necessary to fund the project. Furthermore, City Staff has been
informed that financing will be forthcoming once the City has awarded the bid for
construction of the Boat Launch Facility Project.
The second development hurdle occurred when Cal -Trans required the project to widen
Hwy -74 and provide a deceleration lane for patrons entering the newly redeveloped
Campground Facility at the intersection of Lincoln Avenue and Hwy -74. This
requirement caused a domino effect that subsequently requires the relocation of
EVMWD's sewer lift station along Hwy -74. Building a new sewer lift station is estimated
to cost $2.5 million. In addition, water and sewer connection fees are estimated at $2.1
million. Destination RV Resorts and their prospective lender claim this is too high a
capital cost and is literally, money down the drain. In late March, EVMWD agreed to
pay its share of the capital cost for a new sewer lift station, equivalent to the off -site
effluent volume.
The City's Boat Launch Facility Improvement Project is nearing completion of the
environmental permitting process. The City received a Clean Water Act 401 Permit
Certification from the Santa Ana Regional Water Quality Control Board on September
24, 2008. Concurrent with this Status Report, City Staff is seeking Council's approval of
a Streambed Alteration Agreement with the California Department of Fish & Game. The
final permit required for the project is a Clean Water Act 404 Permit from the U.S. Army
Corps of Engineers (USACE). City Staff anticipates receiving a Final DRAFT of the
requirements for the "Habitat Mitigation & Monitoring Plan (HMMP)" from the Corps by
the end of next week. If the HMMP requirements are reasonable, then Staff will seek
Cit Council's approval of the property mitigation requirements at the June 23` or July
14 meeting.
Considering that Destination RV Resort's Project has been delayed, the City will need to
fill the void for a number of improvements, which includes re- paving the entrance
roadway, install shoreline visitor safety fencing and sewer conveyance system. The
repaving of the entrance roadway and safety fencing will be fairly easy to incorporated
into the existing Project Plans and Specifications; however, preparing alternative sewer
plans for the new restroom facilities are more technically involved.
Staff reviewed an old (1976) "Sanitary System Site Plan" from the LERA Campground
and correlated all existing above ground infrastructure in the field. It appears an 8 -inch
PVC sewer connection to EVMWD's main line along Riverside Drive remains functional
and currently in use for the Campground RV dump station. City Staff directed the
design engineering firm, Noble Consultants Inc. (NCI), to perform a preliminary analysis,
CC June 9, 2009 Item No. 6
Page 2 of 3
Campground & BLF Project Status Report
June 9, 2009
Page 3
including gravity flow or small lift station (forced main), to direct effluent from the new
restroom facility to the existing sewer line connection. After NCI reviewed and
considered the scope of the sewer system requirements, it was mutually agreed that the
City should contract separately with an engineering firm having specific expertise in the
area of sanitary sewer systems. Subsequently, City Staff has been in discussions with
such an experienced engineering firm, RBF Consulting, and plans to obtain a detailed
proposal in the coming weeks.
Staff intends to discuss past, present and future sewage disposal connections, capacity
and fees with EVMWD, once a preliminary analysis is completed.
Preparing alternative plans and specifications for the sewer system connection for the
new restrooms will be the main obstacle in finalizing the Boat Launch Facility
Improvement Project Plans and Specifications prior to advertising for public bid. Staff's
best estimate is to advertise for public bid in early August 2009.
On March 25 City Staff inspected the Campground and prepared a punch list of
maintenance tasks to be addressed by the Concessionaire in a timely manner to bring
the Campground maintenance into compliance with the concession agreement. The
Concessionaire quickly addressed many of the tasks on the list, as well as other self -
imposed maintenance tasks. City Staff is reasonably satisfied with the response by the
Concessionaire. A few maintenance tasks are recurring and require constant attention,
such as weed trimming. As of this writing, the tasks are scheduled to be fully completed
by June 5th
To put the state of the Campground in perspective, the Concessionaire inherited a 40
year old facility that had been flooded several times in the past. The Campground has
no irrigation system, inadequate restroom & shower facilities, a crumbling road system
and no access to the Lake. The state of disrepair of the underlying infrastructure will
continue to undermine the daily maintenance efforts, profitability and customer
satisfaction.
Fiscal Impact
None related to this Status Report.
Recommendation
Receive and file.
Prepared by: Pat Kilroy
Director of Lake and Aquatic Resources
Approved by: Robert A. Brady i
City Manager t
CC June 9, 2009 Item No. 6
Page 3 of 3